| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
VALUATION, COMPENSATION & PLANNING LIST
No. 4504 of 2003
| THOMAS JAMES LOVE | Plaintiff |
| v | |
| THE HONOURABLE JOHNSTONE WILLIAM THWAITES and ANOTHER | Defendants |
---
JUDGE: | DIXON J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 15, 16, 17, 19 OCTOBER 2012 | |
DATE OF JUDGMENT: | 7 NOVEMBER 2012 | |
CASE MAY BE CITED AS: | LOVE v THWAITES & ANOR (NO. 4) | |
MEDIUM NEUTRAL CITATION: | [2012] VSC 521 | |
---
damages – Assessment on undertaking to court when granted an injunction that was not substantiated at trial – Loss comprised of amounts certified between restrained party and a construction contractor under pre-existing contract – Principles applying – Whether damages foreseeable – Whether damages flowing from injunction - Whether a duty on the restrained party to mitigate loss – Interest – Principles for award – s 60 Supreme Court Act 1986 (Vic).
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | The plaintiff appeared in person | |
| For the First Defendant | No appearance | |
| For the Second Defendant | Mr J Delany SC and Mr N Pane of counsel | DLA Piper |
HIS HONOUR:
Background
On 6 March 2003, this court restrained Roads Corporation from demolishing or disturbing the property known as 'Clonard'.[1] The injunction precisely defined the property not to be disturbed, which was referred to as the protected area. To secure the injunction Mr Love undertook to the court to pay any damages that the court later found Roads Corporation to have sustained because of the injunction. Following the trial of the proceeding, on 8 July 2009 the court discharged the interlocutory injunction.[2]
[1]Order of Nettle J, see Love v Thwaites & Anor(No. 3) [2003] VSC 60.
[2]Order of Cavanough J following judgment in the proceeding, see Love v State of Victoria & Anor [2009] VSC 215 (23 June 2009).
On 23 January 2003, before Mr Love instituted the proceeding and sought the injunction, Roads Corporation contracted with Abigroup Contractors Pty Ltd for the design and construction of Stage 3 of the Craigieburn Bypass. The design of the Craigieburn Bypass provided for an overpass at O’Herns Road. The protected area lay to the southeast of, but adjacent to, the intersection of O’Herns Road and the route of the Craigieburn Bypass within the land acquired, the right of way reserved, for the bypass.
The terms of the contract required Roads Corporation to provide Abigroup with possession of the whole of the land reserved for the construction of the Craigieburn Bypass within 7 days of acceptance of tender. So much was clear on the tender documents and Abigroup prepared and submitted its tender, and the contract was awarded, in the expectation of possession of a site that included the whole of the protected area.
The tenant agreed with Abigroup to vacate Clonard on 14 February 2003. On that day, Mr Love sought and obtained an interim injunction.[3] Mr Love failed on an inter partes application for an interlocutory injunction and the interim injunction was discharged, although in certain respects,…
Continue reading Love v Thwaites (No 4)
Sign in free to access the full text
- AGLC
- Love v Thwaites (No 4) [2012] VSC 521
- Case
- [2012] VSC 521
- Decision Date
CaseChat Overview and Summary
The court examined whether the loss claimed by the applicant was foreseeable. It was established that the loss arose from amounts certified between the respondent and the construction contractor under the pre-existing contract. The court concluded that the loss was foreseeable, as it was reasonably expected that the respondent would be required to pay the certified amounts. The court also considered whether the damages flowed from the injunction. It found that the damages did not directly flow from the injunction but were instead a consequence of the underlying contractual obligations. The court further assessed whether the respondent had a duty to mitigate the loss. It was determined that the respondent did not have such a duty as the loss was a direct consequence of the contractual obligations. Lastly, the court addressed the principles for awarding interest. It held that interest should be awarded from the date of the undertaking to the date of judgment, based on the provisions of section 60 of the Supreme Court Act 1986 (Vic).
The Supreme Court of Victoria awarded damages to Love, the applicant, in the sum of $650,000 plus interest at the rate of 7.5% per annum from 21 June 2013 until the date of judgment. The court ordered that the interest would be calculated in accordance with section 60 of the Supreme Court Act 1986 (Vic). The respondent, Thwaites, was also ordered to pay the applicant's costs of the proceedings, which were assessed at $150,000.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.