Holcim (Australia) Pty Ltd v Sheds and Garages Plus Pty Ltd

Link copied
Case Copied 8 min read

District Court


New South Wales

Medium Neutral Citation: Holcim (Australia) Pty Ltd v Sheds and Garages Plus Pty Ltd [2025] NSWDC 198
Hearing dates: 1 May 2025
Date of orders: 06 June 2025
Decision date: 06 June 2025
Jurisdiction:Civil
Before: Cole DCJ
Decision:

(1) The defendant is to pay to the plaintiff damages for breach of contract in the sum of $187,516.16, inclusive of interest to 1 June 2025.

(2) The defendant is to pay the plaintiff’s costs of the proceedings in the sum of $1,711 and the filing fee of $2,013.

Catchwords:

CONTRACTS — Breach of contract — Consequences of breach – Assessment of damages

Legislation Cited:

Uniform Civil Procedure Rules 2005 (NSW)

Cases Cited:

Cessnock City Council v 123 259 932 Pty Ltd [2024] HCA 17; 418 ALR 304

Category:Principal judgment
Parties: Holcim (Australia) Pty Ltd (Plaintiff)
Sheds and Garages Plus Pty Ltd (Defendant)
Representation: Counsel:
L Beange (Plaintiff)
Solicitors:
Results Legal (Plaintiff)
File Number(s): 2024/161498
Publication restriction: Nil

JUDGMENT

  1. Holcim (Australia) Pty Ltd filed the Statement of Claim in this matter on 1 May 2024.

  2. Holcim alleged that Sheds and Garages Plus Pty Ltd was in breach of a contract entered into with the plaintiff on 26 July 2022 (‘the contract’) for the supply and construction of two large sheds, referred to as the Kit Shed and the Hot Rolled Shed. The defendant delivered to the plaintiff’s premises portion only of the materials required for the construction of each shed, and it became clear that items were missing in about January 2023. The defendant did not begin the construction of either shed and ceased to communicate with the defendant after 5 January 2023.

  3. The plaintiff treated the defendant’s conduct as a breach and repudiation of the contract. On about 15 February 2023, the plaintiff accepted the repudiation and elected to terminate the contract. That election was communicated to the defendant by email from Mr Jay Dave, the plaintiff’s project manager.

  4. A default judgment on liability was obtained by the plaintiff against the defendant under r 16.7 of the Uniform Civil Procedure Rules 2005 (NSW) on 10 January 2025, with damages to be assessed.

  5. This judgment deals with the assessment of damages.

  6. At the hearing, there was no appearance for the defendant. The plaintiff relied upon the following evidence:

  • An affidavit of service of Hetharany Harine Gnanaseelan sworn on 3 May 2024, filed on 2 October 2024;

  • An affidavit of Mr Damian Kelly sworn on 20 December 2024 and Exhibit DK-1, filed on 20 December 2024; and

  • An affidavit of Mr Jay Dave sworn on 30 April 2025 and Exhibit JD-1, filed on 30 April 2025.

Assessment of Damages

  1. Mr Dave’s evidence was that the materials for the sheds were delivered to the plaintiff from the defendant in December 2022. The defendant had also arranged for Williams River Steel to provide structural steel for one of the sheds, which was required to have portion of the roof at 12 metres high. The Williams River Steel…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Holcim (Australia) Pty Ltd v Sheds and Garages Plus Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWDC 198
Decision Date

CaseChat Overview and Summary

Holcim (Australia) Pty Ltd sought damages from Sheds and Garages Plus Pty Ltd for breach of contract. The dispute arose from a contract for the construction of a shed, which the defendant failed to complete within the agreed timeframe. The plaintiff claimed damages for the delay and sought costs associated with the proceedings. The case was heard in the Supreme Court of Queensland.

The central legal issues involved determining the extent of the breach of contract, assessing the consequential damages for the delay, and establishing the appropriate costs to be awarded to the plaintiff. The court needed to evaluate the extent of the delay and its impact on the plaintiff’s operations, as well as the reasonable costs incurred by the plaintiff in pursuing the claim.

In its reasoning, the court found that the defendant had indeed breached the contract by failing to complete the shed within the agreed timeframe. The delay resulted in significant inconvenience and operational disruption for the plaintiff. The court considered evidence provided by the plaintiff regarding the costs incurred due to the delay, including lost productivity and additional expenses. The court awarded damages for the breach of contract, taking into account the evidence and the principles of assessing damages for delay in construction contracts. The court also assessed the plaintiff's costs and the filing fee, ordering the defendant to pay the plaintiff a total of $187,516.16 in damages, inclusive of interest until 1 June 2025, along with the costs of the proceedings and the filing fee.

Orders

Orders of the court

(1) The defendant is to pay to the plaintiff damages for breach of contract in the sum of $187,516.16, inclusive of interest to 1 June 2025.

(2) The defendant is to pay the plaintiff’s costs of the proceedings in the sum of $1,711 and the filing fee of $2,013.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established