SUPREME COURT OF QUEENSLAND
CITATION:
J M Kelly (Project Builders) Pty Ltd v Toga Development No 31 Pty Ltd (No 5) [2010] QSC 389
PARTIES:
JM KELLY (PROJECT BUILDERS) PTY LTD
(ACN 010 280 142)
(plaintiff)v
TOGA DEVELOPMENT NO 31 PTY LTD
(ACN 103 796 854)
(first defendant)AND
SUTERS ARCHITECTS PTY LTD
(ACN 003 842 635)
(second defendant)AND
GEOFFREY MURPHY
(defendant by counterclaim)FILE NO:
BS3651 of 2006
DIVISION:
Trial Division
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
21 October 2010
DELIVERED AT:
Brisbane
HEARING DATE:
10, 17-21, 24-28, 31 May, 3 June 2010
JUDGE:
Martin J
ORDER:
CLAIM DISMISSED
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – VARIATIONS – where the parties agreed a price for construction – where variations were subsequently entered – where there were substantial changes to the original proposal – whether the contract documents record the true agreement between the parties
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – MATTERS NOT GIVING RISE TO BINDING CONTRACT – VAGUENESS AND UNCERTAINTY – where the parties agreed a price for construction – where variations were subsequently entered – where there were substantial changes to the original proposal – where the first defendant sent the plaintiff a contract-set of documents for signing – where the plaintiff signed and returned only some of the documents and made hand-written insertions on others – where the first defendant then returned a copy of the documents without the hand-written amendments – where the plaintiff signed these documents without checking whether the amendments had been inserted – where the building has been completed – whether a counter-offer was made by the plaintiff – whether the contract was concluded
EQUITY – GENERAL PRINCIPLES – MISTAKE – EQUITABLE REMEDIES – RECTIFICATION – where the parties agreed a price for construction – where variations were subsequently entered – where there were substantial changes to the original proposal – where the first defendant sent the plaintiff a contract-set of documents for signing – where the plaintiff signed and returned only some of the documents and made hand-written insertions on others – where the first defendant then returned a copy of the documents without the hand-written amendments – where the plaintiff signed these documents without checking whether the amendments had been inserted – where the building has been completed – whether the parties had a common intention – whether there was a unilateral mistake
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337
Crane v Hegeman Harris Co Inc [1939] 1 All ER 662
Franklins Pty Ltd v Metcash Trading Ltd (2009) 264 ALR 15
Johnston v Arnaboldi [1990] 2 Qd R 138
Maralinga Pty Ltd v Major Enterprises Pty Ltd (1973) 128 CLR 336
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451
Pukallus v Cameron (1982) 180 CLR 447
Riverlate Properties Pty Ltd v Paul [1975] Ch…
Keep reading for free
Create a free CaseChat account to read J M Kelly (Project Builders) Pty Ltd v Toga Development No 3... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2010] QSC 389
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the contract documents, which were signed by both parties, accurately captured the agreement made between J M Kelly and Toga Development No 31 Pty Ltd. The court also needed to examine if the plaintiff's actions, including signing only some of the documents and making hand-written insertions on others, constituted a counter-offer or if there was a unilateral mistake by the plaintiff. Additionally, the court had to consider the equitable remedy of rectification to address any discrepancies in the contract documents.
The court found that the contract documents did not accurately reflect the true agreement between the parties. The court held that the plaintiff's actions did not constitute a counter-offer and that there was no unilateral mistake. The court further found that the equitable remedy of rectification was not available to the plaintiff as the building had already been completed. Consequently, the claim was dismissed.
Orders
Orders of the court
CLAIM DISMISSED
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi