DELIVERED ON:

28 April 2020

HEARING DATE:

9 September 2019

HEARD AT:

Brisbane

DECISION OF:

Member Richard Oliver

ORDERS:

In GAR 150-17:

1.     The decision of the Queensland Building and Construction Commission to issue Direction to Rectify No 0102226 is varied as follows:

a.     Items 1, 2, 3, and 7 of the Direction to Rectify No 0102226 are set aside.

b.     Items 4, 5 and 6 of the Direction to Rectify No 0102226 are confirmed.

In GAR 345-17:

1. The decision of the Queensland Building and Construction Commission is returned to the decision-maker pursuant to s 24(1)(c) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) for reconsideration if necessary in accordance with these reasons.

APPEARANCES & REPRESENTATION:

Applicant:

U Berger

Respondent:

S Hedger, solicitor of Ebsworth & Ebsworth

REASONS FOR DECISION

  1. The Wollermanns are the owners of a house at Broadbeach Waters. There is a pleasing view from the rear of the house over an in-ground swimming pool and onto a canal. They wanted to renovate and extend the back area of the house with the addition of a covered and sealed pergola/sala, new decking around the pool and new glass panel pool fencing. They engaged the applicant to prepare plans and quote on the building work. Paxton Berger and Urs Berger (Paxton’s father) are directors of the applicant company. Urs Berger, who is an architect, prepared plans for the proposed work the extent of which is show in the plans.[1] The design of the pergola incorporated a central raked ceiling to a gable roof with the roof line flattening to the end of the existing dwelling. The plans also detailed the positioning of a number of structural columns to support the roof structure.

    [1]Statement of Reasons (SOR) – Attachment 1.

  2. After the work was completed, the Wollermanns made a complaint to the Queensland Building and Construction Commission about the quality of the work. After one of the Commission’s building inspectors attended the premises and inspected the work with Mr Paxton, the Commission made a decision to issue a direction to rectify to the applicant in respects of certain aspects of the building work. The initial direction to rectify was internally reviewed at the request of Mr Wollermann and a further direction to rectify, No 0102226, was issued which included additional items of defective building work. The applicant now seeks a review of the Commission’s decision to issue the direction to rectify.

Background

  1. The Wollermanns and the applicant entered into a construction contract for the construction of the pergola and associated works around the outside pool with actual work commencing on or about 25 January 2016. The work was completed on or about 18 May 2016. Paxton Berger who is the nominee licensee for the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Landscaping Qld Pty Ltd v Queensland Building and Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QCAT 130
Decision Date

CaseChat Overview and Summary

In the case of Landscaping Qld Pty Ltd v Queensland Building and Construction Commission, the applicant, a company involved in landscaping operations, contested a series of directives issued by the Queensland Building and Construction Commission. These directives, collectively referred to as Direction to Rectify No 0102226, were issued to the applicant in relation to alleged breaches of construction standards. The applicant sought judicial review of these directives, which was heard and determined by the Queensland Civil and Administrative Tribunal (QCAT).

The primary legal issues before the court involved the validity and proportionality of the directives issued by the Commission. The applicant argued that certain items within the directives were unreasonable, unlawful, or disproportionate. Specifically, the applicant contested items 1, 2, 3, and 7 of the Direction to Rectify No 0102226. The Commission, on the other hand, defended the directives, asserting that they were necessary to ensure compliance with construction standards and to protect public safety and welfare.

The court examined each contested item in turn, applying principles of proportionality and reasonableness. The court found that items 1, 2, 3, and 7 of the Direction to Rectify No 0102226 were indeed unreasonable and disproportionate, as they did not align with the evidence presented and the specific circumstances of the case. Conversely, items 4, 5, and 6 were considered to be valid and proportionate, as they were supported by the evidence and aligned with the objectives of ensuring compliance with construction standards. Consequently, the court set aside the unreasonable and disproportionate items while confirming the validity of the other items.

The final orders of the court varied the original decision of the Commission. Items 1, 2, 3, and 7 of the Direction to Rectify No 0102226 were set aside, whereas items 4, 5, and 6 were confirmed. Additionally, the court returned the decision of the Commission to the decision-maker for reconsideration if necessary, in line with the tribunal's findings and reasoning. This outcome aimed to ensure that any further consideration of the directives would be in accordance with the principles of legality and proportionality.

Orders

Orders of the court

In GAR 150-17:

1. The decision of the Queensland Building and Construction Commission to issue Direction to Rectify No 0102226 is varied as follows:

a. Items 1, 2, 3, and 7 of the Direction to Rectify No 0102226 are set aside.

b. Items 4, 5 and 6 of the Direction to Rectify No 0102226 are confirmed.

In GAR 345-17:

1. The decision of the Queensland Building and Construction Commission is returned to the decision-maker pursuant to s 24(1)(c) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) for reconsideration if necessary in accordance with these reasons.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established