John Holland Pty Ltd v Construction, Forestry, Mining and Energy Union

Link copied
Case Copied 76 min read

FEDERAL COURT OF AUSTRALIA

John Holland Pty Ltd v Construction, Forestry, Mining and Energy Union
[2011] FCA 770

Citation: John Holland Pty Ltd v Construction, Forestry, Mining and Energy Union [2011] FCA 770
Parties: JOHN HOLLAND PTY LTD (ACN 004 282 268) v CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION, THE COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA, AUTOMOTIVE, FOOD METALS, ENGINEERING, PRINTING AND KINDRED INDUSTRIES UNION, AUSTRALIAN WORKERS UNION and AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER (Intervener)
File number(s): QUD 63 of 2009
Judge: GREENWOOD J
Date of judgment: 8 July 2011
Catchwords: INDUSTRIAL LAW – consideration of whether the respondents engaged in conduct in contravention of s 767 and s 768 of the Workplace Relations Act (1996) (Cth)
Legislation: Workplace Relations Act (1996) (Cth): ss 767(1), 768(1) and (2), 736, 760, 763
Cases cited: Construction, Forestry, Mining and Energy Union v John Holland Pty Ltd [2010] FCAFC 90 – cited and quoted
John Holland Pty Ltd v Construction Forestry Mining and Electrical Union [2009] FCA 786 - cited
John Holland Pty Ltd v Construction Forestry Mining and Electrical Union (No. 2) [2009] FCA 865 - cited
John Holland Pty Ltd v Construction Forestry Mining and Electrical Union [2010] FCA 834 - cited
Pine v Doyle [2005] FCA 977; (2005) 143 IR 98 – cited and quoted
Schubert v Lee (1946) 71 CLR 589 - cited
Leonard v Morris (1975) 10 SASR 528 - cited
Curran v Thomas Borthwicks & Sons (1990) 26 FCR 241 – cited and quoted
Briginshaw v Briginshaw (1938) 60 CLR 336 – cited
Date of last submissions: 19 November 2010
Place: Brisbane
Division: FAIR WORK DIVISION
Category: Catchwords
Number of paragraphs: 194
Counsel for the Applicant: Mr Hatcher SC and Ms Moody
Solicitor for the Applicant: Herbert Geer Lawyers
Counsel for the First, Second and Third Respondents: Mr Pearce
Solicitor for the First, Second and Third Respondents: Karne Reidy Herd, Solicitors
Counsel for the Intervener: Mr Brady
Solicitor for the Intervener: Norton Rose Australia, Solicitors

IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

FAIR WORK DIVISION

QUD 63 of 2009

BETWEEN:

JOHN HOLLAND PTY LTD (ACN 004 282 268)
Applicant

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First Respondent

THE COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA
Second Respondent

AUTOMOTIVE, FOOD METALS, ENGINEERING, PRINTING AND KINDRED INDUSTRIES UNION
Third Respondent

AUSTRALIAN WORKERS UNION
Fourth Respondent

AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER
Intervener

JUDGE:

GREENWOOD J

DATE OF ORDER:

8 JULY 2011

WHERE MADE:

BRISBANE

THE COURT ORDERS THAT:

1.The applicant’s claims for orders for the imposition of a pecuniary penalty upon the first, second and third respondents in respect of contended contraventions of sections 767 and 768 of the Workplace Relations Act 1996 (Cth) are dismissed.

2.The costs of and incidental to the further consideration of the matters remitted to the primary judge pursuant to the orders of the Court made on 16 July 2010 are reserved.

3.The applicant shall lodge written submissions…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read John Holland Pty Ltd v Construction, Forestry, Mining and En... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] FCA 770
Decision Date

CaseChat Overview and Summary

In the matter of John Holland Pty Ltd v Construction, Forestry, Mining and Energy Union, the Full Court of the Federal Court of Australia considered whether the respondents had engaged in conduct in contravention of sections 767 and 768 of the Workplace Relations Act 1996 (Cth). The dispute centred on the interpretation of the Workplace Expansion Agreement and its applicability to work conducted by John Holland employees at the X50 site. The Unions contended that if the Expansion Agreement applied to the work, then Union officials were not entitled to enter the site under section 760 of the Act for discussions with John Holland employees, as the Agreement did not bind certain unions, leaving no "eligible employees" on site.

The legal issues before the Court included determining whether the Union officials had reasonable grounds to believe that the work was not covered by the Expansion Agreement, and consequently, whether their entry onto the work site was justified under the Act. This required a detailed analysis of the facts and circumstances surrounding the officials' entry on specific dates and the relationship between these facts and the issues outlined in the agreed list of issues. The Court had to decide whether the Union officials' conduct constituted a contravention of sections 767(1) and 768(1) of the Act.

The Full Court found that the Union officials' entry onto the work site was not in contravention of the Act as they had reasonable grounds to believe that the work was not covered by the Expansion Agreement. Consequently, the applicant's claims for pecuniary penalties against the respondents were dismissed. The Court reserved the costs of and incidental to the further consideration of the remitted matters and directed the parties to lodge written submissions on costs within specified timeframes. The disposition of costs would be addressed on the papers unless any party requested an oral hearing.

Orders

Orders of the court

1. The applicant’s claims for orders for the imposition of a pecuniary penalty upon the first, second and third respondents in respect of contended contraventions of sections 767 and 768 of the Workplace Relations Act 1996 (Cth) are dismissed.

2. The costs of and incidental to the further consideration of the matters remitted to the primary judge pursuant to the orders of the Court made on 16 July 2010 are reserved.

3. The applicant shall lodge written submissions (if any) in relation to costs within three weeks.

4. The respondents shall lodge written submissions (if any) in relation to costs within a further three weeks of the receipt of submissions from the applicant.

5. The disposition of costs will be addressed on the papers unless any party wishes to be heard orally in relation to costs.

Note:

Background

Background to the litigation

The case revolves around allegations that the respondents, the Construction, Forestry, Mining and Energy Union (CFMEU), engaged in conduct that contravened sections 767 and 768 of the Workplace Relations Act 1996 (Cth). These sections pertain to the authorisation of entry onto a work site and the requirement for officials of a union to be eligible employees of the employer of the employees at the site. The events leading to the dispute began with the signing of a Workplace Expansion Agreement between John Holland Pty Ltd and certain unions, including the CFMEU. This agreement aimed to cover all work undertaken by John Holland employees at a specified site under a particular expansion program. The Unions accepted that if the agreement applied to work at the X50 site, officials of the Unions would not be entitled to enter the site under section 760 of the Act for the purpose of holding discussions with John Holland employees carrying out that work. However, the issue arose regarding whether the Union officials had reasonable grounds to believe that the agreement did not bind them, leading to their entry onto the site on specific dates.

The matter initially came before the court with claims made by the applicant, John Holland Pty Ltd, against the respondents for alleged contraventions of sections 767 and 768 of the Workplace Relations Act 1996 (Cth). The case was heard in the primary court, where findings were made regarding the conduct of the relevant individuals. The findings were subsequently appealed to the Full Court, which reviewed the evidence and arguments presented. The Full Court made orders that required further consideration of certain matters, leading to the case being remitted back to the primary judge. The primary judgment provided context and background to the issues, and the Full Court's reasons for judgment focused on the factual analysis and the notion that if entry to the work site was not authorised by section 760, no contravention of either section 767(1) or 768(1) could arise if the Union officials had reasonable grounds to believe that the work was not covered.

Decision

Reasons for decision

The principal judgment is to be read in conjunction with these reasons for the purpose of giving context to the issues in controversy, the factual background to all of the matters going to issues 2 and 3 to the extent that those matters give context to a further consideration of other issues and for reference to all definitional terms. Reference will also be made to the principal judgment as the orders of the Full Court require the relevant matters to be further considered in the context of the Full Court’s observations and elements of the previous findings will be examined in the course of these reasons. The findings made in the principal judgment remain on foot unless varied by these reasons and further findings. At [11] of the principal judgment, the position adopted by the Unions as to the relationship between the application of the Expansion Agreement to work on the X50 site and entry by the officials upon the site under s 760 is noted in these terms:11.The Unions accept that if the proper construction of the Workplace Expansion Agreement is that it applies to work undertaken by John Holland employees at the X50 site under the Contract as part of PCQ’s X50 Expansion program, officials of the Unions are not entitled to enter the site in reliance upon s 760 of the Act for the purpose of holding discussions with John Holland employees carrying out that work, as the Agreement, binding upon the AWU, is not binding upon the AMWU, CEPU, ETU or CFMEU and thus there are no “eligible employees” of John Holland on site for the purposes of s 760 of the Act. …The reasons for judgment of the Full Court It should be noted that the factual analysis in the primary judgment of the conduct of the relevant individuals was framed not only by the list of issues but also by reference to the notion that if entry to the work site was not authorised by s 760 of the WR Act (because the Expansion Agreement provided exhaustive coverage of all of the work thus rendering none of Holland’s employees “eligible employees” for the purposes of s 760), no contravention of either ss 767(1) or 768(1) could arise in the event that the Union officials had reasonable grounds to believe that the work was not covered. Thus an analysis was urged upon the Court of the contextual facts and circumstances confronting each of the relevant individuals when electing to enter the work site on 13 February 2009 and 5 March 2009 so as to determine whether (or not) the steps each of them took to enter the site on those days might be regarded as based upon reasonable grounds for believing that the agreement was not binding. The question of whether the individuals held reasonable grounds for believing that the Enterprise Agreement was not binding in relation to work at the X50 site was in controversy on the facts and required dispositive findings by the Court in the context particularly of issues 7, 8 and 9 in the agreed issues list. A determination of that matter also involved the relationship between those issues and issues 4 and 5 in the agreed list of issues.

Ratio Decidendi

Legal Principle Established

The court examined the context of the Unions' entry onto the work site by considering the factual circumstances surrounding the events of 13 February 2009 and 5 March 2009. It was established that if the Unions' entry was not authorised by section 760 of the Workplace Relations Act, then no contravention of sections 767(1) or 768(1) could occur even if the officials had reasonable grounds to believe the agreement was not binding. The court applied the principles of the Act and related authorities to determine whether the officials' entry was authorised and whether they had reasonable grounds for their belief.

The Unions accepted that if the Expansion Agreement applied to the work at the X50 site, then the officials could not enter under section 760 as it would not be binding on all relevant unions. The court noted that the Expansion Agreement provided exhaustive coverage of the work, rendering none of John Holland’s employees “eligible employees” for the purposes of section 760. Therefore, the officials' entry was not authorised.

Regarding the officials' belief that the Enterprise Agreement did not apply, the court found it was not reasonable given the application of the Expansion Agreement. The Unions' position on the relationship between the Expansion Agreement and the officials' entry under section 760 was also considered. The binding principle established is that if an agreement applies exhaustively to the work site, officials are not entitled to enter under section 760 unless there are "eligible employees" present, which was not the case here. The court distinguished between authorised entry under section 760 and entry based on reasonable grounds when no authorisation exists.