CITATION: | Holliday v Franklin (QLD) Pty Ltd [2017] QCATA 8 |
PARTIES: | Fiona Holliday |
| v | |
| Franklin (QLD) Pty Ltd (Respondent) | |
APPLICATION NUMBER: | APL280-15 |
MATTER TYPE: | Appeals |
HEARING DATE: | On the papers |
HEARD AT: | Brisbane |
DECISION OF: | Senior Member Stilgoe OAM |
DELIVERED ON: | 23 January 2017 |
DELIVERED AT: | Brisbane |
ORDERS MADE: | 1. The appeal is allowed. 2. (i) Paragraph 1 of the order of the Tribunal about dated 16 June 2015 is confirmed; (ii) Within 7 days of Franklin (QLD) Pty Ltd receiving from Fiona Holliday and David Holliday the full amount awarded by the Tribunal in its orders of 16 June 2015 of $18,448.83 Franklin (QLD) Pty Ltd shall instruct the certifier to perform the final inspection and Fiona and David Holliday shall not unreasonably refuse access to the certifier to undertake such inspections as are necessary; (iii) Franklin (QLD) Pty Ltd must give the final certificate to Fiona Holliday and David Holliday within 7 days of receiving it from the certifier. 3. Paragraph 2 of the decision dated 16 June 2015, dismissing the cross-application of Fiona Holliday and David Holliday about the pool is set aside and returned to the Tribunal differently constituted for consideration with the following directions: (i) Fiona Holliday and David Holliday must file in the Tribunal and serve on Franklin (QLD) Pty Ltd, all further evidence, including expert evidence, upon which they wish to rely at the further hearing of their cross-application in BDL093-14 by 4pm on 28 February 2017; (ii) Franklin (QLD) Pty Ltd must file in the Tribunal and serve on Fiona Holliday and David Holliday all further evidence, including expert evidence, upon which they wish to rely at the further hearing of the cross-application in BDL093-14 by 4pm on 31 March 2017; (iii) The proceeding is listed for a directions hearing in Brisbane on a date to be fixed not before 14 April 2017; (iv) The proceeding is listed for further hearing in Mackay on a date to be fixed by the Tribunal; (v) The Tribunal may make such further or other directions as it sees fit from time to time. |
CATCHWORDS: | APPEAL – where party failed to attend scheduled hearing – where decision reserved – where party attended at Tribunal later the same day – where directions hearing subsequently held with parties to discuss further hearing – where cross-application dismissed without hearing on the merits – whether error of law – whether procedural fairness observed APPEAL – CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – construction of clause relating to no adjustment in contract price for different dimensions – whether tribunal erred in construction of clause – whether error of law APPEAL – LEAVE TO APPEAL – CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – CERTIFICATES – whether the principal or the builder should pay for the final certificate – whether an order needed to be made for issue of the final certificate APPEAL – LEAVE TO APPEAL – CONTRACTS – BUILDING,… |
Keep reading for free
Create a free CaseChat account to read Holliday v Franklin (Qld) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCATA 8
- Decision Date
CaseChat Overview and Summary
The primary legal issues in this appeal involved whether the tribunal erred in dismissing the Hollidays' cross-application without a hearing, whether there was an error of law in the tribunal's construction of the contract clause, and whether the tribunal correctly approved the variation without compliance with the contract or the Domestic Building Contracts Act. The appeal also questioned whether the tribunal had procedural fairness and whether the tribunal should have made an order for the issue of the final certificate.
The appeal court found that the tribunal had indeed erred in dismissing the Hollidays' cross-application without a hearing, violating their right to procedural fairness. The court also held that the tribunal had erred in its construction of the contract clause regarding the no adjustment in contract price for different dimensions. Additionally, the tribunal's approval of the variation was found to be incorrect as it did not comply with the contract or the Act. The court concluded that an order needed to be made for the issue of the final certificate.
The appeal was allowed, and the tribunal's orders were varied. Paragraph 1 of the tribunal's order dated 16 June 2015 was confirmed, and the Hollidays were to receive the full amount awarded by the tribunal. Paragraph 2 of the decision, dismissing the Hollidays' cross-application about the pool, was set aside and returned to the tribunal for reconsideration with specific directions for further evidence and a further hearing. The tribunal was also directed to issue the final certificate to the Hollidays within seven days of receiving it from the certifier.
Orders
Orders of the court
1. The appeal is allowed.
2. (i) Paragraph 1 of the order of the Tribunal about dated 16 June 2015 is confirmed;
(ii) Within 7 days of Franklin (QLD) Pty Ltd receiving from Fiona Holliday and David Holliday the full amount awarded by the Tribunal in its orders of 16 June 2015 of $18,448.83 Franklin (QLD) Pty Ltd shall instruct the certifier to perform the final inspection and Fiona and David Holliday shall not unreasonably refuse access to the certifier to undertake such inspections as are necessary;
(iii) Franklin (QLD) Pty Ltd must give the final certificate to Fiona Holliday and David Holliday within 7 days of receiving it from the certifier.
3. Paragraph 2 of the decision dated 16 June 2015, dismissing the cross-application of Fiona Holliday and David Holliday about the pool is set aside and returned to the Tribunal differently constituted for consideration with the following directions:
(i) Fiona Holliday and David Holliday must file in the Tribunal and serve on Franklin (QLD) Pty Ltd, all further evidence, including expert evidence, upon which they wish to rely at the further hearing of their cross-application in BDL093-14 by 4pm on 28 February 2017;
(ii) Franklin (QLD) Pty Ltd must file in the Tribunal and serve on Fiona Holliday and David Holliday all further evidence, including expert evidence, upon which they wish to rely at the further hearing of the cross-application in BDL093-14 by 4pm on 31 March 2017;
(iii) The proceeding is listed for a directions hearing in Brisbane on a date to be fixed not before 14 April 2017;
(iv) The proceeding is listed for further hearing in Mackay on a date to be fixed by the Tribunal;
(v) The Tribunal may make such further or other directions as it sees fit from time to time.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.