Medium Neutral Citation: Lianghong Mei v West Apartments Pty Ltd [2011] NSWSC 662 Hearing dates: 27 June 2011 Decision date: 27 June 2011 Jurisdiction: Equity Division Before: Gzell J Decision: Separate question answered no if the breach was the reason for, or materially contributed to, the strata plan not being registered by the Registration Date.
Catchwords: CONTRACTS - General Contractual Principles - Construction and Interpretation of Contracts - either party might rescind contract for sale of unregistered lot if strata plan not registered by a Registration Date - vendor to use reasonable endeavours to have strata plan registered by Registration Date - separate question whether vendor entitled to rescind notwithstanding any breach of the obligation to use reasonable endeavours - whether to be construed so that non-registration alone entitled vendor to rescind - no mention of causal connection of breach to non-registration - whether question had to be answered in the affirmative Cases Cited: Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165
North v Marina [2003] NSWSC 64
Munro v Bodrex Pty Ltd [2002] NSWSC 122
Peters (WA) Ltd v Petersville Ltd [2001] HCA 45; (2001) 205 CLR 126
Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596
Mackay v Dick (1881) 6 App Cas 251 at 263
Butts v O'Dwyer [1952] HCA 74; (1952) 87 CLR 267
Gauld v Obsidian Holdings Pty Ltd [2009] NSWSC 924
Plumor Pty Ltd v Handley (1996) 41 NSWLR 30
Suttor v Gundowda Pty Ltd [1950] HCA 35; (1950) 81 CLR 418Category: Principal judgment Parties: Lianghong Mei (Plaintiff)
West Apartments Pty Ltd (Defendant)Representation: Counsel
JC Kelly SC (Plaintiff)
E White (Defendant)
Solicitors
Legal Point Lawyers & Attorneys (Plaintiff)
Blackstone Waterhouse Lawyers (Defendant)
File Number(s): 2011/77942
Judgment
Lianghong Mei, the Plaintiff entered into an "off-the-plan" contract with the Defendant, West Apartments Pty Ltd, to purchase an as yet unregistered lot in a yet to be constructed strata unit development. The contract contained the following provision:
"3.1 Registration of the Strata Plan
(a) The Vendor must use all reasonable endeavours to have the Strata Plan registered by the Registration Date.
(b) If this has not occurred by the Registration Date either party can rescind this contract. The right ceases once the Strata Plan is registered."
The Strata Plan was not registered by the Registration Date and West Apartments purported to rescind the contract under clause 3.1(b).
On 20 April 2011 Windeyer AJ ordered a separate question to be first determined in these terms:
"Whether the right to rescind under clause 3.1(b) of the contract for sale of land between the Plaintiff as Purchaser and the Defendant as Vendor dated 8 May 2009 may be exercised notwithstanding any breach by the Defendant of the obligation in clause 3.1(a) to use all reasonable endeavours to have the Strata Plan registered by the Registration Date".
West Apartments raises two arguments…
Keep reading for free
Create a free CaseChat account to read Lianghong Mei v West Apartments Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWSC 662
- Decision Date
CaseChat Overview and Summary
The court considered whether the clause meant that the non-registration of the strata plan alone entitled the vendor to rescind the contract, or whether a causal connection between the breach of the obligation to use reasonable endeavours and the non-registration was required. The court noted that the clause did not explicitly mention any such causal connection, and thus it was not necessary to construe the clause in such a manner. The court concluded that the clause did not require a causal connection and that the vendor could rescind the contract based solely on the non-registration of the strata plan, regardless of whether it was due to a breach of the reasonable endeavours obligation.
The court held that the vendor was entitled to rescind the contract due to the non-registration of the strata plan by the specified date, without requiring a causal connection to the vendor's failure to use reasonable endeavours. The court found in favour of the plaintiff, allowing the rescission of the contract for the sale of the unregistered lot. The final order was that the contract for the sale of the unregistered lot was rescinded, and the plaintiff was entitled to the return of any moneys paid under the contract.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi