CITATION: Hail Creek Coal Holding Pty Limited & Ors v Michelmore [2021] QLC 19 PARTIES: Hail Creek Coal Holding Pty Limited, Marubeni Coal Pty Ltd, Nippon Steel Australia Pty Limited, Sumisho Coal Development Queensland Pty Ltd
(applicants)v Ian Ferguson Michelmore
(respondent)FILE NO: MRA119-20 PROCEEDING: Determination of compensation payable for grant of mining lease DELIVERED ON: 27 May 2021 DELIVERED AT: Brisbane HEARD ON: 1, 2, 3 & 5 March 2021; 13 & 14 April 2021; 10 May 2021 HEARD AT: Brisbane MEMBER: PG Stilgoe OAM ORDERS: 1. I determine compensation in the sum of Five Hundred and Thirty Thousand, Five Hundred and Thirty Dollars ($530,530), inclusive of the statutory 10% uplift, payable within 14 days of the grant of the mining lease.
I order any submissions seeking a costs order in this proceeding must be filed and served within 14 days of the publication of these reasons.2.
CATCHWORDS: ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – COMPENSATION – where the applicant has lodged an application for a mining lease situated on the land of the respondent – where the applicant had already constructed an accommodation village in the subject land – where the applicant has a lease of the subject land from the respondent – what compensation was payable under s 281(3) of the Mineral Resources Act 1989 – what value can be given to the surface of the land – whether the direct method of valuation should be adopted for the purpose of compensation – whether the net present value method of compensation should be adopted
Land Court Rules 2000 r 24C
Mineral Resources Act 1989 s 281Allianz Australia Insurance Limited v Mashaghati [2017] QCA 127, cited
Antrim Truck Centre Ltd v Ottawa (City) [2009] OMBD No 1, cited
Bingham v Cumberland County Council (1954) 20 LGR (NSW) 1, applied
Commissioner of Succession Duties (SA) v Executor Trustee and Agency Co of South Australia Ltd (1947) 74 CLR 358, cited
de Gobeo v de Gobeo (2003) MBQB 274, 179 Man R (2d) 200, cited
Estate of James v Valuer-General (1942) 15 LGR (NSW) 110, cited
Leichhardt Municipal Council v Seatainer Terminals Pty Ltd (1981) 48 LGRA 409, cited
Love v Acuity Investment Management Inc (2009) 74 CCEL (3d) 272, cited
McBarnon v Traffic Authority New South Wales (1995) 87 LGERA 238, cited
Seatainer Terminals Pty Ltd v Valuer-General (1974) 29 LGRA 6, cited
Spencer v The Commonwealth (1907) 5 CLR 418, applied
Vyicherla Naryana Gajapatirajup Bahadur Garu v Revenue Divisional Officer, Vizagapatam [1939] AC 302, cited
WM & TJ Fischer v Valuer General (1983) 9 QLCR 44, citedAPPEARANCES: DG Clothier QC (instructed by Allens) for the applicants
GA Thompson QC, with E Morzone QC (instructed by Emanate Legal) for the respondent
There has been a mining camp on Fort Cooper since 2004. Ian Ferguson Michelmore owns Fort Cooper. The applicant, Hail Creek Holdings Pty Limited, manages the Hail Creek Mine, which is on a…
Keep reading for free
Create a free CaseChat account to read Hail Creek Coal Holding Pty Limited v Michelmore and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] QLC 19
- Decision Date
CaseChat Overview and Summary
The key legal issues for the CAT to address were whether the direct method of valuation should be used to determine the compensation or if the net present value method was more suitable. The direct method involves assessing the land's value based on its immediate utility, whereas the net present value method considers the future earnings potential of the land. The tribunal had to decide which method best reflected the value of the land's surface in the context of a mining lease.
In its decision, the tribunal determined that the direct method of valuation was appropriate for this case. The tribunal concluded that the value of the land's surface was not influenced by the potential for future mining operations. It was decided that the compensation payable should reflect the immediate value of the land and any improvements made to it. The tribunal calculated the compensation to be $530,530, inclusive of the statutory 10% uplift. This amount was to be paid within 14 days of the grant of the mining lease.
The tribunal's final orders included the determination of the compensation amount and a directive for any submissions regarding costs to be filed and served within 14 days of the publication of the tribunal's reasons.
Orders
Orders of the court
1. I determine compensation in the sum of Five Hundred and Thirty Thousand, Five Hundred and Thirty Dollars ($530,530), inclusive of the statutory 10% uplift, payable within 14 days of the grant of the mining lease.
I order any submissions seeking a costs order in this proceeding must be filed and served within 14 days of the publication of these reasons.2.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi