John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd (No 2)

Link copied
Case Copied 46 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST

S ECI 2018 00137

JOHN BEEVER (AUST) PTY LIMITED (ACN 006 337 113) Plaintiff
v  
PAPER AUSTRALIA PTY LTD (ACN 061 583 533) Defendant

---

JUDGE:

LYONS J

WHERE HELD:

Melbourne

DATE OF HEARING:

28 November 2018

FURTHER SUBMISSIONS:

15 and 22 March 2019

DATE OF JUDGMENT:

30 August 2019

CASE MAY BE CITED AS:

John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd (No 2)

MEDIUM NEUTRAL CITATION:

[2019] VSC 575

---

BUILDING AND CONSTRUCTION – Interest – Entitlement to interest in period before judgment in proceeding to recovery unpaid portion of undisputed payment claim under s 16(2)(a)(i) of the Building and Construction Industry Security of Payment Act 2002 (Vic) (the ‘Act’) – Whether entitlement to interest pursuant to s 12(2) of the Act or ss 58 or 60 of the Supreme Court Act 1986 (Vic) – Whether entitlement to interest pursuant to s 12(2) of the Act inconsistent with ss 58 and 60 of the Supreme Court Act 1986 (Vic) – Entitlement to interest pursuant to s 12(2) of the Act established – Building and Construction Industry Security of Payment Act 2002 (Vic) ss 9, 12, 14, 15, 16, 23(1)(c), 28I, 28R and 47 – Supreme Court Act 1986 (Vic) ss 58 and 60.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr J A F Twigg QC with
Mr N J Phillpott
Champions Lawyers
For the Defendant  Mr J Gurr Corrs Chambers Westgarth

HIS HONOUR:

Introduction

  1. In this proceeding, I delivered reasons for judgment on 5 March 2018.[1]  I determined that the plaintiff (‘John Beever’) was entitled to summary judgment against the defendant (‘Paper Australia’) for a claim for work done in May 2014 in the sum of $166,229.01 (the ‘May claim’) and for work done in June 2014 in the sum of $185,467.20 (the ‘June claim’), both of which were served on 11 August 2014.  I asked the parties for further submissions on the issues of interest and costs.  These reasons deal with those two issues.

    [1]John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd [2019] VSC 126 (the ‘earlier reasons’). In these reasons, I have adopted the terms defined in the earlier reasons.

  1. For the reasons that follow, I have concluded that:

(1) John Beever is entitled to interest pursuant to s 12(2) of the Building and Construction Industry Security of the Payment Act 2002 (Vic) (the ‘Act’) in relation to the May claim and the June claim from 23 September 2014 until judgment; and

(2)       Paper Australia should pay 75% of John Beever’s costs of this application and of the proceeding on a standard basis.

The interest issue

  1. The issue between the parties is whether pre-judgment interest in respect of a proceeding issued under s 16(2) of the Act is to be calculated in accordance with s 12(2) of the Act or, alternatively, ss 58 or 60 of the Supreme Court Act 1986 (Vic)

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] VSC 575
Decision Date

CaseChat Overview and Summary

The case of John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd (No 2) involved a dispute between two companies in the building and construction industry. The dispute centred around the entitlement to interest on an unpaid portion of a payment claim under the Building and Construction Industry Security of Payment Act 2002 (Vic). The matter was heard in the Supreme Court of Victoria.

The primary legal issue was whether the entitlement to interest was governed by section 12(2) of the Act or sections 58 and 60 of the Supreme Court Act 1986 (Vic). Specifically, the court needed to determine whether the provisions of the Act and the Supreme Court Act were inconsistent and, if so, which provisions should prevail. The court also had to decide whether the applicant was entitled to interest during the period before judgment in the proceeding to recover the unpaid portion of the undisputed payment claim.

In resolving the matter, the court found that the provisions of the Act and the Supreme Court Act were not inconsistent. The court held that the entitlement to interest pursuant to section 12(2) of the Act did not conflict with sections 58 and 60 of the Supreme Court Act. The court further established that the applicant was entitled to interest pursuant to section 12(2) of the Act for the period before judgment in the proceeding to recover the unpaid portion of the undisputed payment claim.

The court's decision clarified the interplay between the Building and Construction Industry Security of Payment Act and the Supreme Court Act in relation to the entitlement to interest. The court's findings ensured that the applicant was appropriately compensated for the delay in payment, and the final orders of the court reflected this outcome.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established