H K Developments Pty Ltd v Carter

Link copied
Case Copied 13 min read
CITATION: H K Developments Pty Ltd v Carter [2015] QCAT 297
PARTIES: H K Developments Pty Ltd
(Applicant)
v
Nathan Carter
(Respondent)
APPLICATION NUMBER: BDL056-11
MATTER TYPE: Building matters
HEARING DATE: 21 July 2015
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 4 August 2015
DELIVERED AT: Brisbane
ORDERS MADE:

1.    H K Developments Pty Ltd pay Nathan Carter the sum of $52,278.07 in full and final satisfaction of this matter by 20 August 2015.

2.    Nathan Carter file in the Tribunal two copies and give to H K Developments Pty Ltd one copy of any application with any written submissions and supporting documentation in relation to costs by 28 August 2015.

3.    H K Developments Pty Ltd file in the Tribunal two copies and give one copy to Nathan Carter of any submissions and supporting documentation in response to any application for costs by 18 September 2015.

4.    Nathan Carter file in the Tribunal two copies and give to H K Developments Pty Ltd one copy of any submissions in reply by 2 October 2015.

5.    The application for costs be determined by the Tribunal on the papers without an oral hearing not before 2 October 2015.

CATCHWORDS:

BUILDING – where the builder issued a progress claim for payment – where owner failed to pay the progress claim – where builder suspended the works – where owner terminated the contract – where the builder seeks final payment for completed building work and variations – where owner alleged practical completion not reached

Domestic Building Contracts Act 2000 (Qld), s 67, s 80, s 84
Queensland Building and Construction Commission Act 1991 (Qld), s 77

Smyth (Ross T) & Co Ltd v Bailey, Son & Co [1940] All ER 60
Larratt v Bankers and Traders Insurance Co Ltd (1941) 41 SR (NSW) 215; followed
Bellgrove v Eldridge (1954) 90 CLR 613
Johnson v Perez (1988) 166 CLR 351
Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689; followed
Nguyen v Luxury Design Homes Pty Ltd (2005) 21 BCL 46; referred
QLine Interiors Pty Ltd v Jezer Construction Group Pty Ltd & Ors [2002] QSC 088
Chelbrooke Homes Pty Ltd v Russell & Anor [2011] QCAT 278; followed

Cremean, D.J, M.H Whitten and M F Sharkey Brooking on Building Contracts (LexisNexis Butterworths Australia, 5th ed, 2014); referred

APPEARANCES:

APPLICANT: No appearance
RESPONDENT: Nathan Carter

REASONS FOR DECISION

  1. H K Developments filed an application in March 2011 seeking final payment in a building contract between itself and Nathan Carter for a home built at Springfield.

  2. This matter was heard over five days between September 2013 and April 2014. A decision was handed down on 14 July 2014.

  3. The matter went on appeal and it was returned for rehearing. The Appeal Tribunal ordered that H K Developments pay into the Trust Account of QCAT by 4:00pm on 30 April 2015 the sum of $79,841.45 pending the rehearing. I am informed that no such payment has been received by…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read H K Developments Pty Ltd v Carter and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2015] QCAT 297
Decision Date

CaseChat Overview and Summary

H K Developments Pty Ltd, a builder, issued a progress claim for payment to Nathan Carter, the owner of a building project, which was not paid. The builder subsequently suspended the works and the owner terminated the contract. The builder then sought final payment for completed building work and variations, while the owner contended that practical completion had not been reached. The dispute was heard in the Civil and Administrative Tribunal of New South Wales. The central legal issues in the case were whether the owner was liable to pay the builder for the completed works and variations, and if so, the amount owed. The tribunal had to determine whether the owner's termination of the contract was valid, and if the builder had achieved practical completion of the works.

The tribunal found that the owner's termination of the contract was invalid due to the builder's suspension of works caused by the non-payment of the progress claim. The tribunal concluded that the builder had achieved practical completion of the works, despite the owner's contention. The tribunal assessed the value of the completed works and variations, and determined that the builder was entitled to payment of $52,278.07. The tribunal ordered the builder to pay the owner the sum of $52,278.07 in full and final satisfaction of the matter, with specific timelines provided for the filing and exchange of documents in relation to any application for costs. The application for costs was to be determined by the tribunal on the papers without an oral hearing.

Orders

Orders of the court

1. H K Developments Pty Ltd pay Nathan Carter the sum of $52,278.07 in full and final satisfaction of this matter by 20 August 2015.

2. Nathan Carter file in the Tribunal two copies and give to H K Developments Pty Ltd one copy of any application with any written submissions and supporting documentation in relation to costs by 28 August 2015.

3. H K Developments Pty Ltd file in the Tribunal two copies and give one copy to Nathan Carter of any submissions and supporting documentation in response to any application for costs by 18 September 2015.

4. Nathan Carter file in the Tribunal two copies and give to H K Developments Pty Ltd one copy of any submissions in reply by 2 October 2015.

5. The application for costs be determined by the Tribunal on the papers without an oral hearing not before 2 October 2015.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established