In the Matter of Macquarie Prestige Developments Pty Ltd

Case

[2012] NSWSC 1060

29 August 2012


Supreme Court


New South Wales

Medium Neutral Citation: In the Matter of Macquarie Prestige Developments Pty Ltd [2012] NSWSC 1060
Hearing dates:29 August 2012
Decision date: 29 August 2012
Jurisdiction:Equity Division - Corporations List
Before: Brereton J
Decision:

Order that the creditor's statutory demand be varied pursuant to s 459H(4)

[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]

Catchwords: CORPORATIONS - creditor's statutory demand - application to set aside - Corporations Act s 459G - whether genuine offsetting claim exists - whether sufficient evidence adduced to allow the court to be satisfied as to the amount of the claim
Legislation Cited: (Cth) Corporations Act 2001, s 459G
Cases Cited: Royal Premier Pty Limited v Taleski [2001] WASCA 48
Macleay Nominees Pty Limited v Bell Property East Pty Limited [2001] NSWSC 743
Elm Financial Services Pty Limited v McDougall [2004] NSWSC 560
Grass Manufacturers Pty Limited v Sraennik Pty Limited [2003] NSWSC 95
V & M Davidovic Pty Limited v Professional Services Group trading as Rosier Partners Lawyers [2012] NSWSC 134
Macquarie Prestige Developments Pty Limited v Cavasinni Constructions Pty Limited [2012] NSWSC 778
Endeavour Film Management Pty Limited v Fox Studios Australia Pty Limited [2003] NSWSC 831
Category:Principal judgment
Parties: Macquarie Prestige Developments Pty Limited (Plaintiff)
Cavasinni Constructions Pty Limited (Defendant)
Representation: Counsel:
C P Carter (Plaintiff)
D Nego (Defendant)
Solicitors:
Doyles Construction Lawyers (Plaintiff)
Ghobrial Legal (Defendant)
File Number(s):2012/82664

Judgment (ex tempore)

  1. HIS HONOUR: By originating process filed on 14 March 2012 the plaintiff Macquarie Prestige Developments Pty Limited ("Macquarie") applies pursuant to (Cth) Corporations Act 2001, s 459G, for an order setting aside a creditor's statutory demand served on it by the defendant Cavasinni Constructions Pty Limited ("Cavasinni") on 23 February 2012, which claimed a debt of $115,845.75, described as follows:

The debt arises in connection with the building contract between the creditor and the debtor company in relation to building works carried out by the creditor for the debtor company at 88 Berry Street, North Sydney, and is the amount certified for payment in respect of progress claim number 6.

The issue in dispute is whether the plaintiff has raised a genuine dispute, or offsetting demand, in respect of the whole of the debt.

Background

  1. The plaintiff was the developer, and the defendant was the builder, of a project at 88 Berry Street, North Sydney, under a written building contract between them, clause 20 of which provided that the plaintiff was to ensure that at all times there was a superintendent, and that the superintendent fulfilled all aspects of their role and functions reasonably and in good faith. Under clause 37.1 and item 28 of the contract, the defendant was entitled to make monthly progress claims for payments as the works progressed. Clause 37.2 relevantly provided that the superintendent would, within 14 days, issue a progress certificate evidencing the superintendent's opinion of the moneys due from the plaintiff to the defendant pursuant to each progress claim.

  1. The defendant issued progress claim number 6 on or about 20 December 2012, claiming a sum of $177,613.92. On 19 January 2012, the superintendent, Ms Bridie Gough, issued a progress claim certificate for $115,854.75, and requested provision of an amended tax invoice to reflect the certificate. That amended tax invoice was sent by the defendant on 25 January 2012. On the same day the superintendent sent to the plaintiff a document entitled "Payment Recommendation Certificate" stating:

I have examined the tax invoice number 738 with regards to its accuracy and validity for payment, and certified to the best of my knowledge and belief it is in accordance with the conditions of agreement/contract.
  1. The section 459G affidavit filed and served in support of the present application was affirmed by Ms Gough, who deposes she is the architect, and was initially the superintendent's representative, and later became the superintendent. She does not depose to any error or change of view in relation to the certification of progress claim number 6. There is no evidence that shows any dispute in relation to that amount and that claim. The true case propounded by the plaintiff is not one of a genuine dispute as to the debt itself, but one of an offsetting demand.

The offsetting demand

  1. The plaintiff contends that it has a claim for damages for breach of contract and other related grounds. In Ms Gough's s 459G affidavit, this was summarised as follows:

TERMINATION OF CONTRACT
[68] On 24 February 2012, the Plaintiff instructed its lawyers, Doyles Construction Lawyers, to issue a Notice of Termination on the Defendant...
[69] It is my understanding and belief that the Defendant, having failed to show cause, delayed the project by approximately 13 weeks and performed a significant number of defect works is [sic] in breach of the Contract and has subsequently been terminated effective from 25 February 2012.
DEFECTS EVIDENT AFTER TERMINATION
[70] After termination of the Defendant as the Builder, Growthbuilt Pty Ltd entered into a contract with the Plaintiff on 24 February 2012, to complete the works and rectify the defects performed by the Defendant.
[71] On 29 February 2012, I observed Growthbuilt Pty Ltd commence work on the site.
[72] Since that time Growthbuilt have notified me of various defective works performed by the Defendant which require rectification...
[73] It is my understanding and belief that as a result of the need to rectify those defects Growthbuilt have issued variation orders 1 to 11 in order to perform the rectification works associated with the defective work performed by the Defendant...
DELAY AFTER TERMINATION
[74] It is my understanding and belief that as a result of the variations annexed hereto..., which are ongoing and the need to rectify the defects to mitigate any delay, the project is now and will be further delayed...
[75] On reviewing Growthbuilt's Program for Completion, I noted that the time for completion is now September 2012, some four months after the original completion date...
PROGRESS CLAIM 6 ISSUED BY THE DEFENDANT
[76] On 23 November 2011, the Defendant issued Progress Claim 5...
[77] On 20 December 2011, the Defendant issued Progress Claim 6, the subject of the Plaintiff's Statutory Demand...
[78] In relation to the Subcontractor Statutory Declarations, dated 23 November 2011 and 20 December 2011 respectively, I made enquiries with the Subcontractors of the Defendant. Various Subcontractors engaged by the Defendant notified me that they have not been paid what they are owed by the Defendant.
[79] On or about 20 February 2012 I received various invoices from Subcontractors engaged by the Defendant, which have not been paid for by the Defendant...
  1. It will be seen that that affidavit propounds complaints in respect of defects that became evident after termination, and delay occasioned after termination.

The claim for rectification of defects

  1. So far as the defects are concerned, the affidavit annexes a copy of variation orders 1 through 11 issued by the replacement builder. Of those variations, one - that is to say, variation number 10, in the sum of $2,656.50 - is, on its face, not related to any such defect, but to a new variation with the new builder. The others are, at least sufficiently arguably, related to rectification of defects arising out of issues with the defendant as builder, or the investigation of such defects. Those variations total $88,802.37, and for present purposes I would accept the plaintiff has a genuine offsetting demand for that amount.

The claim for damages for delay

  1. That amount is, of course, less than the $115,854.75 in the statutory demand. The plaintiff contends there is nonetheless an offsetting claim in respect of at least the difference. One way in which that might be put is that, aside from the evidence of damage associated with defects, there is damage associated with delay. It is not difficult for the court to infer that delay in building works will cause damage, either in the nature of lost income, or from use of the property following completion, or from increased holding costs. However, it has repeatedly been held that there must be at least some evidence from which the court can see that the offsetting claim will exceed the amount of the debt the subject of the demand.

  1. In Royal Premier Pty Limited v Taleski [2001] WASCA 48, Ipp J, then speaking for the Full Court of the Supreme Court of Western Australia, said (at [57]):

...[T]here is no evidence of any damages that the appellant might have suffered in consequence of the alleged negligence or misleading or deceptive conduct on the part of the respondent. Of course, at this stage it is not necessary for evidence as to damages to be given in meticulous detail. But there must be at least some material upon which the court can conclude that some damage has been sustained and which will enable the court to make a reasonable assessment as to the amount thereof. In this case, however, there is simply no way of determining whether damage was suffered by the appellant in consequence of the alleged negligence or misleading or deceptive conduct, and there is no evidentiary material from which damage suffered by the appellant can be calculated.
  1. In Macleay Nominees Pty Limited v Bell Property East Pty Limited [2001] NSWSC 743, Palmer J said (at [18]):

In my opinion, a genuine offsetting claim...means a claim on a cause of action advanced in good faith, for an amount claimed in good faith. "Good faith" means arguable on the basis of facts asserted with sufficient particularity to enable the court to determine that the claim is not fanciful. In a claim for unliquidated damages for economic loss, the court will not be able to determine whether the amount claimed is claimed in good faith unless the plaintiff adduces some evidence to show the basis upon which the loss is said to arise and how that loss is calculated. If such evidence is entirely lacking, the court cannot find that there is a genuine offsetting claim...
  1. In Elm Financial Services Pty Limited v McDougall [2004] NSWSC 560, Barrett J, as his Honour then was, said (at [19]):

It is not necessary that the parties seeking to have the statutory demand set aside should particularise the claim to the last dollar and cent. There may be various ways of approaching the issue as to assessment... It is sufficient that there be, on the evidence, a plausible and coherent basis for asserting a claim to a sum which, despite elements of uncertainty, can be seen to be, in any event, greater than the amount of the debt the subject of the statutory demand. Of course, the narrower the margin between the alleged debt and the plaintiff's estimate or initial quantification, the greater will be the need for particularity in assessing the amount of the offsetting claim.
  1. The Plaintiff referred to Grass Manufacturers Pty Limited v Sraennik Pty Limited [2003] NSWSC 95, for the proposition (at [19]) that in claims made by a plaintiff for economic loss, the court would not require a great deal of evidence to quantify with precision the amount claimed by way of set-off. The Plaintiff observed that in that case, it was sufficient evidence to prove loss to the plaintiff of a significant customer whose business was clearly of considerable value, which was arguably far greater than the amount claimed in the statutory demand. Palmer J nonetheless concluded (at [23]):

There is also sufficient particularity in the plaintiff's evidence to support the assertion that the amount of damages for which the defendant could be liable on the cross-claim exceeds the amount of the debt claimed in the invoices the subject of the statutory demand.
  1. Recently, in V & M Davidovic Pty Limited v Professional Services Group trading as Rosier Partners Lawyers [2012] NSWSC 134, Black J, after referring to some of the cases to which I have referred, said (at [22]):

The decisions in Grass Manufacturers v Straennik and Elm Financial Services v McDougall indicate that the material required to quantify an offsetting claim may not need to be substantial but do not suggest that such evidence is not required.

Thus, his Honour concluded that the material filed in respect of the application did not establish a genuine offsetting claim for the reason, inter alia, that there was not sufficient evidence to establish the quantum of the damages claimed, even to the relatively undemanding standard required to establish an offsetting claim.

  1. In the present case, for reasons I have given, there is evidence that establishes the amount of the offsetting claim to the requisite standard, to the extent of about $88,000. But that is not sufficient to exceed the amount of the statutory demand. There is simply no evidence that enables me to conclude, by inference or otherwise, that the plaintiff's offsetting claim for delay may exceed, in value, the difference between $88,000 and $115,000.

The claim based on the related proceedings

  1. The plaintiff also relied on a cross-claim that it had filed in related proceedings between the parties in the Technology and Construction List. After the parties fell into dispute, there were negotiations between them, which resulted in a deed being drafted that, if completed, would have settled the dispute between them. In the related proceedings, the present defendant sues the present plaintiff on the deed, for the amount for which it is said that their disputes were compromised. The present plaintiff disputes that there was a binding and enforceable deed.

  1. In an earlier hearing, I held that that deed and the negotiations that led to it would be admissible in these proceedings, in exception to the without prejudice rule, because it was then the intention of the defendant to assert in these proceedings that, even if there had once been a dispute, there no longer was because it had been compromised [Macquarie Prestige Developments Pty Limited v Cavasinni Constructions Pty Limited [2012] NSWSC 778]. Ultimately, because in the related proceedings the defendant now not only disputes that there ever was a concluded agreement but, alternatively, contends, by a recent amendment, that the defendant ought not be entitled to rely, or ought be estopped from relying, on it even if it were concluded, that argument was not pursued before me.)

  1. By cross-claim in the related proceedings, the present plaintiff claims damages for "work done and expenses incurred as a result of the cross-defendant's breach of contract." In the relief claimed, there is a bare claim for "the minimum sum of $300,000 including GST" on that account. The pleading alleges in paragraph 15 that, as a result of the present defendant's breach of contract, the present plaintiff suffered loss or damage. But the particulars, other than asserting damages for delay, damages for defective work, damages for rectification work, additional costs of finance, interest and costs, does not descend to any quantification of the amount of that claim. There is nothing in that pleading, nor is there anything in the evidence, extensive as it is, adduced before me, to support the sum of $300,000, or to show how it is calculated. As Master Macready, as his Honour then was, said in Endeavour Film Management Pty Limited v Fox Studios Australia Pty Limited [2003] NSWSC 831 (at [13]), annexing a statement of claim to an affidavit in support of an application to set aside a statutory demand does not provide sufficient evidence as to quantum for that purpose.

Other evidence in support of the offsetting claim

  1. In support of the contention that there was a genuine dispute to the extent of the full amount of the debt, I was taken to an affidavit of Gregory Walker affirmed 18 June 2012, which deposed as follows:

[8] The basis upon which I say there is a bona fide and real dispute between the Plaintiff and Cavasinni Constructions Pty Ltd in relation to the alleged debt of $115,845.75 is as follows:
[9] I am aware that the Defendant has commenced proceedings number 2012/157742 in the Technology and Construction List of this Court against the Plaintiff (the Construction List Proceedings).
[10] It is my understanding and belief that the damages sought by the Defendant, in the Construction List Proceedings, relate to and include claims made by it in respect of monies it alleges are owed to it, including progress claim #6 for $115,845.75, which is otherwise identified in the Statutory Demand as the basis for alleging the debt in these proceedings.
[11] The Plaintiff denies any liability to the Defendant in the Construction List Proceedings and is contesting those proceedings.
[12] It is my understanding and belief that the Plaintiff has an offsetting claim against the Defendant for breach of contract in respect of the Project.
[13] It is my understanding and belief that the Plaintiff has an offsetting claim against the Defendant in respect of rectification works for defects notified prior to the termination of the cont[r]act between them.
[14] It is my understanding and belief that the Plaintiff has an offsetting claim against the Defendant in respect of rectification works for defects discovered or identified after termination of the cont[r]act between them.
[15] It is my understanding and belief that the Plaintiff has an offsetting claim against the Defendant for breach of statutory warranties.
[16] It is my understanding and belief that the Plaintiff has an offsetting claim against the Defendant in respect of delay caused on the Project, caused as a result of the defective works performed by the Defendant and delayed progress on the project.
  1. It is self-evident that nothing in that affidavit demonstrates how the offsetting claim is quantified.

  1. I was also taken to the draft deed of settlement, to which I have referred. It was at one stage, I think, faintly suggested that the effect of that was to evidence a bona fide offsetting claim that was additional to the amount of $88,000 comprised by the variations to which I have referred, but I do not think that submission was seriously, if at all, pressed. In any event, on examination of the deed, I do not see how it can be said to illustrate a claim for an amount over and above the $88,000, particularly in the context that the deed takes into account not just progress claim number 6, but various other sums also said to be due to the present defendant.

Conclusions on the offsetting demand

  1. For those reasons, I am satisfied that the plaintiff has an offsetting claim to the extent of $88,802.37 only. The admitted total of the debt for the purposes of section 459H(5) is $115,854.75, and the offsetting total is $88,802.37. The substantiated amount of the demand is therefore $27,052.38.

Costs

  1. The question of costs is not straightforward, as there are competing considerations. First, the plaintiff has had a substantial measure of success in reducing the amount of the demand to some 25 per cent of its original amount. This was not the subject of any offer or concession until the defendant's written submissions, which more or less accepted the inevitability of that outcome; but that was only right on the eve of the trial.

  1. Secondly, the case and the evidence in it was substantially expanded by the tender of evidence of the compromise agreement to which I have referred, and evidence responding to that. Although the defendant contends that, until the recent amendment of the plaintiff's cross-claim in the related proceedings, it had a very strong case in respect of the whole debt, I think I know sufficient from the earlier hearing of the evidence on that question to express the view that I think it very doubtful that the defendant would have succeeded on that basis.

  1. Thirdly, the defendant has succeeded in sustaining the demand, although to a much reduced extent. The practical consequences of that from the point of, in due course, establishing any presumption of insolvency from non-payment, is also quite potentially significant.

  1. Taking into account the relatively minor extent and quantum of the defendant's ultimate success, the substantial success achieved by the plaintiff in reducing the quantum of the demand, and the extension by the defendant of the case to issues which necessarily incurred considerable costs but ultimately proved to be irrelevant, the proper outcome is that there be no order as to costs.

Orders

  1. I make the following orders:

(1)   Order pursuant to section 459H(4), that the creditor's statutory demand dated 23 February 2012 be varied by substituting for the amount of the demand the sum of $27,052.38;

(2)   Declare that the demand has had effect as so varied as from the date on which it was served on the plaintiff, namely 23 February 2012;

(3)   No order as to costs, to the intent that each party bear its own costs of the proceedings.

**********

Decision last updated: 28 September 2012

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

1

Zhang v Metcalf [2020] NSWCA 228
Cases Cited

7

Statutory Material Cited

1