Group Konstrukt Pty Ltd v Arrow International Ltd

Link copied
Case Copied 16 min read

GROUP KONSTRUKT PTY LTD v ARROW INTERNATIONAL LTD
[2011] ACTSC 14 (4 FEBRUARY 2011)

PRACTICE AND PROCEDURE – pleading – action by subcontractor against builder – defence and counterclaim – counterclaim failed to set out material facts relied on – previous similar defects – whether point reached where counterclaim should be struck out – defendant given final opportunity to produce draft defence and counterclaim in satisfactory form

Court Procedures Rules 2006 (ACT), rr 21, 405, 406, 430, 431, 441 and 470.

Aon Risk Services Ltd v Australian National University (2009) 239 CLR 175
Canberra Data Centres Pty Ltd v Vibe Constructions (ACT) [2010] ACTSC 20
Bruce v Odhams Press Ltd [1936] 1 KB 697
Banque Commerciale SA (in liquidation) v Akhil Holdings Ltd (1990) 169 CLR 279
Mulltigroup Distibution Services v TNT Australia Pty Ltd [1996] ATPR 41-552
McMahon v John Fairfax Publications Pty Ltd [2010] NSWCA 308

No.  SC 359 of 2008

Judge:             Master Harper
Supreme Court of the ACT

Date:              4 February 2011

IN THE SUPREME COURT OF THE     )
  )          No.  SC 359 of 2008
AUSTRALIAN CAPITAL TERRITORY           )

BETWEEN:GROUP KONSTRUKT PTY LTD

ACN 111 141 336

Plaintiff

AND:ARROW INTERNATIONAL LTD

ABN 081 136 352

First Defendant

ORDER

Judge:  Master Harper
Date:  4 February 2011
Place:  Canberra

THE COURT ORDERS THAT:

  1. The defendant have until 4 April 2011 to deliver to the plaintiff’s solicitors a draft further amended defence and counterclaim in conformity with these reasons.

  1. Each party be at liberty to have the matter listed in the Friday applications list on seven days’ notice to the other.

  1. Proceedings in this building case were commenced on 9 May 2008. The application presently before the court is brought by the plaintiff seeking relief in relation to what it submits is a defective defence and counterclaim. There is also a dispute about security for costs.

  1. The claim arises from the refurbishment during 2007 and 2008 of the Chisholm Village Shopping Centre in the southern suburbs of Canberra. The shopping centre, which included a Coles Supermarket as lead tenant, was and may still be owned by Over Fifty Funds Management Ltd. That company engaged the defendant as head contractor to undertake substantial building work at the site. The defendant engaged the plaintiff as a subcontractor to provide carpentry and associated works.

  1. The plaintiff claims some $250,000.00 as payable under the subcontract, plus interest and costs.

  1. The subcontract was wholly in writing, and consisted of a document entitled MBAV Copyright Form SC 6 Subcontract Document, numbered 219100CA and dated 16 May 2007. The defendant says that the subcontract between the parties included a quotation from the plaintiff and a letter of acceptance from the defendant. The contract referred to the head contract between the owner and the defendant which the plaintiff acknowledged having inspected or at least having had a reasonable opportunity to do so.

  1. It was a term of the subcontract that the plaintiff would carry out and complete the work described in the first schedule to the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Group Konstrukt Pty Ltd v Arrow International Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] ACTSC 14
Decision Date

CaseChat Overview and Summary

Group Konstrukt Pty Ltd, the plaintiff, initiated legal proceedings against Arrow International Ltd, the defendant, in relation to a subcontractor's dispute. The plaintiff sought compensation for damages and losses incurred due to the defendant's alleged failure to meet contractual obligations. The defendant responded by filing a defence and a counterclaim, asserting that the plaintiff had breached the contract and caused the alleged defects. The case was heard by the Supreme Court of New South Wales, which was tasked with resolving the conflicting claims and determining the appropriate legal remedies.

The primary legal issue before the court was whether the defendant's counterclaim was sufficiently particularised. The plaintiff argued that the defendant's counterclaim failed to specify the material facts upon which it relied, particularly with regard to previous similar defects. The court needed to determine whether the point had been reached where the counterclaim should be struck out, and if so, whether the defendant should be granted a final opportunity to amend its pleadings. The court also had to consider the appropriate timeline for the defendant to submit a revised defence and counterclaim.

In its judgment, the court held that the defendant's counterclaim did not adequately set out the material facts relied upon, particularly in relation to previous similar defects. However, the court was inclined to give the defendant a final opportunity to rectify this deficiency. The court noted that the defendant had already had several opportunities to amend its pleadings, and it was not prepared to allow the matter to proceed without a properly particularised counterclaim. The court set a deadline of 4 April 2011 for the defendant to submit a draft further amended defence and counterclaim in conformity with the reasons provided. The court also allowed each party the liberty to list the matter in the Friday applications list on seven days' notice to the other party.

The court's orders mandated that the defendant deliver a draft further amended defence and counterclaim to the plaintiff's solicitors by 4 April 2011. Additionally, each party was granted the liberty to have the matter listed in the Friday applications list on seven days' notice to the other party. These orders aimed to ensure that the case could progress with properly particularised pleadings and to facilitate the efficient management of the litigation process.

Orders

Orders of the court

1. The defendant have until 4 April 2011 to deliver to the plaintiff’s solicitors a draft further amended defence and counterclaim in conformity with these reasons.

2. Each party be at liberty to have the matter listed in the Friday applications list on seven days’ notice to the other.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.