SUPREME COURT OF QUEENSLAND
CITATION:
PARTIES:
LANDBANK TINANA PTY LTD (ACN 107 156 972)
(plaintiff)
v
DUDLEY NORMAN McKAY
(first defendant)
KEITH ERIC McKAY
(second defendant)
LEONE MICHELLE KREICBERGS
(third defendant)FILE NO/S:
SC No 6708 of 2004
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court Brisbane
DELIVERED ON:
24 March 2006
DELIVERED AT:
Brisbane
HEARING DATE:
13 March 2006; 14 March 2006; 15 March 2006; 16 March 2006
JUDGE:
de Jersey CJ
ORDER:
1. that the plaintiff’s proceeding be dismissed with costs to be assessed
2. pursuant to s 127 of the Land Title Act 1994, that the plaintiff forthwith secure the removal of caveat number 707910671 over the subject land.CATCHWORDS:
CONVEYANCING – BREACH OF CONTRACT – BREACH BY THE PURCHASER: REMEDIES OF VENDOR – RESCISSION – WHERE TIME OF ESSENCE – contract for the sale of land – contract became unconditional – settlement required by 5pm on 19 July 2004 with time of the essence – plaintiff did not tender the purchase monies in time, and the contract was terminated – validity of termination – disputes over place for and manner of completion – whether vendor’s conduct contributed to purchaser’s inability to complete – unconscionability
Land Title Act 1994 (Qld), s 127
Jeppesons Road Pty Ltd v Di Domenico & Anor (2005) QCA 391; CA No 3521 of 2005, 21 October 2005, cited
Lowe v Evans (1989) 1 Qd R 295, cited
re Ronim Pty Ltd (1999) 2 Qd R 172, cited
Romanos v Pentagold Investment Pty Ltd (2003) 217 CLR 367, cited
Tanwar Enterprises Pty Ltd v Cauchi (2004) 217 CLR 315, citedCOUNSEL:
P L O’Shea SC with J W Peden for the plaintiff
R G Bain QC with C J Conway for the three defendantsSOLICITORS:
Flower & Hart Lawyers for the plaintiff
Griffiths Parry Lawyers for the three defendants
de JERSEY CJ: By a contract dated 26 November 2003, the defendants agreed to sell, and the plaintiff agreed to purchase, land comprising lot 1 on registered plan 173593 in the County of March, Parish of Tinana, situated at 8 and 14 Teddington Road, Maryborough. The purchase price was $800,000. The contract became unconditional, with settlement ultimately being required (after various extensions) between 9am and 5pm on 19 July 2004. When the plaintiff did not tender the balance purchase monies by 5pm that day, the defendants terminated the contract. The plaintiff challenges the validity of that termination, and sues for specific performance.
Findings of fact
The evidence was largely non-contentious. I accepted it save in some respects the evidence of Mr Karavelas, a director of the plaintiff, as indicated in what follows. I will now set out my findings on essential matters.
Terms of contract
The contract provided for payment of deposit monies totalling $75,000. It was subject to Maryborough City Council’s approval of a development application. That approval was forthcoming. As the defendants knew, the plaintiff intended to subdivide the…
Keep reading for free
Create a free CaseChat account to read Landbank Tinana P/L v McKay and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] QSC 55
- Decision Date
CaseChat Overview and Summary
The court found that the purchaser's failure to complete on time was a breach of the contract and that time was of the essence. The court held that the vendor was entitled to terminate the contract and that the vendor's conduct did not contribute to the purchaser's inability to complete. The court also found that there was no unconscionability in the vendor's conduct. The court held that the purchaser's failure to complete on time was a fundamental breach of contract and that the vendor was entitled to terminate the contract and keep the deposit.
Landbank Tinana P/L's proceeding was dismissed with costs to be assessed. Pursuant to section 127 of the Land Title Act 1994, Landbank Tinana P/L was ordered to forthwith secure the removal of caveat number 707910671 over the subject land. The court held that the purchaser's failure to complete on time was a fundamental breach of contract and that the vendor was entitled to terminate the contract and keep the deposit. The court found that the vendor's conduct did not contribute to the purchaser's inability to complete and that there was no unconscionability in the vendor's conduct.
Orders
Orders of the court
1. that the plaintiff’s proceeding be dismissed with costs to be assessed
2. pursuant to s 127 of the Land Title Act 1994, that the plaintiff forthwith secure the removal of caveat number 707910671 over the subject land.
Background
Background to the litigation
The matter was heard in the Supreme Court of Queensland, with the initial proceeding filed by the plaintiff to enforce specific performance of the contract. The defendant filed a counterclaim for rescission of the contract. The matter was heard by the court, which considered the evidence and submissions from both parties. The court dismissed the plaintiff's proceeding and ordered the plaintiff to secure the removal of a caveat over the subject land.
Decision
Reasons for decision
1. Whether the plaintiff's failure to complete the settlement on time justified the defendant's termination of the contract.
2. Whether the defendant's conduct contributed to the plaintiff's inability to complete the settlement on time.
3. Whether the plaintiff's conduct was unconscionable.
Held
1. The court held that the plaintiff's failure to complete the settlement on time justified the defendant's termination of the contract.
2. The court found that the defendant's conduct did not contribute to the plaintiff's inability to complete the settlement on time.
3. The court held that the plaintiff's conduct was not unconscionable.
Ratio Decidendi
Legal Principle Established
The court began by addressing the first issue of whether the plaintiff's failure to complete the settlement on time justified the defendant's termination of the contract. The court noted that the contract specified that time was of the essence and that the settlement was to be completed by 5pm on 19 July 2004. The plaintiff did not complete the settlement on time, and as a result, the defendant had the right to terminate the contract. The court held that the defendant's termination of the contract was valid.
The court then moved to the second issue of whether the defendant's conduct contributed to the plaintiff's inability to complete the settlement on time. The court found that the defendant's conduct did not contribute to the plaintiff's inability to complete the settlement on time. The court held that the plaintiff's failure to complete the settlement on time was due to its own actions and not due to any actions or inactions by the defendant.
Finally, the court addressed the third issue of whether the plaintiff's conduct was unconscionable. The court held that the plaintiff's conduct was not unconscionable. The court found that the plaintiff had acted in good faith and had not engaged in any unconscionable conduct.
The binding legal principle established by this decision is that a vendor may terminate a contract for the sale of land if the purchaser fails to complete the settlement on time and time is of the essence. The court also held that a vendor's conduct does not contribute to a purchaser's inability to complete the settlement on time if the purchaser's failure to complete is due to its own actions and not due to any actions or inactions by the vendor. Finally, the court held that a purchaser's conduct is not unconscionable if it is done in good faith and without any intent to take unfair advantage of the vendor.