QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Jacques v Lohman & Anor [2019] QCAT 263
PARTIES:
IAN CLARK JACQUES
(applicant)v GRAHAM J LOHMANN
and
MERYL C LOHMANN(respondents)
APPLICATION NO/S:
BDL225-17
MATTER TYPE:
Building matters
DELIVERED ON:
26 August 2019
HEARING DATE:
14 September 2018 and 19 November 2018
HEARD AT:
Brisbane
DECISION OF:
Member Paratz
ORDERS:
Graham J Lohmann and Merrill C Lohmann are to pay the amount of Six Thousand One Hundred and Forty-One Dollars and Sixty-Three Cents ($6,141.63) to Ian Clark Jacques.
CATCHWORDS:
CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – whether the terms of a written contract applied – whether the building contract was a ‘cost plus’ or a ‘lump sum’ contract – where the scope of works was uncertain – where positive and negative variations were considered.
Queensland Building and Construction Commission Act 1991 (Qld), s 77(h)
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 100, s 102Lavish Constructions Pty Ltd v Haywagner Investments Pty Ltd [2017] QCAT 52
Nichols v Earth Spirit Home Pty Ltd [2015] QCA 219
Swindells v Hosking & Anor (No 2) [2012] QDC 17APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
Self-represented
REASONS FOR DECISION
Mr Jacques conducted a domestic building business trading as ‘I and K Construction Solutions’ (‘the builder’). He performed building works for Mr Lohmann and Ms Lohmann (‘the owners’) at their property at 16 Towers Street, Charters Towers, in Queensland.
The works included renovations to an existing house, and work on a new large shed and concrete carport slab and driveway.
The builder claims the amount of $39,310.79 as an amount owing for work performed, together with interest and costs.
The owners counterclaim for a total of $14,865.90 as follows:-
(a)Variations of $6,956.70;
(b)Late completion charges of $2,750.00;
(c)Replacement of vertical blinds of $2,666.00;
(d)Payment for loss of income by Ms Lohmann of $195.00; and
(e)Legal costs of $2,298.20.
The parties initially entered into an HIA ‘Alteration, Addition and Renovation Contract’ dated 21 September 2016. The contract was expressed to be between J and Merrill C Lohmann as owners, and Ian Clark Jacques as building contractor. The contract price (including GST) was $161,595.33.
The owners have paid $145,435.79 to the builder. They have not paid the final stage payment of $16,159.53.
The HIA contract provided for work to start on 31 October 2016 and to reach practical completion within 63 days after commencement. An ‘amended progress payment schedule’ was attached to the contract follows:
Deposit
5%
$8,079.76
Demolition & stripout
30%
$48,478.60
Bathroom installation
25%
$40,398.83
Fix out & kitchen
30%
$48,478.60
Balance & practical completion
10%
$16,159.53
Total
100%
$161,595.32
A ‘Scope of Works’ was attached to the contract. It is relevant to reproduce the whole of that document:
Project: 16 Towers Street Charters Towers
Owners: Graham and Merrill Lohmann
Builder: I & K Jacques Construction Solutions
Licence: 1148100
Project cost: as per contract
Statement of Purpose:-
The purpose of the Scope of Works is the implementation of building works to be carried out…
Keep reading for free
Create a free CaseChat account to read Jacques v Lohman and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QCAT 263
- Decision Date
CaseChat Overview and Summary
The legal issues the court had to determine were whether the terms of the written contract applied and whether the contract was a ‘cost plus’ or a ‘lump sum’ arrangement. The court examined the written contract, the parties' correspondence, and their actions post-contract. The owners argued that the contract was revived, but they could not provide evidence to support this claim. The builder argued that the work was proceeding on a ‘do and charge’ basis, but they also could not provide evidence of the owners' agreement to this. The court had to determine the basis of the contract and whether the builder was entitled to recover for work done under a wholly oral building contract.
The court found that no further written contract was entered into after the initial agreement on 21 September 2016. The parties had further correspondence and discussions regarding the pricing and scope of work, but no clear arrangements were made. The court applied the principles of quantum meruit and unjust enrichment to assess a fair price for the work done by the builder. The court held that the builder was entitled to recover for the work done under the wholly oral building contract, as the failure to put the contract in writing did not render it unenforceable. The court ordered Graham J Lohmann and Merrill C Lohmann to pay the builder the sum of Six Thousand One Hundred and Forty-One Dollars and Sixty-Three Cents ($6,141.63).
Orders
Orders of the court
Graham J Lohmann and Merrill C Lohmann are to pay the amount of Six Thousand One Hundred and Forty-One Dollars and Sixty-Three Cents ($6,141.63) to Ian Clark Jacques.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: GRAHAM J
Full text does not contain this section.