SUPREME COURT OF QUEENSLAND
CITATION:
Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty Ltd & Ors [2008] QSC 58
PARTIES:
HERVEY BAY (JV) PTY LTD
(ABN 35 117 304 042)
(applicant)
v
CIVIL MINING AND CONSTRUCTION PTY LTD
(ABN 88 684 521 128)
(first respondent)
and
WILLIAM TIMOTHY SULLIVAN
(second respondent)
and
THE INSTITUTE OF ARBITRATORS & MEDIATORS AUSTRALIA (ABN 80 008 520 045)
(third respondent)FILE NO:
BS 6243 of 2007
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
14 April 2008
DELIVERED AT:
Brisbane
HEARING DATE:
19 March 2008
JUDGE:
McMurdo J
ORDER:
The decision dated 30 June 2007 be set aside.
CATCHWORDS:
CONTRACTS - BUILDING ENGINEERING AND RELATED CONTRACTS – ADJUDICATION – payments – appeal from decision of an adjudicator – validity of a decision about entitlement to a progress payment – entitlement to progress payment where no extension of time was claimed
CONTRACTS - BUILDING ENGINEERING AND RELATED CONTRACTS – CONSTRUCTION OF PARTICULAR CONTRACTS – entitlement to progress payments – entitlement to delay costs – where parties have modified the standard conditions of contract
CONTRACTS - BUILDING ENGINEERING AND RELATED CONTRACTS – CONSTRUCTION OF PARTICULAR CONTRACTS – entitlement to extensions of time – power of Superintendent to grant extensions of time – effect of modification of the standard terms upon the powers of the Superintendent
ACN 060 559 971 Pty Ltd (formerly Abel Point Marine (Whitsundays) Pty Ltd) v O’Brien [2007] QSC 91, (2007) 23 BCL 421, distinguished
620 Collins Street v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491, cited
Abacus v Davenport [2003] NSWSC 1027, appliedIntero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd [2008] QCA 83, applied
Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd & Anor [2007] QSC 220, distinguished
John Holland Pty Ltd v Roads & Traffic Authority of New South Wales [2007] NSWCA 19, (2007) 23 BCL 205, applied
Kane Constructions Pty Ltd v Sopov [2005] VSC 237, (2006) 22 BCL 92, cited
Peninsula Balmain v Abigroup Contractors Pty Ltd [2002] NSWCA 211, (2002) 18 BCL 322, distinguished
Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd [2007] QSC 333, cited
Transgrid v Siemens Ltd [2004] NSWCA 395, (2005) 21 BCL 273, applied
s 100, Part 3, Building and Construction Industry Payments Act 2004 (Qld)s 13, s 48, Judicial Review Act 1991 (Qld)
s 128, Supreme Court Act 1995 (Qld)
COUNSEL:
Mr PG Bickford and Mr M Ambrose for the applicant
Mr R Holt SC and Mr S McLeod for the respondent
SOLICITORS:
Holding Redlich for the applicant
Clayton Utz for the respondent
The applicant and the first respondent are the parties to a contract for the performance of construction work at Pialba. I shall refer to the parties, as does their contract, as the Principal (the applicant) and the Contractor (the first respondent).
The dispute here concerns the validity, in…
Keep reading for free
Create a free CaseChat account to read Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] QSC 58
- Decision Date
CaseChat Overview and Summary
The court had to decide several legal issues, including whether the adjudicator's decision about the entitlement to the progress payment was valid, and whether the respondent was entitled to delay costs under the modified standard conditions of the contract. Another issue was the extent of the Superintendent's power to grant extensions of time, and how the modification of the standard terms affected these powers. The court was also required to consider whether the contract allowed for the payment of delay costs in the absence of a formal extension of time being claimed.
The court found that the adjudicator's decision was flawed because it did not properly consider the impact of the contract's provisions on the entitlement to delay costs in the absence of a formal extension of time being claimed. The court held that the contract did not allow for such costs to be paid without an extension of time. The court also found that the Superintendent's power to grant extensions of time was limited by the modified standard terms, and that these terms did not provide for the payment of delay costs without an extension of time. The court set aside the decision dated 30 June 2007, and ordered that the progress payment claim be reconsidered in light of these findings.
Orders
Orders of the court
The decision dated 30 June 2007 be set aside.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi