Leeward Management Pty Ltd v Noosa Shire Council

Link copied
Case Copied 18 min read

PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND

CITATION:

Leeward Management Pty Ltd v Noosa Shire Council [2023] QPEC 38

PARTIES:

LEEWARD MANAGEMENT PTY LTD ATF LE TRUST TRADING AS PROJECT BA

ABN 12 119 712 501

(appellant)

v

NOOSA SHIRE COUNCIL

(respondent)

FILE NO:

25/2022

DIVISION:

Planning and Environment

PROCEEDING:

Appeal

ORIGINATING COURT:

Planning and Environment Court, Maroochydore

DELIVERED ON:

28 September 2023

DELIVERED AT:

Planning and Environment Court, Maroochydore

HEARING DATE:

11 September 2023

JUDGE:

Long SC DCJ

ORDER:

Appeal allowed, development approval granted, subject to conditions.

CATCHWORDS:

PLANNING AND ENVIRONMENT COURT – APPEAL – Where after the determination of the respondent’s application in pending proceedings, challenging the competency of this appeal and the grant of an extension of time for the filing of the notice of appeal, the respondent concedes that the appeal should be allowed – Where the consequence is the granting of the approval which might have been originally granted by the respondent as assessment manager and including, pursuant to s 54(3) of the Planning Act2016, those functions and powers the respondent would also have as a referral agency – where there remained only dispute in respect of some proposed conditions as to a performance bond and compliance of aspects of building work to the approved plans – observations as to the necessity for discrimination and notation as to those conditions required in respect of the performance of the respondent’s functions and powers as a referral agency and which will bind the function to be performed by the private building certifier in respect of granting any building permit.

PLANNING AND ENVIRONMENT COURT – APPEAL – CONDITIONS – whether a condition requiring a performance bond may be lawfully imposed other than pursuant to s 65(2)(e) of the Planning Act2016. – whether it is demonstrated that proposed conditions are not an unreasonable imposition on, the development

LEGISLATION:

Planning Act 2016 ss 54, 60, 63, 65, 67, 229, sch 1, sch2
Planning and Environment Court Act 2016 s 47
Planning Regulation2017 s 21(4)

CASES:

Leeward Management Pty Ltd v Noosa Shire Council [2022] QPEC 58

Sincere International Group Pty Ltd v Council of the City of GoldCoast [2018] QPEC 53

COUNSEL:

J Timmins for the appellant

S Hedge for the respondent

SOLICITORS:

Project BA for the appellant

Thynne + Macartney Lawyers for the respondent


Introduction

  1. By notice of appeal filed 27 January 2022 the appellant sought to appeal the decision of the respondent, notified to it on 25 November 2021, “to refuse part of the development application on land located at 340 Dath Henderson Road, Cooroy Mountain”. That decision related to a development application involving the removal of part of an existing shed on the property and extensions to be made to two sides of the remaining structure. 

  2. The notice of appeal was initially met by an application in pending proceedings by the respondent seeking to have it struck out as incompetent.  As may be noted from the reasons for the decision delivered on 23…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Leeward Management Pty Ltd v Noosa Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QPEC 38
Decision Date

CaseChat Overview and Summary

Leeward Management Pty Ltd appealed against the Noosa Shire Council's refusal to approve a development application for an extension to an existing building. The Council had raised issues regarding the competency of the appeal and the extension of time for filing the notice of appeal, which it later conceded. The primary dispute centered on the proposed conditions, specifically a performance bond and the compliance of building work with approved plans. The court had to determine whether the conditions were reasonable and whether they could be lawfully imposed.

The court examined whether a performance bond could be required under the Planning Act 2016 beyond section 65(2)(e), and whether the proposed conditions were unreasonable. It found that the proposed condition requiring a performance bond was not unreasonable. However, it concluded that the condition about compliance with approved plans should include the word "generally" and appropriate qualifications regarding strict compliance with other conditions. The court emphasized the importance of the respondent's dual role as both an assessment manager and a referral agency, highlighting the need for clear conditions that bind the private building certifier when issuing any building permits.

The court allowed the appeal and granted the development approval subject to specific conditions. It directed the parties to prepare an agreed draft judgment to reflect these reasons and the conditions. The decision underscored the necessity for clear and precise conditions that address both the assessment manager and referral agency roles, ensuring they are enforceable by the private building certifier.

Orders

Orders of the court

Appeal allowed, development approval granted, subject to conditions.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Accordingly, the appropriate conclusion is that in respect of the proposed Condition 18, it is not demonstrated to be a not unreasonable imposition on the development and for similar reasons, the proposed Condition 4 should include the word “generally” in respect of compliance with the approved plans and an appropriate qualification as to strict compliance with the proposed Conditions 16 and 17.Conclusion It will be necessary for the parties to prepare an agreed draft judgment, to reflect these reasons and so that this appeal is now determined, by the granting of the respondent’s approval of the proposed development. In doing so and in the context of some discussion as to the form of the expression of the conditions attaching to that approval, on the further hearing of this matter, it is necessary to return to the earlier observations as to the basis upon which this matter is before the Court and particularly the understanding that the decision which is now being made is that which was required of the respondent pursuant to s 54(3) and 60(4) of the PA. That is, in particularly understanding that the effect of s 54(3) is not to put aside the role of the respondent as a referral agency but rather to include such functions and powers with those to be performed as assessment manager. As has been noted, the potential importance of this, in the usual circumstances, lies in the determination of the basis upon which decisions, including the imposition of conditions, has been made and in determining who may be respondents and co-respondents to an appeal.[21] Here and as already observed and to the extent that Table 7 might have been engaged to make the respondent the referral agency as well as assessment manager for the building work in the nature of demolition or removal of part of the existing structure, the inclusion of such functions and powers is of no practical significance, because the decision which could the subject of any appeal is that of the respondent as assessment manager and there is no practical consequence of any concurrent engagement of the respondent’s functions and powers as referral agency in respect of its own decision. However and even though it may be thought to be, also in this particular instance, of little or no practical importance, this need not be so in respect of the part of the development in relation to the additional building work and where the respondent’s exercise of functions and powers are those it would have as a referral agency in respect of the assessment to be performed by the appellant as private building certifier, as to any granting of a building permit. Accordingly, the decision should follow a format which would be ordinarily expected and which seeks to identify those conditions which are required, pursuant to the exercise of those referral agency functions and powers, to be imposed in the granting of any such permit.[21]See paragraph [5], above.

Ratio Decidendi

Legal Principle Established