| CITATION: | Franklin (QLD) Pty Ltd v Holliday [2015] QCAT 217 |
| PARTIES: | Franklin (QLD) Pty Ltd (Applicant) |
| v | |
| Fiona Holliday and David Holliday (Respondent) |
| APPLICATION NUMBER: | BDL093-14 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 1 May 2015 |
| HEARD AT: | Mackay |
| DECISION OF: | Member Rogers |
| DELIVERED ON: | 16 June 2015 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. That Fiona and David Holliday pay Franklin (QLD) Pty Ltd the amount of $18,448.83 on or before 19 August 2015. 2. That the counterclaim of David and Fiona Holliday be dismissed. |
| CATCHWORDS: | BUILDING DISPUTE – where variations to contract not written and signed- where counter claim already before tribunal in different proceedings- where respondent failed to appear at hearing- whether tribunal grant approval for applicant to recover amount for variation. Domestic Building Contracts Act 2000 (Qld) s 84(2) |
APPEARANCES:
| APPLICANT: | Franklin (QLD) Pty Ltd through its Director Francis John Galea, |
| RESPONDENT: | No appearance |
This matter was part heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
Procedural Matters
The applicant builder is seeking an order for the payment of the sum of $36,140 plus interest plus costs. This claim relates to a contract dated 25 June 2013 for the construction and completion of a new garage and storeroom (the extensions contract) at the building owners’ home and is restricted to work that formed part of that contract. Part of the claim relates to unwritten variations to the contract and requires leave of the Tribunal pursuant to s 84(2) of the Domestic Building Contracts Act 2000 (Qld), (the Act).
The building owners filed a response and counter claim on 27 May 2014 seeking orders that the builder’s claim be dismissed with costs and orders relating to the final inspection of the extensions.
The owners then referred to a building contract dated 21 August 2012 entered into by the parties for the construction of a concrete pool, (the pool contract) and applied for an order
‘to repair the pool surface and pool leak and leave the pool in ‘as-new’ condition or compensate us sufficiently to enable a professional and experienced builder to do so’
On 15 May 2014 the owners filed Application GAR167-14 in the tribunal seeking a review of a decision dated 17 April 2014 of the Queensland Building and Construction Commission, which declined to issue orders sought for the rectification of the pool. A letter provided to the tribunal in these proceeding from QBCC to the owners dated 4 November 2014 indicates the Commission found defective work but it was unable to issue an order until the building dispute is resolved.
The tribunal had adjourned the QBCC application pending the determination of this application.
This application was listed for hearing at 9.30 am on 1 May 2015 at Mackay. The applicant builder, through its director Mr Galea was present. The respondent building owners were not present. Repeated attempts to contact the owners by telephone were unsuccessful.
I satisfied myself the owners…
Keep reading for free
Create a free CaseChat account to read Franklin (Qld) Pty Ltd v Holliday and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QCAT 217
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the tribunal should grant the builder's application to recover the additional costs claimed for variations to the original contract, despite the fact that these variations were not documented in writing as required by the contract. Another issue was whether the tribunal could proceed with the hearing in the absence of the respondents, given that a counterclaim by the respondents was already before the tribunal in a separate proceeding. The builder argued that the respondents' absence should not prevent the tribunal from making a decision, while the respondents contended that their absence prejudiced their ability to defend the claims.
The tribunal found that the builder had not followed the contractual requirement to obtain written and signed approval for the variations. However, it also noted that the builder had a longstanding relationship with the homeowners and had acted in good faith, assuming that he would be compensated for the additional work. The tribunal concluded that the builder was entitled to recover the additional costs, subject to a reduction to account for the homeowners' failure to provide proper written quotations for the work. The tribunal also determined that it could proceed with the hearing in the absence of the respondents, as the issues in the two proceedings were separate and did not overlap significantly.
The tribunal ordered that the homeowners pay the builder the amount of $18,448.83, representing the cost of the additional works, reduced by the amount of $1,000 to account for the builder's failure to provide written quotations. The tribunal also dismissed the homeowners' counterclaim.
Orders
Orders of the court
1. That Fiona and David Holliday pay Franklin (QLD) Pty Ltd the amount of $18,448.83 on or before 19 August 2015.
2. That the counterclaim of David and Fiona Holliday be dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.