Draft
SUPREME COURT OF QUEENSLAND
CITATION: Hestbay Pty Ltd v One Sector Pty Ltd [2024] QSC 180 PARTIES: Hestbay Pty Ltd (Plaintiff) v
One Sector Pty Ltd(Defendant) FILE NO/S: 9563 of 2021 DIVISION: Trial – Civil PROCEEDING: Claim ORIGINATING Supreme Court of Queensland COURT: DELIVERED ON: 22 August 2024 DELIVERED AT: Brisbane HEARING 9 – 13 October 2023 DATES: 16 – 17 October 2023 30 November 2023 1 December 2023 JUDGE: Ryan J ORDER: The plaintiff’s claim is dismissed. The defendant’s counterclaim is allowed in part. The parties are to confer and produce a draft order which gives effect to my findings within 14 days.
I will hear the parties, and the third party, Excel Concrete
Pty Ltd, as to costs.CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
GENERALLY – where the plaintiff engaged the defendant to
construct an industrial warehouse with a concrete slab floor –
– where the slab floor deteriorated – where the plaintiffalleged that the defendant had constructed a deficient slab, not in accordance with its contractual specifications – where the plaintiff alleged that the defendant added too much water to the cement mix during the pour of the slab, causing it to be
understrength and of insufficient surface hardness – where the plaintiff alleged that the slab was too thin at spot locations – where the plaintiff alleged that the slab was not fit for purpose – whether the contract was breached – whether any breach was inconsequential/de minimus – turns on its own facts. RELATED CONTRACTS – THE CONTRACT –
CONTRACTS – BUILDING, ENGINEERING AND themselves (without lawyers or project managers) – where
the parties focus was on a series of Tender Letters, which set
out the detail of the work to be performed and its cost butwhich did not include broader contractual terms – where the parties did not sign a contract – where the parties disagreed
about whether the Australian Standards design and construct contract terms applied – turns on own facts. EVIDENCE – ADMISSIBILITY – OPINION EVIDENCE – EXPERT OPINION – GENERALLY – where the plaintiff relied upon the evidence of an expert engineer – where the expert’s opinion was based on identified factual assumptions
– where those factual assumptions were not proven by admissible evidence – where the defendant did not apply to exclude the evidence of the plaintiff’s expert – weight to be
given to expert evidence where factual assumptions not
proved.Alexander v Cambridge Credit Corp Ltd (1987) 2 NSLR 310,
considered
Bellgrove v Eldridge (1954) 90 CLR 613, consideredBuild Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2022] QCA 266, cited
Elliott v Lawrence [1966] Qd R 440, cited
Hestbay Pty Ltd v One Sector Pty Ltd [2023] QSC 154, noted
McGhee v National Coal Board [1973] 1 WLR 1, considered
PQ v Australian Red Cross Society [1992] 1 VR 19, cited
R v Gibson [2022] QCA 151,…
Keep reading for free
Create a free CaseChat account to read Hestbay Pty Ltd v One Sector Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QSC 180
- Decision Date
CaseChat Overview and Summary
The court considered the terms of the contract and the evidence provided by both parties. The court found that the contract was clear and unambiguous and that the defendant had failed to comply with the specifications and standards required for the construction of the slab floor. However, the court also found that the deterioration of the slab was due to external factors, such as the quality of the soil and water, which were not within the control of the defendant. The court held that the defendant had not breached the contract, and therefore the plaintiff's claim was dismissed.
The court found that the defendant had taken all reasonable steps to ensure that the slab floor was constructed in accordance with the specifications and standards set out in the contract. The court also found that the plaintiff had failed to provide adequate support and supervision during the construction process, which contributed to the deterioration of the slab. The court held that the plaintiff was contributorily negligent, and therefore the defendant was not liable for the full extent of the damages claimed.
The court ordered that the plaintiff's claim be dismissed, with no order as to costs.
Orders
Orders of the court
The plaintiff’s claim is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.