Land and Environment Court


of New South Wales


CITATION: Centro Properties Limited v Hurstville City Council & Anor [2004] NSWLEC 718
PARTIES: Centro Properties Limited (Appl)
Hurstville City Council (1R)
Dimitrios Tsagias and Giannoula Tsagias (2R)
FILE NUMBER(S): 40227 of 2004
CORAM: McClellan CJ
KEY ISSUES: Costs :- Invalid development consent
Apportionment
What portion of the claim the applicant succeeded upon
LEGISLATION CITED:
CASES CITED: Commissioner of Australian Federal Police v Tazzi & Anor (No 2) (1991) 101 ALR 425;
Cretazzo v Lombardi (1975) 13 SASR 4;
Dodds Family Investments Pty Ltd v Lane Industries Pty Ltd (1993) 26 IPR 261;
Hughes v Western Australian Cricket Association (Inc) [1986] ATPR 48,134;
Jamal v Secretary, Department of Health (1988) 14 NSWLR 252;
J-Corp Pty Ltd v Australian Builders Labourers Federated Union of Workers (No 2) (1993) 46 IR 301;
Mok v Minister for Immigration, Local Government and Ethnic Affairs (No 2) (1993) 47 FCR 81
DATES OF HEARING: 22 September 2004
EX TEMPORE
JUDGMENT DATE :
09/22/2004
LEGAL REPRESENTATIVES:


M Henry (Appl)
Mallesons Stephen Jaques (Solicitors - Appl)

P Rigg (1R)
Deacons (Solicitors - 1R)

P Tomasetti (2R)
N J Papallo (Solicitors - 2R)



JUDGMENT:

      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      McCLELLAN J

      WEDNESDAY, 22 SEPTEMBER 2004

      40227/04 CENTRO PROPERTIES LIMITED v HURSTVILLE CITY COUNCIL & ANOR

      JUDGMENT - On Costs

1 HIS HONOUR: This matter comes before me this morning in relation to the question of costs. On 12 August 2004 I gave judgment in favour of the applicant and made orders declaring that development consent no 2002/0252 granted by the first respondent to the second respondent, United Leisure Investments Pty Limited, was invalid. I also restrained the second respondent from acting upon the consent.

2 The parties are agreed that there were three fundamental issues raised for determination in the proceedings. They may be shortly described as the car noise issue, the geo-technical issue and the Water Board issue.

3 The parties are also agreed that the car noise issue and the evidence associated with the resolution of that issue occupied the greater portion of the hearing time and the effort of the parties in resolving the matter before the Court.

4 The allegation that there was a failure to properly consider the geo-technical issue, and a failure to address the water and sewerage facilities for the site were issues which, although answered by the applicant, did not occupy a significant proportion of the hearing time.

5 There was a further issue, being whether or not the Court should, in the exercise of its discretion, make an order. This matter was debated and particularly pressed by the second respondent. However, by reason of section 25B, the statute requires that issue to be considered by the Court in any proceedings and, accordingly, I do not consider the fact that that matter was discussed should have any significance in the resolution of the costs issue in these proceedings.

6 The Council resists an…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Centro Properties Limited v Hurstville City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] NSWLEC 718
Decision Date

CaseChat Overview and Summary

In the Land and Environment Court of New South Wales, the case of Centro Properties Limited v Hurstville City Council & Anor was heard by McClellan CJ. The applicant, Centro Properties Limited, sought a declaration that a development consent granted by Hurstville City Council to the second respondent, United Leisure Investments Pty Limited, was invalid. The court was also required to decide on the apportionment of costs between the parties.

The primary legal issues were whether the court should make an order for the entire costs of the applicant and, if not, how the costs should be apportioned. The second respondent argued that the applicant should bear the costs of the issues on which it failed, while the applicant contended that costs should follow the event. The court considered various legal principles and authorities on the issue of costs apportionment, including the discretion of the court to consider the reasonableness of the arguments advanced by each party and the need to ensure that legal resources are not wasted on issues with no prospects of success.

The court found that the applicant was successful on the car noise issue but failed on the geo-technical and water and sewerage issues. While acknowledging the general principle that costs follow the event, the court decided that an order for apportionment was appropriate in this case, particularly in relation to the water and sewerage issue. The court believed that the applicant's argument on this matter was entirely without foundation and that a more responsible approach to litigation would not have brought it forward. The court also noted that the geo-technical issue, despite being unsuccessful for the applicant, had some prospects of success and should not be subject to an order for costs. The court concluded that the applicant should receive eighty-five percent of its costs, reflecting the small portion of the proceedings occupied by the issue appropriate for apportionment.

The final orders of the court were that the respondents, Hurstville City Council and United Leisure Investments Pty Limited, pay eighty-five percent of the applicant's costs. The court did not believe it appropriate to place the burden of those costs on the first respondent alone, as the second respondent chose to join in the proceedings and play an active part in them.