Medium Neutral Citation: Ireland v Burnett [2019] NSWSC 1501 Hearing dates: 28 October 2019 Date of orders: 28 October 2019 Decision date: 01 November 2019 Jurisdiction: Equity Before: Ward CJ in Eq Decision: (1) Summary judgment be entered for the plaintiffs against the first defendant;
(2) Order that the first defendant take all steps necessary specifically to perform the agreement reached in October 2017 by:
(a) completing within seven days all remaining works necessary for the construction of the Gooseneck trailer and applying within that time for the requisite engineering certificate required for registration of the Gooseneck trailer with Roads and Maritime Services;
(b) within seven days of receipt of the requisite engineering certificate register the Gooseneck trailer for road use by Roads and Maritime Services, such registration to be at the first defendant's cost; and
(c) within one business day of registration of the Gooseneck trailer for road use deliver up or make the Gooseneck trailer available for collection by the plaintiffs (subject only to the tender by the plaintiffs of the sum of $17,600 on collection of the Gooseneck trailer);
(3) Grant liberty to apply on three days' notice;
(4) Stand the matter over for damages to be assessed;
(5) List the matter for directions at 9am on 5 November 2019;
(6) Order the first defendant to pay the plaintiffs' costs of the amended notice of motion on an indemnity basis; otherwise reserve the costs of these proceedings;
(7) Order that these orders be entered forthwith.Catchwords: PRACTICE AND PROCEDURE – application for summary judgment – r 13.1 of the Uniform Civil Procedure Rules 2005 (NSW) – construction and purchase of a horse trailer – summary judgment ordered against the first defendant Legislation Cited: Uniform Civil Procedure Rules 2005 (NSW), r 13.1 Cases Cited: General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125; [1964] HCA 69
Stojanovski v Stojanovski [2018] NSWSC 1967Category: Procedural and other rulings Parties: Corey Dean Ireland (First Plaintiff)
Prudence Jane Ireland (Second Plaintiff)
Gregory Howard Burnett (First Defendant)
Elle Burnett (Second Defendant)Representation: Counsel:
Solicitors:
AD Crossland (Plaintiffs)
J Polese (Defendants)
Foulsham & Geddes (Plaintiffs)
Aqua Law (Defendants)
File Number(s): 2019/00183825 Publication restriction: Nil
Judgment
-
HER HONOUR: This is an application by amended notice of motion filed 22 October 2019 by the plaintiffs seeking summary judgment or, in the alternative, default judgment against the defendants in relation to a claimed contract for the purchase of a horse trailer known as a Gooseneck horse trailer.
Background
-
These proceedings were commenced by statement of claim filed on the 13 June 2019 by the plaintiffs, Mr and Mrs Ireland. The defendants are Mr and Mrs Burnett. The statement of claim pleads the following allegations:
1. The defendants operate a business building and selling custom-made horse floats and trailers;
2. On or about 31 October 2016, the plaintiffs and defendants entered into the following agreement:
(a) The defendants would build a ’1300 x 2400 x 2200…
Continue reading Ireland v Burnett
Sign in free to access the full text
- AGLC
- Ireland v Burnett [2019] NSWSC 1501
- Case
- [2019] NSWSC 1501
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.