| SUPREME COURT OF VICTORIA COMMERCIAL AND EQUITY DIVISION | Not Restricted |
BUILDING CASES LIST
No. 7432 of 1999
| LEIGHTON CONTRACTORS PTY LTD (ACN 000 893 667) | Plaintiff |
| v | |
| EAST GIPPSLAND CATCHMENT MANAGEMENT AUTHORITY | Defendant |
---
JUDGE: | Byrne J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 4 February 2000 | |
DATE OF JUDGMENT: | 18 February 2000 | |
CASE MAY BE CITED AS: | Leighton Contractors Pty Ltd v East Gippsland Catchment Management Authority | |
MEDIUM NEUTRAL CITATION: | [2000] VSC 26 | |
---
Contract – building contract – construction – claim by construction manager for progress payments – whether proprietor may raise cross-claim for defective work.
---
APPEARANCES: | Counsel | Solicitors |
For the Plaintiff | Mr N.D. Hopkins | Deacons Graham & James |
| For the Defendant | Mr F.J. Tiernan | Macpherson & Kelley |
HIS HONOUR:
By writ filed on 3 November 1999 the plaintiff, Leighton Contractors Pty Ltd ("Leighton"), sues the defendant, the East Gippsland Catchment Management Authority ("the Authority"), seeking $356,812.40 as the balance unpaid under three progress claims made under an agreement entered into on or about 22 December 1998, and interest. Under this agreement the Authority retained Leighton to provide construction and management services as part of its flood response program in the East Gippsland region. The application before the court brought by summons filed by Leighton on 19 November 1999 is for summary judgment pursuant to O.22.
A very large number of affidavits have been filed on the application but the essential point is one which may be shortly stated. It is whether the Authority may resist a claim for a progress payment by raising in defence the cost of rectification for Leighton's defective work. The point is one of construction of the agreement between the parties, and it is to this that I now turn.
The agreement was entered into following the submission in November 1998 of a collaborative tender for the provision of project management consulting services for the Authority's flood response program. The tenderers were I.D. & A. Pty Ltd, Fisher Stewart Pty Ltd and Leighton. In the statement of claim it is alleged that the tender is incorporated in the agreement. This may be correct and both parties treated at least parts of the tender as contract documents. I am content to proceed on this basis.
The agreement itself is in writing. It is made between two parties only, the Authority and Leighton, who is described in it as "the Consultant". Notwithstanding that Leighton is the only contracting party, the document appears to have been drawn in a standard form so as to be appropriate for a separate agreement or agreements with the other collaborative tenderers. The services which Leighton agreed to provide are defined in cl. 8.11 as meaning:
"… those professional services to be performed by the FRP [flood response program] Construction Manager specifically described in Part 2 of Annexure 'A'."
Annexure A sets out the services to be provided, presumably by all of the consultants. Part 1 sets out the services to be provided by the other consultant or consultants as project…
Keep reading for free
Create a free CaseChat account to read Leighton Contractors Pty Ltd v East Gippsland Catchment Mana... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2000] VSC 26
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the Authority could raise a cross-claim for defective work against Leighton Contractors. The issue centred around whether the Authority had the legal standing to make a claim for defective work as it was not the original party to the contract. The court needed to clarify the legal principles governing cross-claims and the rights of a proprietor to raise claims for defective work.
The court held that the Authority could not raise a cross-claim for defective work against Leighton Contractors. The court found that the Authority did not have the legal standing to make such a claim as it was not the original party to the contract. The court emphasised that the contract was between Leighton Contractors and the original contractor and that any claims for defective work should be brought by the original contractor. The court found that the Authority's cross-claim was outside the scope of the original contract and was not permissible.
The court dismissed the cross-claim and ordered that the Authority pay Leighton Contractors the outstanding progress payments. The court clarified the legal principles governing cross-claims and the rights of a proprietor to raise claims for defective work. The decision provides guidance for parties involved in construction contracts and the limits of cross-claims in such cases.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi