Hutchison 3G Pty Ltd v City of Mitcham & Ors

Link copied
Case Copied 26 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court)

HUTCHISON 3G AUSTRALIA PTY LTD v CITY OF MITCHAM & ORS

Judgment of The Full Court

(The Honourable Justice Besanko, The Honourable Justice Anderson and The Honourable Justice Layton)

5 July 2005

ENVIRONMENT AND PLANNING - BUILDING CONTROL - COUNCIL CONSENT AND APPROVAL - MATTERS FOR CONSIDERATION BY COUNCIL

Appeal against orders of the full bench of the Environment, Resources and Development Court - appeal on a question of law - whether the Court erred in its interpretation of certain Objectives and Principles of Development Control in the Development Plan dealing in particular with the need for a telecommunications facility and its effect on visual amenity - whether the Court erred in failing to give sufficient reasons in support of its conclusions - appeal dismissed.

Environment, Resources and Development Court Act 1993 s 30; Telecommunications Act 1997 s 56; Telecommunications Code of Practice 1997; Telecommunications (Low-impact Facilities) Determination 1997; Development Act 1993 .; Heritage Act 1993 ., referred to.
City of Burnside & Ors v City Apartments Pty Ltd [2004] SASC 294, considered.

HUTCHISON 3G AUSTRALIA PTY LTD v CITY OF MITCHAM & ORS
[2005] SASC 249

Full Court:  Besanko, Anderson & Layton JJ

  1. BESANKO J:       This is an appeal against an order made by the Environment, Resources and Development Court (“ERD Court”).  The appeal lies to the Full Court of this Court because the order was made by a full bench of the ERD Court and the appeal is limited to an appeal on a question of law because no leave has been sought to appeal on a question of fact (s 30(1) and (2) of the Environment, Resources and Development Court Act 1993).

  2. The appellant is Hutchison 3G Australia Pty Limited and it made an application to the first respondent, City of Mitcham (“the council”), for provisional development plan consent in relation to a proposed development.  The application was refused and the appellant appealed against the decision of the council to the ERD Court.  The second respondents, Mr and Mrs Stokes, lodged representations with the council and they were joined as parties to the appeal.  The ERD Court dismissed the appeal and the appellant appeals to this Court.

    The facts

  3. The University of Adelaide owns land off Hartley Grove in the suburb of Urrbrae. Hutchison 3G Australia Pty Limited is a member of the Hutchison Whampoa group of companies. The appellant holds a carrier licence under s 56(1) of the Telecommunications Act 1997.  It sought to undertake development on the land owned by the University.  The proposed development consists of the erection and construction of the following:

    1A single 25 metre high steel monopole.

    2Three panel antennae (each 1.95 metres in length and light grey in colour) installed at the top of the new pole in a turret formation.

    3A single, 300 mm diameter parabolic transmission antenna mounted on the new pole at the 18 metre high level.

    4A new equipment shelter (3.0 mL x 2.5mW x 3.0…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hutchison 3G Pty Ltd v City of Mitcham & Ors and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2005] SASC 249
Decision Date

CaseChat Overview and Summary

In this appeal, Hutchison 3G Australia Pty Limited sought to challenge the decision of the City of Mitcham to refuse their application for provisional development plan consent in relation to a proposed telecommunications facility. The respondents to the appeal were the City of Mitcham and Mr and Mrs Stokes, who had lodged representations with the council. The appellant's application was dismissed by the Environment, Resources and Development Court and they now appeal to this Court. The central issue before the Court was whether the ERD Court had erred in its interpretation of certain Objectives and Principles of Development Control in the Development Plan. Specifically, the appellant argued that the Court had not properly considered the need for the telecommunications facility and its effect on visual amenity. The Court also had to determine whether the ERD Court had failed to give sufficient reasons in support of its conclusions.

The Court found that the ERD Court had correctly interpreted and applied the relevant provisions of the Development Plan. The Court gave careful consideration to the effect of the proposed tower on visual amenity, the community need for the facility, and the other options available to the appellant. In light of these factors, the Court concluded that provisional development plan consent should be refused. The Court held that this was a quintessentially a planning judgment, and there was no warrant for this Court to interfere with that judgment. The appeal was therefore dismissed.

The Court found that the ERD Court had not erred in its interpretation of the Development Plan and had provided sufficient reasons in support of its conclusions. The Court held that the appellant had not demonstrated that the ERD Court had made any error of law in refusing the application for provisional development plan consent.

The final orders of the Court were that the appeal be dismissed, and the appellant pay the costs of the respondents.

Orders

Orders of the court

Background

Background to the litigation

The appellant is Hutchison 3G Australia Pty Limited and it made an application to the first respondent, City of Mitcham (“the council”), for provisional development plan consent in relation to a proposed development. The application was refused and the appellant appealed against the decision of the council to the ERD Court. The second respondents, Mr and Mrs Stokes, lodged representations with the council and they were joined as parties to the appeal. The ERD Court dismissed the appeal and the appellant appeals to this Court.The facts The University of Adelaide owns land off Hartley Grove in the suburb of Urrbrae. Hutchison 3G Australia Pty Limited is a member of the Hutchison Whampoa group of companies. The appellant holds a carrier licence under s 56(1) of the Telecommunications Act 1997. It sought to undertake development on the land owned by the University. The proposed development consists of the erection and construction of the following:1A single 25 metre high steel monopole.2Three panel antennae (each 1.95 metres in length and light grey in colour) installed at the top of the new pole in a turret formation.3A single, 300 mm diameter parabolic transmission antenna mounted on the new pole at the 18 metre high level.4A new equipment shelter (3.0 mL x 2.5mW x 3.0 mH) installed at the base of the tower.5The replacement of the existing compound fence with a new 2.7 metre high security fence, surrounding the proposed facility. It is proposed that the appellant will enter into a lease with the University. The proposed development is to form part of a new service provided by the appellant and referred to by the ERD Court as the 3G network. The 3G network was launched in Adelaide on 1st July 2003. The ERD Court described the new service in the following terms:The 3G network is a high-speed wire free data network which presently operates in Australia in and around Perth, Adelaide, Melbourne, Sydney and Brisbane. Customers of Hutchison can, through the use of mobile telephone handsets, obtain via the 3G network telephone, text messaging, video messaging and internet services. The network, put very simply, comprises a series of transmission hubs and downlink sites placed at strategic intervals across the area over which the network services are accessible to customers. The proposed development is a transmission hub. Transmission hubs receive and transmit radio waves from and to handsets and each other. The appellant has identified a number of trouble spots in relation to the 3G network. A trouble spot is an area which is inoperable or unreliable from the point of view of a customer because calls cannot be initiated by the customer in that area, and calls in progress “drop out” upon entry into that area. The reason for that is insufficient signal strength within the trouble spot. The purpose of the development is to overcome three trouble spots, the first being in the streets north of Cross Road in Myrtle Bank, the second in streets east of Waite Road in Urrbrae and the third in streets south of Claremont Avenue in Netherby. Recently, the appellant entered into an agreement with Telstra under which Telstra will use the appellant’s network and infrastructure, including the tower. At present, the appellant has an agreement with Vodafone which enables it to overcome at least some of the problems associated with the trouble spots. Under the agreement, in the case of a customer of the appellant making a call from within the trouble spot, the Vodafone network carries the call. This arrangement does not prevent a caller who initiates a call from outside the trouble spot from losing the call, but he or she can redial and be connected via the Vodafone network. The agreement with Vodafone does not cover video calls or internet connection.

Evidence

Evidence before the court

Decision

Reasons for decision

ANDERSON J LAYTON J
The Court weighed up its finding as to the effect of the tower on visual amenity, its finding as to the community need for the facility and its finding as to the other options available to the appellant and considered those matters in light of the relevant provisions of the Development Plan. It decided that provisional development plan consent should be refused. That is quintessentially a planning judgment and there is no warrant for this Court to interfere with that judgment.Conclusion For these reasons, the appeal should be dismissed. I agree that the appeal should be dismissed for the reasons published by Besanko J. In my opinion the appeal should be dismissed and I agree with the reasons given by Besanko J.

Ratio Decidendi

Legal principle established

Established by: ANDERSON J, LAYTON J