Heather v Sunshine Coast Regional Council

Link copied
Case Copied 41 min read

PLANNING AND ENVIRONMENT COURT OF QUEENSLAND

CITATION:

Heather & Anor v Sunshine Coast Regional Council & Ors [2022] QPEC 37

PARTIES:

JAY ANTHONY HEATHER
ELISABETH IRENE HEATHER

(applicants)

v

SUNSHINE COAST REGIONAL COUNCIL

(first respondent)

GLYNN EDWARD MOSELEY
KARRAN JAYNE MOSELEY

(second respondents)

FILE NO/S:

11/2021

DIVISION:

Planning and Environment

PROCEEDING:

Application for declarations and ancillary orders

DELIVERED ON:

7 October 2022

DELIVERED AT:

Maroochydore

HEARING DATES:

21 February 2022, 22 February 2022

JUDGE:

Cash DCJ

ORDERS:

The application is dismissed.

CATCHWORDS:

PLANNING AND ENVIRONMENT–– APPLICATION FOR DECLARATIONS OR ORDERS – REVIEW OF DECISIONS – where the respondent was successful in an application for prescribed tidal works to build a jetty – where the application was code assessable – where the application was approved and the jetty was constructed – where the applicant sought declarations and orders setting aside the  decision to approve prescribed tidal works – whether the decision was materially affected by legal error or was legally unreasonable

Coastal Protection and Management Regulation 2017 (Qld), Schedule 3
Planning Act 2016 (Qld), s 45, s 60

Planning and Environment Court Act 2016 (Qld), s 11
Planning Regulation 2017 (Qld), s 21, s 28, Schedule 8, Schedule 10

Australia Pacific LNG Pty Limited & Ors v The Treasurer, Minister for Aboriginal and Torres Strait Islander Partnerships and Minister for Sport [2019] QSC 132, [161], [191], [232], followed
Australian Retailers Association v Reserve Bank of Australia (2005) 148 FCR 446, [522], followed
Craig v South Australia (1995) 184 CLR 163, 179 [14], applied
Elias v Commissioner of Taxation (Cth) (2002) 123 FCR 499, [57], followed
Ferreyra v Brisbane City Council [2016] QPEC 10; [2016] QPELR 33, [7]-[9], [76], applied
Fraser Coast Regional Council v Walter Elliott Pty Ltd [2017] 1 Qd R 13, [40], applied
Friends of Buddina Ltd v Sunshine Coast Regional Council &
Anor [2021] QPEC 57, [18], [19], applied
Hossain v Minister for Immigration and Border Protection [2018] HCA 34; 264 CLR 123; 92 ALJR 780; 359 ALR 1, [30], [39]-[43], [74], applied
Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24, 40-41, applied
Minister for Immigration and Citizenship v Li [2013] HCA 18; 249 CLR 332; 87 ALJR 618; 297 ALR 225, [68], [75], [76], [105], [108], applied

COUNSEL:

A N S Skoien for the applicants
K W Wylie for the first respondent
P A Beehre for the second respondents

SOLICITORS:

P&E Law for the applicants
Sunshine Coast Council Legal Services for the first respondent
North Coast Law for the second respondents

Introduction

  1. The applicants (the Heathers) and the second respondents (the Moseleys) own properties near each other on a canal in Minyama. The first respondent (the Council) gave the Moseleys approval to construct a gangway, deck and pontoon protruding into the canal. The works have been completed. The applicants are unhappy with the decision of the Council to approve the works. They challenge the decision, alleging it was affected…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Heather v Sunshine Coast Regional Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QPEC 37
Decision Date

CaseChat Overview and Summary

In Heather v Sunshine Coast Regional Council, the applicant challenged the Council's approval of a prescribed tidal works application, which allowed for the construction of a jetty. The application was deemed code assessable, meaning it did not require referral to the Minister for a decision. Following the approval and subsequent construction of the jetty, the applicant sought declarations and orders to set aside the decision, arguing that it was materially affected by legal error or was legally unreasonable.

The court was required to determine whether the decision to approve the prescribed tidal works was legally flawed. This involved examining the criteria and process by which the decision was made, and whether the Council had adhered to the relevant legislative and procedural requirements. The applicant's contention was that the decision was legally unreasonable because it did not properly consider the impact on the applicant's property and the surrounding environment.

The court examined the legislative framework and found that the Council had correctly followed the prescribed process for assessing the tidal works application. The court held that the decision was not materially affected by legal error and was not legally unreasonable. The court found that the Council had appropriately considered the relevant factors and statutory criteria in approving the application. Consequently, the applicant's challenge to the decision was dismissed, and the construction of the jetty was upheld.

Orders

Orders of the court

The application is dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established