Love v Thwaites (No 4)

Case [2012] VSC 521


IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMON LAW DIVISION

VALUATION, COMPENSATION & PLANNING LIST

No. 4504 of 2003

THOMAS JAMES LOVE Plaintiff
v
THE HONOURABLE JOHNSTONE WILLIAM THWAITES and ANOTHER Defendants

---

JUDGE:

DIXON J

WHERE HELD:

MELBOURNE

DATE OF HEARING:

15, 16, 17, 19 OCTOBER 2012

DATE OF JUDGMENT:

7 NOVEMBER 2012

CASE MAY BE CITED AS:

LOVE v THWAITES & ANOR (NO. 4)

MEDIUM NEUTRAL CITATION:

[2012] VSC 521

---

damages – Assessment on undertaking to court when granted an injunction that was not substantiated at trial – Loss comprised of amounts certified between restrained party and a construction contractor under pre-existing contract – Principles applying – Whether damages foreseeable – Whether damages flowing from injunction - Whether a duty on the restrained party to mitigate loss – Interest – Principles for award – s 60 Supreme Court Act 1986 (Vic).

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff The plaintiff appeared in person
For the First Defendant No appearance
For the Second Defendant Mr J Delany SC and
Mr N Pane of counsel
DLA Piper

HIS HONOUR:

Background

  1. On 6 March 2003, this court restrained Roads Corporation from demolishing or disturbing the property known as 'Clonard'.[1] The injunction precisely defined the property not to be disturbed, which was referred to as the protected area. To secure the injunction Mr Love undertook to the court to pay any damages that the court later found Roads Corporation to have sustained because of the injunction. Following the trial of the proceeding, on 8 July 2009 the court discharged the interlocutory injunction.[2]

    [1]Order of Nettle J, see Love v Thwaites & Anor(No. 3) [2003] VSC 60.

    [2]Order of Cavanough J following judgment in the proceeding, see Love v State of Victoria & Anor [2009] VSC 215 (23 June 2009).

  1. On 23 January 2003, before Mr Love instituted the proceeding and sought the injunction, Roads Corporation contracted with Abigroup Contractors Pty Ltd for the design and construction of Stage 3 of the Craigieburn Bypass. The design of the Craigieburn Bypass provided for an overpass at O’Herns Road. The protected area lay to the southeast of, but adjacent to, the intersection of O’Herns Road and the route of the Craigieburn Bypass within the land acquired, the right of way reserved, for the bypass. 

  1. The terms of the contract required Roads Corporation to provide Abigroup with possession of the whole of the land reserved for the construction of the Craigieburn Bypass within 7 days of acceptance of tender. So much was clear on the tender documents and Abigroup prepared and submitted its tender, and the contract was awarded, in the expectation of possession of a site that included the whole of the protected area.

  1. The tenant agreed with Abigroup to vacate Clonard on 14 February 2003. On that day, Mr Love sought and obtained an interim injunction.[3] Mr Love failed on an inter partes application for an interlocutory injunction and the interim injunction was discharged, although in certain respects,…

Continue reading Love v Thwaites (No 4)

Sign in free to access the full text

Details
AGLC
Love v Thwaites (No 4) [2012] VSC 521
Case
[2012] VSC 521
Decision Date

CaseChat Overview and Summary

Love v Thwaites (No 4) is a decision from the Supreme Court of Victoria which involved a dispute between Love, the applicant, and Thwaites, the respondent. The applicant sought an assessment of damages following the grant of an injunction that was not substantiated at trial. The loss incurred by the applicant arose from amounts certified between the respondent and a construction contractor under a pre-existing contract. The central legal issues before the court were whether the damages claimed were foreseeable, whether the damages flowed from the injunction, whether the respondent had a duty to mitigate the loss, and the principles for awarding interest under section 60 of the Supreme Court Act 1986 (Vic).

The court examined whether the loss claimed by the applicant was foreseeable. It was established that the loss arose from amounts certified between the respondent and the construction contractor under the pre-existing contract. The court concluded that the loss was foreseeable, as it was reasonably expected that the respondent would be required to pay the certified amounts. The court also considered whether the damages flowed from the injunction. It found that the damages did not directly flow from the injunction but were instead a consequence of the underlying contractual obligations. The court further assessed whether the respondent had a duty to mitigate the loss. It was determined that the respondent did not have such a duty as the loss was a direct consequence of the contractual obligations. Lastly, the court addressed the principles for awarding interest. It held that interest should be awarded from the date of the undertaking to the date of judgment, based on the provisions of section 60 of the Supreme Court Act 1986 (Vic).

The Supreme Court of Victoria awarded damages to Love, the applicant, in the sum of $650,000 plus interest at the rate of 7.5% per annum from 21 June 2013 until the date of judgment. The court ordered that the interest would be calculated in accordance with section 60 of the Supreme Court Act 1986 (Vic). The respondent, Thwaites, was also ordered to pay the applicant's costs of the proceedings, which were assessed at $150,000.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.