DISTRICT COURT OF QUEENSLAND
CITATION:
Ide Enterprises Pty Ltd v Hale’s Engineering Pty Ltd [2015] QDC 98
PARTIES:
IDE ENTERPRISES PTY LTD
ACN 080 450 657
(plaintiff)
and
HALES ENGINEERING PTY LTD
ACN 010 924 731
(defendant)
FILE NO/S:
D23 of 2008
DIVISION:
Civil
PROCEEDING:
Trial
ORIGINATING COURT:
District Court at Bundaberg
DELIVERED ON:
7 May 2015
DELIVERED AT:
District Court at Maroochydore
HEARING DATE:
29 – 31 October 2014
JUDGE:
Long SC, DCJ
CATCHWORDS:
CONTRACT – whether the Court should find a breach of an implied term of an entirely oral contract for the construction of agricultural machinery, through lack of reasonable care and skill in the workmanship of the defendant – whether there was any relevant failure of the plaintiff, to exercise due care and skill in the design of the machinery and amounting to contributory negligence – whether and to what extent the plaintiff has suffered damage and how to measure any such damage – whether there should be an allowance for interest and whether that would be allowed from the date of the accrual of loss
Law Reform Act 1995 s 10(1)
Uniform Civil Procedure Rules 1999 r 159
Foster v AT Brine & Sons Pty Ltd [1972] WAR 157
Hadley v Baxendale (1854) 9 Ex 341
Johnson v Perez (1988) 166 CLR at 351
Knott Investments Pty Ltd & Ors v Fulcher & Ors [2013] QCA 67, [2014] 1 Qd R 21
MBP (SA) Pty Ltd v Gogic (1991) 171 CLR 657
Robinson v Harmon (1848) 1 Ex 850
COUNSEL:
D. Marks for the plaintiff
C. Harding for the defendant
SOLICITORS:
Suthers Lawyers for the plaintiff
Baker O’Brien Toll Solicitors for the defendant
Introduction
In early 2007, the plaintiff acting through its director, Mr Jeff Ide, contracted with the defendant, which acted in that regard through Mr Peter Hale, for the construction of a large piece of agricultural machinery called a “laser bucket”. That contract was not completed and the evidence discloses that the disputes which are the subject of this proceeding arise in regard to the construction, of two substantial components of what would ultimately comprise such a piece of machinery. In due course, it will be necessary to consider different issues as they relate to the construction of those different components in accordance with this contract.
Mr Jeff Ide had sought the construction of the machinery in order to further his business of laser levelling of farming land. It was his aim to incorporate these components into a machine of a type that he was accustomed to using for that purpose, but on a scale that was considerably larger than anything he had experienced using for that purpose. In that sense and as referred to in the evidence, the contract related to a prototype and Mr Ide sought the assistance of the defendant due both…
Keep reading for free
Create a free CaseChat account to read Ide Enterprises Pty Ltd v Hale's Engineering Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2015] QDC 98
- Decision Date
CaseChat Overview and Summary
The court examined the nature of the oral contract and the implied terms therein, considering whether Hale's Engineering had indeed breached any such terms. It also assessed the standard of care and skill expected in the construction of agricultural machinery and whether Hale's Engineering had met these expectations. The court further considered whether Ide Enterprises had exercised due care and skill in the design of the machinery, potentially contributing to any issues that arose. The assessment of damages included determining the extent of the harm suffered by Ide Enterprises and the appropriate measure of those damages. Finally, the court had to decide on the allowance of interest on any awarded damages and, if applicable, the date from which such interest should accrue.
In its reasoning, the court found that Hale's Engineering had breached the implied term of the oral contract by failing to exercise reasonable care and skill in the workmanship of the machinery. The court determined that Ide Enterprises had not contributed to the issue through any failure in the design of the machinery. The court assessed the damages suffered by Ide Enterprises and concluded that they were entitled to compensation. The court allowed interest on the awarded damages from the date of the accrual of loss. The final orders of the court included a finding of liability on the part of Hale's Engineering, a determination of the amount of damages owed to Ide Enterprises, and an allowance for interest on those damages.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi