QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Kiril Kozulin t/a K & V Plastering v Victoria Gala [2023] QCAT 376
PARTIES:
KIRIL KOZULIN T/A K & V PLASTERING (applicant)
v
VICTORIA GALA (respondent)
APPLICATION NO/S:
BDL034-21
MATTER TYPE:
Building matters
DELIVERED ON:
20 September 2023
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member King-Scott
ORDERS:
The Tribunal directs Victoria Gala pay Kiril Kozulin t/a K & V Plastering the sum of $5,000.00 by 4:00 pm on 20 October 2023.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF
WORK – REMEDIES FOR BREACH OF CONTRACT –
DAMAGES – MEASURE OF – where a builder was
engaged to perform building work – where there was no
contract in writing signed by the parties in breach of s 13(2)
of Sch 1B of the Queensland Building and Construction
Commission Act 1991 (Qld)
IMPLIED AND CONSTRUCTIVE CONTRACTS - NATURE AND GROUNDS OF OBLIGATION - SERVICES RENDERED - WORK AND LABOUR IN GENERAL - QUANTUM MERUIT - where the builder is entitled to claim under quantum meruit – where work defective - where the owner was entitled to recover for damage caused by the builder for defective work.Queensland Building and Construction Commission Act 1991 (Qld)
Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Andrew Shelton & Co Pty Ltd v Alpha Healthcare Ltd (2002) 5 VR 577
Balfour Beatty Power Construction Australia Pty Ltd v Kidston Goldmines Ltd [1989] 2 Qd R 105
Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Background
The Applicant builder, Kiril Kozulin, a plasterer, lived on Russell Island. The homeowner (Victoria Gala) was an owner builder and licensed to build a 2-bedroom house and 28 m2 deck on Russell Island. No written contract was entered into by the parties.
The builder provided a quote for plastering work on 20 January 2020. The quote for $9,779.00 included all transport and delivery costs.
The homeowner paid for the work in two instalments, $5,000.00 on 7 March 2020 and $4,779.00 on 24 April 2020. She had not inspected the work because of Covid restrictions in place at the time. She paid an additional amount of $2,960.70 on 1 May 2020.
A dispute has arisen not in relation to the initial quote which was for $9,779.00 nor for additional variations of $2,960.70 but for a further claim of $11,794.30 for additional work completed by the builder.
The work was completed on 30 April 2020. The progress of the works was interfered with by the Covid restrictions.
The dispute between the parties does not involve monies already paid, although there is a cross claim for defective work. The dispute arises from seven…
Keep reading for free
Create a free CaseChat account to read Kiril Kozulin t/a K & v Plastering v Victoria Gala and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] QCAT 376
- Decision Date
CaseChat Overview and Summary
The legal issues before the Tribunal included whether the contract was valid and enforceable, and if not, whether the builder could claim under quantum meruit for the reasonable value of work done. The Tribunal noted that the contract between the parties was not in writing and signed by both parties as required by s 13(2) of Schedule 1B of the Queensland Building and Construction Commission Act 1991 (Qld). Consequently, the contract was void and unenforceable. However, this did not preclude the builder from claiming for the reasonable value of the work done under quantum meruit.
The Tribunal considered the principles of quantum meruit, which allow for the recovery of the reasonable value of work done when a contract is unenforceable. The builder was entitled to claim for the materials and labour used, including the barge fees and travel time for workers, which were originally included in the quote. However, the Tribunal also noted the homeowner's complaints about the quality of the work and the alleged exaggeration of hours and materials. The Tribunal concluded that the homeowner did not receive the full benefit of the work due to its defective nature. The Tribunal ordered the homeowner to pay the builder the sum of $5,000.00, reflecting the reasonable value of the work performed, reduced by the homeowner's rectification costs.
The Tribunal's decision underscores the importance of adhering to statutory requirements for written contracts in regulated building contracts and the potential remedies available under quantum meruit when such contracts are unenforceable.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi