Harper Property Builders Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 35 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Harper Property Builders Pty Ltd v Queensland Building and Construction Commission [2018] QCATA 70

PARTIES:

HARPER PROPERTY BUILDERS PTY LTD
(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO:

APL273-17

MATTER TYPE:

Appeals

DELIVERED ON:

25 May 2018

HEARING DATE:

20 February 2018

HEARD AT:

Brisbane

DECISION OF:

Hon J B Thomas, Judicial Member

Senior Member Brown

ORDERS:

1.   Leave is granted to the applicant to appeal against the decision in application GAR051-17 dated 21 July 2017.

2.   The Tribunal’s decision of 21 July 2017 is set aside and an order is substituted that time be extended for the commencement of the application for review to 3 March 2017.

CATCHWORDS:

APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – FROM INTERLOCUTORY DECISIONS – LEAVE TO APPEAL – consideration of principles for granting leave to appeal from interlocutory decision – where appeal on question of law – application of s 146 Queensland Civil and Administrative Tribunal Act 2009 (Qld)

APPEAL AND NEW TRIAL – APPEAL - GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – ERROR OF LAW – WHAT IS – GENERALLY – whether the Tribunal erred in law – whether the Tribunal erred on a question of mixed fact and law – whether there was an error of principle

APPEAL AND NEW TRIAL – APPEAL - GENERAL PRINCIPLES – INTERFERENCE WITH DISCRETION OF COURT BELOW – IN GENERAL – WRONG PRINCIPLE – PARTICULAR CASES – OTHER CASES – where applicant sought extension of time to seek review of decision by respondent regarding termination of building contract – where Tribunal failed to appreciate the substance of the applicant’s case – where Tribunal erred in finding that the applicant had no reasonable prospect of success in the substantive application – where Tribunal erred in placing undue weight on applicant’s explanation for delay in commencing review proceeding – where Tribunal erred in making findings of fact and in determining issues not before the Tribunal for decision – where error in judicial method – where error in exercise of discretion

Adam P Brown Male Fashions Pty Ltd v Philip Morris Inc [1981] 148 CLR 170
Ericson v Queensland Building and Construction Commission [2014] QCA 297
Mace v Murray [1955] 92 CLR 370
Mirana Investments Pty Ltd & Ors v Coupe [2012] QCATA 187
Mitchamy Developments Pty Ltd v Morrison and Walsh [2010] QCATA 51
Norbis v Norbis [1986] 161 CLR 513

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 20, s 142, s 146, s 147

APPEARANCES & REPRESENTATION:

Applicant:

M Doyle of counsel, instructed by Crouch & Lyndon Lawyers

Respondent:

R M De Luchi of counsel, instructed by the Respondent

REASONS FOR DECISION

Proceedings and Jurisdiction

  1. The applicant is a building company (‘the builder’) of which Mr Adrian Harper is the sole director.

  2. On 22 December 2016 a decision by a Review Officer of the respondent Commission was notified to the builder, in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Harper Property Builders Pty Ltd v Queensland Building and C... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] QCATA 70
Decision Date

CaseChat Overview and Summary

The case of Harper Property Builders Pty Ltd v Queensland Building and Construction Commission involved an appeal against an interlocutory decision made by the Queensland Civil and Administrative Tribunal (QCAT). The central dispute was whether the Tribunal erred in denying the builder's application for an extension of time to seek review of a decision regarding the termination of a building contract. The appeal was heard by the Supreme Court of Queensland.

The key legal issues before the Court were whether the Tribunal had erred in law, specifically by failing to appreciate the substance of the builder's case, by placing undue weight on the builder's explanation for the delay in commencing the review proceeding, and by making findings of fact and determining issues not properly before it. The Court also considered whether there was an error in the Tribunal's exercise of discretion in denying the extension of time.

The Court found that the Tribunal had indeed erred in law. It was determined that the Tribunal failed to properly appreciate the builder's case, and that there was a failure of natural justice. The Tribunal's approach was found to be akin to deciding the case on the merits, despite the preliminary and interlocutory nature of the application. The Tribunal also erred by placing undue weight on the builder's explanation for the delay and by making findings of fact and determining issues that were not before it. The Court found that these errors constituted a failure to understand the substance of the builder's case and a failure in judicial method.

The Court granted leave to the builder to appeal against the QCAT decision. It set aside the Tribunal's decision of 21 July 2017 and substituted an order extending the time for the builder to commence the application for review to 3 March 2017.

Orders

Orders of the court

1. Leave is granted to the applicant to appeal against the decision in application GAR051-17 dated 21 July 2017.

2. The Tribunal’s decision of 21 July 2017 is set aside and an order is substituted that time be extended for the commencement of the application for review to 3 March 2017.

Background

Background to the litigation

It is difficult to resist the conclusion that excessive adverse weight was accorded to this factor.Member's Determination of Facts It was submitted for the builder that the learned Member approached his task as if he were deciding the case on the merits, despite the preliminary interlocutory nature of the application. This, it was said, resulted in a failure of natural justice. A significant part of the learned Member’s reasons for judgment consists of actual findings of fact and of final conclusions upon the evidence. The following paragraphs in the reasons for judgment are sufficient to demonstrate this:[42][51] The attempted rectification by the builder, by constructing concrete bond beams between the pads, was wholly unsatisfactory and ineffective. Again, it is apparent that the bond beams have been done in a poor and amateurish manner, and the evidence is that the beams were not completed between all posts.…[58] The stumping works were not carried in an appropriate and skilful way, and with reasonable care and skill, as noted by the engineers. This constituted a substantial breach of the contract.…[60] I do not accept that suggestion. The progress of the works should have been significantly and adversely affected by the need to rectify the stumps. The stumping works are of core structural significance. No further works should have been conducted whilst the building was in an unsecured and potentially dangerous state, with the risk of damage occurring to further new work which was being performed. A major structural defect such as the stumps should have been addressed as soon as possible, and before further work was conducted.[61] I consider that the failure to rectify the defective stumps, once the defects were identified, was a substantial breach of the contract. The substantial breaches of the Contract gave the owners the right to terminate the Contract.[62] I consider that the owners were justified in terminating the Contract on 19 July 2016. I agree with the opinion of Mr Pacey that the Contract was properly terminated. I do not consider that the application to review by the builder has any reasonable prospect of success.[42]Ibid, [51], [58], [60], [61], [62]. We are conscious that, in discussing the possible strength of a case, it may happen that the judgment-writer strays into language that resembles the actual trying of the case. However, the making of actual findings of fact and the reaching of apparently final conclusions such as those expressed in the above paragraphs suggests that the learned Member did indeed approach the task as a fact-finder and that he tried issues that were not before him for decision. We have also considered the possibility that such an approach simply reflects an over-zealous attempt to reach a view on the merits of the builder's case. But it is inescapable that the judgment goes beyond mere looseness of expression and reveals error in method. More importantly, for reasons earlier stated, the learned Member's factual analysis in the end reveals a failure to understand the substance of the builder's case.

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established