Hodgkins v Munro Building Group

Link copied
Case Copied 48 min read

CITATION:

Hodgkins v Munro Building Group [2018] QCAT 37

PARTIES:

Susie Hodgkins

(Applicant)

v

Christopher Robin Munro trading as Munro Building Group
(Respondent)

APPLICATION NUMBER:

BDL207-16

MATTER TYPE:

Building matters

HEARING DATES:

8 and 9 June 2017

HEARD AT:

Townsville

DECISION OF:

Member Pennell

DELIVERED ON:

20 February 2018

DELIVERED AT:

Townsville

ORDERS MADE:

1.   That the Respondent pay the Applicant the sum of $806.60 by 4:00pm on 7 April 2018.

2.   That the Applicant’s application be otherwise dismissed.

3.   There is no Order as to costs.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – where the parties entered into a contract for the builder to build a house in the same design, appearance and with the same specifications as the builder’s display house inspected by the applicant – where the applicant altered the plans to include an additional room – where the house constructed according to the modified plans – where the applicant alleges breach of contract by the respondent builder – whether the respondent builder has breached the contract

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – where the applicant claims damages for the alleged breach of contract by the respondent builder – whether the applicant has adequately identified and quantified her actual loss suffered

Queensland Building and Construction Commission Act 1991 (Qld), s 67A

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 28


Addis v Gramophone Co Ltd
[1909] AC 488
Commonwealth of Australia v Amann Aviation Pty Ltd (1991) 174 CLR 64
Luna Park (NSW) Ltd v Tramways Advertising Pty Ltd (1938) 61 CLR 86

R v War Pensions Entitlement Appeals Tribunal; ex-parte Bott (1933) 50 CLR 228

Robinson v Harman (1848) 154 ER 363

APPEARANCES:

APPLICANT:

Self Represented

RESPONDENT:

Self Represented

REASONS FOR DECISION

INTRODUCTION

[1]The Applicant was in the market for a new house.  She found one that appealed to her which had been built by the Respondent.  What impressed here about the house was the design, features and colours. 

[2]She later met with the Respondent for an inspection of his house.  Arising from that was the parties entered into a contract for the Respondent to build a house for the Applicant.[1]  The signatures of the parties were witnessed by the Applicant’s close friend.[2]  The contract price for the construction of the house was $270,000.  Accompanying the contract was a preliminary specification document.[3]

[1]A standard new home construction contract for the construction of the Applicant’s house signed and dated 29 April 2015.

[2]Mr Ross Collins.

[3]Exhibit 1 at Document Tab 2.

[3]At the time of the hearing, the Applicant told the Tribunal that she accepted that the house is structurally sound, and she had already been living in it for the 18 months.[4]  She said that she entered into the contract with the Respondent in good faith, but he lied to her and he was dishonest.  She was of the belief that she was getting…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hodgkins v Munro Building Group and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] QCAT 37
Decision Date

CaseChat Overview and Summary

The case of Hodgkins v Munro Building Group was heard in the Queensland Civil and Administrative Tribunal (QCAT) where the Applicant, Ms Hodgkins, claimed that the Respondent, Munro Building Group, had breached their contract by failing to construct her house to the specifications of the display house that she had inspected. The contract between the parties stipulated that the house would be built in the same design, appearance, and specifications as the display house. However, Ms Hodgkins made alterations to the plans and the house was built according to the modified plans. Ms Hodgkins argued that this constituted a breach of contract by the builder.

The primary issue for the Tribunal to determine was whether the builder had breached the contract by not adhering to the original specifications of the display house. Additionally, the Tribunal had to consider whether Ms Hodgkins had adequately identified and quantified her actual loss suffered as a result of the alleged breach. In determining these issues, the Tribunal had to weigh the evidence provided by both parties and consider the terms of the contract between them.

In delivering its decision, the Tribunal found that the builder had not breached the contract as the modifications to the plans had been agreed to by Ms Hodgkins and the builder. The Tribunal also found that Ms Hodgkins had failed to demonstrate that she had suffered any actual loss as a result of the modifications. The Tribunal ordered that the builder pay Ms Hodgkins the sum of $806.60, which represented the cost of the modifications to the plans. The Tribunal dismissed the remainder of Ms Hodgkins’ application and made no order as to costs.

The Tribunal’s decision provides guidance to builders and homeowners regarding the importance of clear communication and agreement on modifications to building plans. It also highlights the need for homeowners to demonstrate actual loss in order to successfully claim damages for breach of contract.

Orders

Orders of the court

1. That the Respondent pay the Applicant the sum of $806.60 by 4:00pm on 7 April 2018.

2. That the Applicant’s application be otherwise dismissed.

3. There is no Order as to costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established