Land and Environment Court
of New South Wales
CITATION: Hastings Point Progress Association Inc v Tweed Shire Council and Anor; Hastings Point Progress Association Inc v Tweed Shire Council and Ors [2008] NSWLEC 219 PARTIES: APPLICANT
Hastings Point Progress Association Inc
FIRST RESPONDENT
Tweed Shire Council
SECOND RESPONDENTS
Aeklig Pty Ltd
Planit Consulting Pty Ltd
THIRD RESPONDENTS
Kylie Ann Campion
Jody Anne Kearney
Kelly Anne GilliesFILE NUMBER(S): 40785 of 2007, 40967 of 2007 CORAM: Pain J KEY ISSUES: Judicial Review :- failure to consider mandatory matter in grant of development consent by the Council - whether order under s 25B Land and Environment Court Act 1979 should be made to suspend operation of consent LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 79C
Land and Environment Court Act 1979 s 25B, s 25E
Tweed Local Environmental Plan 2000CASES CITED: Belmore Residents’ Action Group Inc v Canterbury City Council and Anor (2006) 147 LGERA 226
Bungendore Residents Group Inc v Palerang Council and Anor (No 4) [2007] NSWLEC 536
Centro Properties Limited v Hurstville City Council and Anor (2004) 135 LGERA 257
Hastings Point Progress Association Inc v Tweed Shire Council and Anor; Hastings Point Progress Association Inc v Tweed Shire Council and Ors [2008] NSWLEC 180
Homemakers Supacenta-Belrose Pty Limited v Warringah Council and Anor [2008] NSWLEC 54
Kindimindi Investments Pty Ltd v Lane Cove Council and Anor (2007) 150 LGERA 333
Mid Western Community Action Group Inc v Mid-Western Regional Council & Stockland Development Pty Ltd [2007] NSWLEC 411DATES OF HEARING: Written submissions filed after substantive judgment
DATE OF JUDGMENT:
31 July 2008LEGAL REPRESENTATIVES: APPLICANT
Mr A Pickles with Ms Y Cachia
SOLICITOR
Environmental Defenders OfficeFIRST RESPONDENT
Submitting appearance
SECOND and THIRD RESPONDENTS
Mr P McEwen SC with Dr S Berveling
SOLICITOR
Stacks
JUDGMENT:
THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALESPain J
40785 of 2007, Hastings Point Progress Association Inc v Tweed Shire Council and Anor (No 2)31 July 2008
JUDGMENT40967 of 2007 Hastings Point Progress Association Inc v Tweed Shire Council and Ors (No 2)
1 Her Honour: In Hastings Point Progress Association Inc v Tweed Shire Council and Anor; Hastings Point Progress Association Inc v Tweed Shire Council and Ors [2008] NSWLEC 180 I held that the Tweed Shire Council as the First Respondent (the Council) in matter no 40967 of 2007, (Planit Consulting Pty Limited as Second Respondent and Kylie Ann Campion, Jody Anne Kearney and Kelly Anne Gillies as Third Respondents), had failed to take into account cl 8(1)(c) of the Tweed Local Environmental Plan 2000 (TLEP) when it granted development consent to the Third Respondent’s development consent for DA07/0022. The relevant background to the finding is set out in the judgment. Importantly, I found that this clause was a condition precedent to the granting of development consent under the TLEP and the Council had failed to consider it; see [91]-[111]. The Applicant now seeks a declaration that the development consent is invalid.
Keep reading for free
Create a free CaseChat account to read Hastings Point Progress Association Inc v Tweed Shire Counci... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] NSWLEC 219
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the Council had properly considered the statutory requirements and the merits of the development application, and whether the Association had standing to challenge the decision. The court had to determine if the Council had adhered to the necessary legislative provisions in granting the development consent and whether the Association had the right to seek judicial review.
The court found that the Council had indeed failed to properly consider the statutory requirements and the merits of the application, leading to the conclusion that the development consent was granted without proper procedure. Consequently, the court declared the development consent void and of no effect. Additionally, the court dismissed the Association's application for further relief, reserving the matter of costs for later determination.
Orders
Orders of the court
The Court makes the following declaration and orders:
In matter no 40967 of 2007:
1. A declaration that development consent DA 07/0022 in respect of development at lot 9 DP 14141, 21 Tweed Coast Road, Hastings Point, granted by the First Respondent on 19 June 2007 is void and of no effect.
2. Costs are reserved.
In matter no 40785 of 2007:
1. The application is dismissed.
2. Costs are reserved.