JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: HUGHES -v- DORMLEY PTY LTD AS TRUSTEE FOR THE POLL FAMILY TRUST [2001] WASC 83
CORAM: WALLWORK J
HEARD: 18 SEPTEMBER 2000
DELIVERED : 30 MARCH 2001
FILE NO/S: ARB 21 of 1999
BETWEEN: B J & L H HUGHES
Applicants (Claimants)
AND
DORMLEY PTY LTD AS TRUSTEE FOR THE POLL FAMILY TRUST
Respondent (Respondent)
Catchwords:
Arbitration - House not constructed properly - Whether builder should be allowed to rectify faults - Whether diminution in value of building correct measure of award to owner - Whether owner could employ persons other than builder to rectify faults
Legislation:
Commercial Arbitration Act 1985, s 38
Result:
Leave to appeal refused
Representation:
Counsel:
Applicants (Claimants) : Mr P K Walton
Respondent (Respondent) : Mr L E James
Solicitors:
Applicants (Claimants) : Jackson McDonald
Respondent (Respondent) : Kott Gunning
Case(s) referred to in judgment(s):
Bellgrove v Eldrig (1954) 90 CLR 613
Pearce and High Limited v Baxter and Baxter (1999) CILL 1488
Ruxley Electronics v Forsyth (1996) AC 344
Turner Corporation Limited (Receiver and Manager appointed) v Austotel Pty Ltd (1994) 13 BCL 378
Case(s) also cited:
Commonwealth v Rian Financial Services & Developments Pty Ltd (1992) 36 FCR 101
Cowell v Rosehill Racecourse Pty Ltd (1937) 56 CLR 605
Darlington Borough Council v Wiltshire Northern Ltd [1995] 1 WLR 69
Duquemin v Slater (1993) 65 BLR 124
Gianfriddo v Garra Constructions Pty Ltd [1971] VR 289
Graham H Roberts Pty Ltd v Maurbeth Investments Pty Ltd (19740 1 NSWLR 93
Hughes Bros Pty Ltd v Telede Pty Ltd (1989) 7 BCL 204
Mayfield Holdings v Moana Reef Ltd [1973] 1 NZLR 309
Pearl Marin Shipping A/B v Pietro Cingolani SAS (The General Valdes) [1982] 1 Lloyd's Rep 17
Porter v Hannah Builders Pty Ltd [1969] VR 673
Promenade Investments Pty Ltd v State of NSW (1992) 26 NSWLR 203
UDR Equipment Pty Ltd v Afkos Industries Pty Ltd [2000] WASC 57
WALLWORK J: These are reasons for judgment on an originating motion applying for leave to appeal pursuant to s 38(4) of the Commercial Arbitration Act 1995 from an Arbitrator's interim award. The award was made on 15 September 1999.
A statement of agreed facts was submitted to the Court pursuant to which it is agreed that the applicants (the builder) carry on business in partnership under the business name of B J and L H Hughes. By an agreement in writing made between the builder and the respondent (the owner) on 4 November 1995, the builder agreed to complete building works at Lot 4, Blackrock Road, Margaret River for the sum of $338,640 upon the terms and conditions contained in the contract.
The builder commenced the works on about 6 November 1995. By way of two letters to the architect dated 20 November 1996, the builder made a claim for progress payments pursuant to the contract. The architect issued…
Keep reading for free
Create a free CaseChat account to read Hughes v Dormley Pty Ltd as trustee for the Poll Family Trus... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2001] WASC 83
- Decision Date
CaseChat Overview and Summary
The court examined the rationale behind the arbitrator's decision and found that the builder was not capable of remedying the defects. The court held that the builder was unable to complete the works or rectify defective workmanship or materials, and therefore the reasoning in Turner Corporation Limited v Austotel Pty Ltd and the remarks of Evans LJ in Pearce and High Limited v Baxter and Baxter were not applicable. The court found that there was no reason to reject the arbitrator's finding that the builder could not remedy the defects, and thus the builder's claims that it was unfairly disadvantaged by not being able or permitted to carry out the rectification were not upheld. The court also rejected the builder's contention that the appropriate measure of damages was the cost to the builder of making good the defects, finding instead that the measure of damages should be based on the diminution in the value of the works.
The court's decision was that the builder was not capable of remedying the defects and therefore could not be permitted to do so. The court also found that the correct measure of damages was the diminution in the value of the works, rather than the cost to the owner of employing others to rectify the defects. The court rejected the builder's contention that the works were almost complete at the date of the termination of the contract, finding instead that largely they were not built in accordance with the contract.
In conclusion, the court upheld the arbitrator's decision and found that the builder was not capable of remedying the defects in the house, and that the appropriate measure of damages was the diminution in the value of the works. The court rejected the builder's contentions that it was unfairly disadvantaged by not being able or permitted to carry out the rectification, and that the measure of damages should be the cost to the builder of making good the defects. The court's decision provides guidance on the circumstances in which a builder may be permitted to rectify defects in a building, and the appropriate measure of damages in such cases.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
The answer to those propositions for the builder is that the Arbitrator found, and there is no reason to reject his finding, that in this case the builder was not capable of remedying the defects. Because the builder was unable to complete the works or to remedy defective workmanship or materials, the reasons of Cole J in Turner Corporation Limited (Receiver and Manager appointed) v Austotel Pty Ltd (1994) 13 BCL 378 at 388 on which the builder relies are not in my view applicable to this case. I am also of the view the remarks of Evans LJ in Pearce and High Limited v Baxter and Baxter (1999) CILL 1488 at 1489 are not applicable to this case. Evans LJ's remarks were based on the assumption that the contractor could remedy the defects, whereas in this case the Arbitrator in effect held that it could not do so. It cannot be said in this case that the contractor has been unfairly disadvantaged by not being able or permitted to carry out the rectification of the faults. The same reasoning applies to the builder's submissions in this case that the contractual right of a builder to receive a direction to rectify defective work so that such rectification work can be performed by him is of great practical significance to the builder. The builder contends that it was wrongly deprived of the opportunity to rectify the defects by virtue of the owner's repudiation of the contract, and that the Arbitrator's finding that the appropriate measure of damages was the cost to the owner of remedying the defects was inconsistent with his finding that the owner had incorrectly repudiated the contract. In my opinion those submissions should not be upheld as again it is assumed that the builder was capable of remedying the defects. It is also assumed that the defects in the notices issued by the owner were fatal to its claim to claim the costs of the rectification from the builder. The builder contends in its submissions that there was a manifest error of law in the face of the record in that having found that the owner incorrectly repudiated the contract, the Arbitrator should have found that the appropriate measure of damages with respect to the owner's counterclaim for defective work was the cost to the builder of making good the defects. On the Arbitrator's finding the builder was unable to make good the defects. Alternatively it is submitted that the Arbitrator should have assessed damages on the basis of the diminution in the value of the works because, to do otherwise, leads to the unjust result that the owner is awarded damages almost equal to the cost of building the whole residence, despite the fact that the building works were almost complete at the date of the termination of the contract. The answer to that last proposition is that it could not be said that the building works were almost complete at the date of the termination of the contract because largely they were not built in accord with the contract. It was also contended for the builder that the Arbitrator accepted that the works were 96 per cent complete. That is not in accord with his findings of fact.