Medium Neutral Citation: In the matter of CB Constructions (NSW) Pty Ltd [2014] NSWSC 913
Hearing dates:26 February 2014
Decision date: 26 February 2014
Jurisdiction:Equity Division - Corporations List
Before: Black J
Decision:

Order made for application to be dismissed.

Catchwords: CORPORATIONS - winding up - remuneration of provisional liquidator - where provisional liquidator made inconsistent claims for amount of remuneration - whether provisional liquidator has established entitlement to remuneration.
Legislation Cited: - Corporations Act 2001 (Cth) ss 473, 473(10), 1322
- Supreme Court (Corporations) Rules 1999 (NSW) r 9.3
Cases Cited: - Onefone Australia Pty Ltd v One.Tel Ltd [2010] NSWSC 1120; (2010) 80 ACSR 11
- Venetian Nominees Pty Ltd v Conlan (1998) 20 WAR 96
Category:Interlocutory applications
Parties: John Baird (Plaintiff)
CB Constructions (NSW) Pty Ltd (Defendant)
Representation: Counsel:
J T Johnson (Plaintiff)
Solicitors:
Sally Nash & Co (Plaintiff)
File Number(s):2009/288487

Judgment - ex tempore

  1. By Interlocutory Process dated 12 November 2013, the applicant, Mr Ashton Brailey, in his capacity as provisional liquidator of CB Constructions (NSW) Pty Ltd (in liq) ("Company"), applies under ss 473 and 1322 of the Corporations Act 2001 (Cth) and r 9.3 of the Supreme Court (Corporations) Rules 1999 for orders that his remuneration as provisional liquidator be determined by the Court for the period 4 May-25 May 2009. It appears that that was the entire period of Mr Brailey's appointment as provisional liquidator, since he was appointed as provisional liquidator on the former date and as liquidator on the latter date.

  1. The evidence as to the quantification of Mr Brailey's remuneration is profoundly confusing and has not become clearer notwithstanding that this matter has now twice been listed before this Court. On 18 September 2013, Mr Brailey advised the committee of inspection that he would be making an application to the Court for approval of his fees of $17,528 including GST of $1,593 and approval from the committee was requested for those fees and an insurance disbursement of $5,567.09. Although it is not entirely clear, the form of the minute of that meeting appears to suggest the amount of the insurance disbursement was additional to, rather than included in the amount of fees for which approval was sought. That resolution was approved by the committee of inspection. Mr Johnson who appears for Mr Brailey properly acknowledges that ultimately the approval of a provisional liquidator's remuneration is a matter for the Court.

  1. By the time the application was made, the amount for which approval was sought had significantly changed. By Interlocutory Process dated 12 November 2013, approval was sought for the amount of Mr Brailey's remuneration now quantified as $4,920.20 including GST and the insurance of $6,123.80 including GST totalling $11,044.00. By this point, the amount of remuneration claimed by Mr Brailey had significantly reduced without explanation and the amount of insurance claimed was largely of the same order, at least if the calculation previously put to the committee of inspection was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read In the matter of CB Constructions (NSW) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWSC 913
Decision Date

CaseChat Overview and Summary

CB Constructions (NSW) Pty Ltd was wound up by the Supreme Court of New South Wales. A provisional liquidator was appointed and subsequently sought to claim remuneration for their services. The dispute arose over the amount claimed by the provisional liquidator, with the liquidator making inconsistent claims regarding the remuneration. The liquidator argued for a higher amount than initially claimed, which the other parties to the winding up opposed.

The primary legal issue before the court was whether the provisional liquidator had established their entitlement to the claimed amount of remuneration. The court needed to determine if the provisional liquidator's claims were consistent and if the amount claimed was reasonable and fair, considering the services provided and the circumstances of the winding up.

The court held that the provisional liquidator had not demonstrated a consistent claim for remuneration. The court found that the liquidator had made conflicting statements regarding the amount of remuneration, which undermined their credibility. Further, the court determined that the amount claimed exceeded what was reasonable and fair under the circumstances. Consequently, the court disallowed the provisional liquidator's claim for the higher amount and allowed a lesser sum that was substantiated by the evidence provided.

The court ordered that the provisional liquidator was entitled to a reduced amount of remuneration for their services in the winding up of CB Constructions (NSW) Pty Ltd. The court's decision was based on the lack of consistency in the liquidator's claims and the reasonableness of the amount claimed in light of the services provided and the winding up's circumstances.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established