Lend Lease (Millers Point) Pty Ltd v Barangaroo Delivery Authority

Link copied
Case Copied 79 min read

Supreme Court


New South Wales

Medium Neutral Citation: Lend Lease (Millers Point) Pty Limited v Barangaroo Delivery Authority [2013] NSWSC 1848
Hearing dates:27, 28 March and 24 May 2013
Decision date: 12 December 2013
Jurisdiction:Equity Division
Before: Lindsay J
Decision:

Subject to allowing the parties an opportunity to make submissions as to the form of the orders to be made in disposition of the proceedings, the Court proposes to declare that, upon the proper construction of the Project Development Agreement for the Barangaroo Project, an Approved Valuer making a determination of the Current Market Value for the grant of a Lease of the Premises on which the proposed buildings C4 and C5 are to be constructed (for the purpose of clause 1.2 of Schedule 3 to the PDA) is not entitled to input as cash inflows, in performing a discounted cash flow valuation for the purpose of paragraph (g) of the definition of Current Market Value in clause 1.1 of PDA Schedule 3, those cash contributions paid before Practical Completion to the Developer (by the Nominee nominated by the Developer to accept a Call Offer) respectively referred to in clause 18 of the C4 Agreement and clause 19 of the C5 Agreement.

Catchwords: CONTRACT - Construction - Dispute resolution clauses - Expert Valuation - Dispute about terms of instructions to Valuers - Declarations sought as to proper construction of contract - Declaratory relief available
REMEDIES - Declarations - Declarations without consequential relief - Construction of contract - Commercial contract - Dispute resolution clauses - Declarations granted in aid of contractual dispute resolution procedure
Legislation Cited: Barangaroo Delivery Authority Act 2009 NSW
Court Suppression and Non-Publication Orders Act 2010 NSW
Government Information (Public Access) Act 2009 NSW
Supreme Court Act 1970 NSW
Valuers Act 2003 NSW
Cases Cited: AG Robertson Limited v Valuer-General (1952) 8 LGR (NSW) 261 at 262
Albany v Commonwealth (1976) 60 LGRA 287 at 293-294
Australian Broadcasting Commission v Australasian Performing Right Association Limited (1973) 129 CLR 99 at 109
Australian Provincial Assurance Association Limited v Commissioner of Land Tax [1942] ALR 156 at 158
Blair v Curran (1939) 62 CLR 464 at 531-533, that render them binding on the parties
Boland v Yates Property Corp Pty Limited (1999) 74 ALJR 209 at 268
Codelfa Constructions Pty Limited v State Rail Authority of New South Wales (1982) 149 CLR 337 at 350, 352
Equuscorp Pty Limited v Glengallan Investments Pty Limited (2004) 218 CLR 471 at 483 [34]
Fitzgerald v Masters (1956) 95 CLR 420 at 426-427; 436-438
Hogan v Hinch (2011) 243 CLR 506 at 531 [21])
John Fairfax & Sons Limited v Police Tribunal (NSW) (1986) 5 NSWLR 465 at 476-477
Legal & General Life of Australia Limited v A Hudson Pty Limited (1985) 1 NSWLR 314 at 335D-336B
Pacific Carriers Limited v BNP Paribas (2004) 218 CLR 451 at 461-462 [22]
Royal Botanic Gardens and Domain Trust v South Sydney City Council (2009) 240 CLR 45 at 62-63 [39]
Spencer v The…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lend Lease (Millers Point) Pty Ltd v Barangaroo Delivery Aut... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2013] NSWSC 1848
Decision Date

CaseChat Overview and Summary

Lend Lease (Millers Point) Pty Ltd and Barangaroo Delivery Authority were involved in a dispute concerning the interpretation of the terms of a construction contract. The case was heard in the Supreme Court of New South Wales. The plaintiffs, Lend Lease, sought declarations regarding the correct construction of certain terms in the construction contract, specifically focusing on the definition of "Current Market Value" and the extent to which certain cash contributions should be considered in the valuation process. The Barangaroo Delivery Authority, the defendant, argued for a different interpretation of these terms.

The court had to determine whether the definition of "Current Market Value" in the contract allowed for the inclusion of cash contributions received by the plaintiffs as part of the valuation process. The plaintiffs argued that the valuers could consider the cash contributions but not as part of the internal rate of return (IRR) calculation. The defendant, on the other hand, contended that the cash contributions should be included in the IRR calculation as they were indicative of land values. The court needed to decide on the proper construction of the contract, particularly in relation to the valuation process outlined in the contract.

In its decision, the court found that the definition of "Current Market Value" did permit the valuers to consider the cash contributions received by the plaintiffs, but only to the extent that these contributions were indicative of land values. The court held that the cash contributions should not be included in the IRR calculation as they were not indicative of the presumptive profitability of the project but rather were driven by the plaintiffs' funding arrangements. The court emphasised that the valuation process should be unaffected by decisions about financing arrangements. The court granted the declarations sought by the plaintiffs, clarifying the proper construction of the contract terms in question.

The court's final order was that the Approved Valuers may consider the C4 Agreement and the amounts paid under clause 18 of that Agreement but not as inputs in the IRR calculation. The court clarified that the valuation process should not be influenced by the plaintiffs' funding decisions.

Background

Background to the litigation

Decision

Reasons for decision

On the proper construction of the PDA, the definition of "Current Market Value" in PDA Schedule 3 does not require (but, subject to qualifications addressed in these Reasons for Judgment, permits) an Approved Valuer, when assessing the Current Market Value for the premises for the C4 Building, to take into account an allowance for some part of the cash contributions received by the first plaintiff as Developer under clause 18 of the C4 Agreement. On the proper construction of the definition of "Current Market Value" in PDA Schedule 3, an Approved Valuer is permitted to take into account the cash contributions received by the first plaintiff under clause 18 of the C4 Agreement to the extent that those payments: Characterisation of part of the moneys periodically paid to the first plaintiff under clause 18 of the C4 Agreement as referable, in substance, to a payment on account of acquisition of an interest in land owned by the defendant (and hence indicative of land values) involves an evaluative process which the PDA contemplates will be conducted by one or more Approved Valuers leading, in the case of dispute, to an outcome determined by PDA Schedule 3 clause 1.2. This is consistent with the assumption for which paragraph (g) of the definition of "Current Market Value" However, the expression "a pre-financing (ungeared) project IRR" in paragraph (g), read with the worked example in PDA annexure W, is, on the proper construction of the PDA, intended to encapsulate the idea that the valuation exercise for which PDA Schedule 3 clause 1.2 provides is to result in a determination of "value" not affected by decisions that may have been made by the plaintiffs about how construction of a building is to be financed, whether by debt or equity financing. The words "pre-financing" and "ungeared" jointly and severally point in that direction, elliptical though they are. PDA annexure W is to the same effect. The fact that the subject matter of paragraph (f) is an "entitlement" attributed to the hypothetical Purchaser and going to the presumptive profitability of the project reinforces the same conclusion, and tends against factoring into a mathematical IRR calculation cash flows which, though they may bear upon market conditions, are driven by the plaintiffs' funding arrangements. This is reinforced by the assumption for which paragraph (c) of the definition provides, reading it (as I have determined it must be read) as providing that the hypothetical Purchaser is to be taken not to have incurred funding costs before the grant of a Lease The funding cash flows of the Purchaser (and, for completeness, it must be said, those of the first plaintiff as Developer) are to be ignored in determining Current Market Value. The plaintiffs contend (and I agree) that the Approved Valuers may have regard to the C4 Agreement and the amounts paid under clause 18 of that Agreement, but not, as the defendant would have it, as moneys required to be used as inputs in the IRR calculation contemplated, by paragraph (g) of the definition of Current Market Value, as indicative of an assumed entitlement of the hypothetical Purchaser.

Ratio Decidendi

Legal principle established