[2005] QSC 305

SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION

DUTNEY J

No BS7417 of 2005

J J MCDONALD & SONS ENGINEERING PTY LTD Applicant
and
NEIL GALL First Respondent
and
RICS DISPUTE RESOLUTION SERVICE QLD Second Respondent
BN 19467680
and
CEPM PTY LTD Third Respondent
BRISBANE
..DATE 12/10/2005

JUDGMENT
HIS HONOUR: This is an application for judicial review. Two

1

issues were argued before me. First, whether the decision
sought to be reviewed was a decision of an administrative

character made under an enactment. The second concerns the propriety of the decision. The decision maker in this case was an adjudicator appointed under section 23 of the Building

10

and Construction Industry Payments Act 2004.
The Building and Construction Industry Payments Act was
enacted with the expressed object of providing for progress
payments to contractors or, in this case, subcontractors 20
irrespective of the terms of the contracts entered into.
Section 13 of the Act entitles a contractor to progress
payments either in an amount calculated under the contract or,
if not provided for under the contract, at intervals provided
for by the legislation. 30
In this case the contract provides for progress payments at
times referred to in the schedule to the contract. By section
17 of the Act the contractor is entitled to serve a progress
claim on the principal setting out the details of the work and 40
the amount claimed. Under section 18 the principal is
required to respond with a document entitled a "Payment
Schedule" setting out the amount the principal is prepared to
pay.
50

If there is a dispute as to the amount payable the contractor can apply for an adjudication under section 21. That application is made to an authorised nominating authority. That authority then appoints an adjudicator under section 23.

2

JUDGMENT

60

1

The application for the adjudication must provide particulars
of the claim and any submissions in support. When the

adjudicator is appointed the principal has an opportunity to respond to the application for adjudication by providing the adjudicator with a document called an "Adjudication Response".

10

The adjudication response is similar to the application in
that it may contain submissions and supporting material. By
section 24(4) of the Act, however, it cannot include any
reasons for withholding payment unless those reasons have 20
already been included in the payment schedule served on the
claimant.
In considering the respective positions the adjudicator may
only consider the matters specified in section 26(2). These 30
include, by paragraph 9(d), the payment schedule, if any, to
which the application relates together with all submissions
including relevant documentation that may have been properly
made by the respondent in support of that schedule.
40
In this case the progress payment claim was for $175,295.97.
The payment schedule in reply admitted an entitlement to an
amount of $22,222.84. Relevant to this controversy the
payment schedule made the following comment under a heading
"Scheduled Amount":  50

"We have adopted CEPM rates (as supplied in your letter…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read J J McDonald & Sons Engineering Pty Ltd v Rics Dispute Resol... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] QSC 305
Decision Date

CaseChat Overview and Summary

In this judicial review matter, J J McDonald & Sons Engineering Pty Ltd sought to challenge the decision of an adjudicator appointed under section 23 of the Building and Construction Industry Payments Act 2004. The applicant contested the adjudicator's determination that it was not entitled to withhold payment for certain works due to procedural errors in the payment schedule and the adjudicator's finding of an implied contract based on a lump sum offer. The court was required to determine whether the adjudicator's decision was an administrative decision made under an enactment and if any errors in the decision warranted judicial review. The court found that the adjudicator's decision met the criteria for being an administrative decision under the enactment, as it was authorised by the statute and affected the legal rights of the parties. However, the court was not persuaded that any relevant error was demonstrated in the adjudicator's decision, and the application for judicial review was dismissed.

The court held that the adjudicator's decision to exclude the unattached valuation from the adjudication response was a correct interpretation of the Act. While the reference to the unattached valuation in the payment schedule might be debated, whether it was sufficient to introduce a reason for withholding payment was a question of fact. Additionally, the court found that the adjudicator's conclusion of an acceptance by conduct of the respondent's offer of a lump sum price for variations was not plainly wrong, and thus, the application for judicial review was dismissed. The court ordered the first respondent's costs of the application to be assessed on a standard basis.