Supreme Court
New South Wales
Medium Neutral Citation: Intercon Engineering Pty Ltd v Lend Lease Project Management & Construction (Australia) Pty Ltd; Christopher John Wright v Lend Lease Project Management & Construction (Australia) Pty Ltd [2014] NSWSC 441 Hearing dates: 8 April 2014 Decision date: 16 April 2014 Jurisdiction: Equity Division Before: Ball J Decision: Both proceedings be dismissed.
Catchwords: CONTRACT - construction - whether subcontract incorporated terms of head contract - uncertainty Cases Cited: Austra Tanks Pty Ltd v Running [1982] 2 NSWLR 840
Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd [2014] HCA 7Category: Principal judgment Parties: Intercon Engineering Pty Ltd ACN 084 882 815 (Plaintiff 2013/347434)
Christopher John Wright and Cathy Maree Wright (Plaintiff 2013/347418)
Lend Lease Project Management & Construction (Australia) Pty Ltd (ABN 97 000 098 162) (Defendants)Representation: Counsel:
H F Woods (Plaintiffs)
S Robertson with R E Raffell (Defendants)
Solicitors:
Michael Flaherty (Plaintiffs)
Dibbs Barker (Defendants)
File Number(s): 2013/347434 and 2013/347418 Publication restriction: None
Judgment
Introduction
In July 2007, the defendant in each of the 2 proceedings with which this judgment is concerned, now known as Lend Lease Building Pty Ltd (Lend Lease), entered into a head contract (the Head Contract) with the Commonwealth of Australia, represented by the Department of Defence, for the design, construction, commissioning and qualification of a facility referred to as the "Mulwala Redevelopment Project" (the Project).
In April 2009, the plaintiffs in matter 2013/347418 (Mr and Mrs Wright) entered into 3 subcontracts with Lend Lease to perform certain work in connection with the Project. In August 2009, the plaintiff in matter 2013/347434 (Intercon) entered into a subcontract with Lend Lease also to perform certain work in connection with the Project.
The issue in both proceedings is whether Lend Lease is obliged to release the balance of the retention amounts it continues to hold under each subcontract.
Factual background
Each of the subcontracts is in substantially the same terms. Clause 10.8.1.1(1) of each subcontract entitles Lend Lease to retain from any amount payable under the subcontract an amount determined at the rate, and up to the limit, specified in the appendix to the subcontract. Clause 10.9 of each subcontract provides that, in lieu of the retention referred to in cl 10.8.1.1(1), the subcontractor may provide 2 unconditional banker's undertakings of equal value for a total amount that is equal to the limit of the amount Lend Lease is entitled to retain. Clause 10.10.1 of each subcontract provides:
Upon the later of Substantial Completion and receipt by [Lend Lease] of a written request from the Subcontractor for release of either a banker's undertaking or money retained and subject to Clause 6.9.3, [Lend Lease] must release to the Subcontractor either one banker's undertaking or one half of the money retained under Clause 10.8.1.1(1) as applicable. Upon the later of the making good of defects and other matters not in accordance with the Subcontract, the expiration of the Defects Liability…
Keep reading for free
Create a free CaseChat account to read Intercon Engineering Pty Ltd v Lend Lease Project Management... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NSWSC 441
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining the precise nature of the contractual relationship between Lend Lease and Intercon. Specifically, the court had to decide if the subcontract between the parties included all terms of the head contract, particularly those that would bind Intercon to the terms of the head contract. The central issue was whether such incorporation would create sufficient certainty in the subcontract, or if it would lead to an uncertain and thus unenforceable agreement. The court needed to clarify whether the subcontract could stand independently from the head contract, or if it required the head contract's terms to be explicitly referenced and incorporated.
In resolving the matter, the court examined the language of both the head contract and the subcontract. It found that while the subcontract did not explicitly incorporate all terms of the head contract, the subcontract did implicitly require Intercon to adhere to the head contract's terms. The court held that the subcontract was sufficiently certain, as the head contract's terms were reasonably ascertainable and could be inferred from the nature of the work and the industry practice. The court emphasised that the subcontract's terms, combined with the head contract, created a binding agreement that was not unacceptably uncertain. The appeal was dismissed, affirming the lower court's decision that the subcontract was valid and enforceable as it stood.
The final orders of the court confirmed that the subcontract between Intercon and Lend Lease was valid and enforceable, and that the subcontract did not need to explicitly incorporate the head contract's terms to be certain. The court ruled that the subcontract's terms, coupled with the head contract, provided sufficient certainty and clarity to the agreement. This decision provided clarity for future construction projects involving subcontractors, ensuring that such agreements could be upheld in the absence of explicit incorporation of the head contract's terms.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi