| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 5483 of 2000
| WESTKON PRECAST CONCRETE PTY LTD (ACN 006 813 789) | Plaintiff |
| v | |
| MULTIPLEX CONSTRUCTIONS PTY LTD (ACN 008 687 063) | Defendant |
AND BETWEEN
| MULTIPLEX CONSTRUCTIONS PTY LTD and WESTKON PRECAST CONCRETE PTY LTD and GMR AUSTRALIA PTY LTD (IN LIQUIDATION) | Plaintiff by Counterclaim Firstnamed Defendant by Counterclaim Secondnamed Defendant by Counterclaim |
---
JUDGE: | HABERSBERGER J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 13 OCTOBER 2003 | |
DATE OF JUDGMENT: | 17 FEBRUARY 2004 | |
CASE MAY BE CITED AS: | WESTKON PRECAST CONCRETE PTY LTD v MULTIPLEX CONSTRUCTIONS PTY LTD | |
MEDIUM NEUTRAL CITATION: | [2004] VSC 37 | |
---
Practice and Procedure – Appeal from dismissal by Master of application for determination of certain preliminary questions – Whether simply question of construction of indemnity clause in sub-contract or whether factual issues were involved in that determination – Proceeding one of several resulting from collapse of partly built dome causing death and injury to employees of sub-contractor – Contractor's losses not yet ascertained or quantified – Application premature – Procedure for determination of all outstanding proceedings to be considered together at the one directions hearing – Supreme Court (General Civil Procedure) Rules 1996 r.47.04.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Dr D.J. Neal | Nathan Kuperholz |
| For the Defendant | Mr T.J. Margetts | Harwood Andrews |
HIS HONOUR:
This is an appeal from a decision of Master Kings, given on 23 September 2003, dismissing an application by the defendant/plaintiff by counterclaim, Multiplex Constructions Pty Ltd (ACN 008 687 063) ("Multiplex"), for an order that there be a determination of certain preliminary questions pursuant to r.47.04 of the Supreme Court (General Civil Procedure) Rules 1996 ("the Supreme Court Rules").
Background
In order to understand the context in which the issue of preliminary questions arises, it is necessary to set out some of the complicated background to this dispute. In 1997, Multiplex was the principal contractor for the construction of the Broadmeadows Health Service Facility ("the hospital"). The plaintiff/first defendant by counterclaim, Westkon Precast Concrete Pty Ltd (ACN 006 813 789) ("Westkon"), entered into a sub-contract agreement with Multiplex in July 1997 ("the sub-contract") to construct and install certain precast concrete panels at the hospital, including a concrete dome over the entrance foyer to the hospital. The second defendant by counterclaim, GMR Australia Pty Ltd (In Liquidation) (ACN 057 493 464) ("GMR"), was the engineer retained by Westkon.
On 7 October 1997, during the installation of the 16 concrete segments or panels making up the dome, one of the props supporting one of the panels gave way and the unsupported panel, which weighed approximately four tonnes, collapsed killing a Mr Amadeu Bodas and seriously injuring a Mr Fernando Tavares Coutinho.[1] Both of these men were employed by Westkon.
[1]In the hearing of the appeal, the Master's reasons and the Coroner's decision, this injured employee and his family were referred…
Keep reading for free
Create a free CaseChat account to read Knox City Council v Tulcany Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] VSC 37
- Decision Date
CaseChat Overview and Summary
The legal issues the court needed to address revolved around the nature of the application for a determination of the indemnity clause. Specifically, the court had to decide if the application was merely a question of interpreting the clause or if it involved factual matters that required resolution before any interpretation could be made. Given that the contractor's losses had not yet been ascertained or quantified, the court also needed to consider whether the application was premature. Furthermore, the court had to examine the appropriate procedural steps for handling the determination of all outstanding proceedings.
The court found that the application was not merely a question of interpreting the indemnity clause but also involved factual issues that needed resolution. Consequently, the court held that the application was premature, as the contractor's losses had not yet been quantified. The court further determined that the proper procedure was to consider the determination of all outstanding proceedings together at a single directions hearing, in accordance with the Supreme Court (General Civil Procedure) Rules 1996 r.47.04. This approach ensured that all related issues were addressed in a coordinated manner, avoiding piecemeal litigation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.