Groove Properties Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 26 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Groove Properties Pty Ltd v Queensland Building and Construction Commission [2022] QCAT 191

PARTIES: GROOVE PROPERTIES PTY LTD

(applicant)

V

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S:

GAR 342-20

MATTER TYPE:

General administrative review matters

DELIVERED ON:

17 May 2022

HEARING DATE:

25 January 2022

HEARD AT:

Brisbane

DECISION OF:

Member Lember

ORDERS:

1.       The decision of the Queensland Building and Construction Commission dated 28 August 2020 to issue a direction to rectify defective building work to Groove Properties Pty Ltd is confirmed.

2.       Any application for costs is to be made by filing in the Tribunal two (2) copies and giving one (1) copy of any submissions and evidence to be relied upon to the other party by 4:00pm on that date which is twenty-eight days after the date of this order.

3.       If an application for costs is made in accordance with order 2:

(a)    the other party is to file in the Tribunal two (2) copies and give one (1) copy to the party making the application any submissions and evidence in response by 4:00pm on that date which is twenty-eight days after the date in order 2; and

(b)   the application will be determined on the papers and without an oral hearing unless a party requests an oral hearing not before 4:00pm on that date which is twenty-eight days after the date in order 2.

4.       If no application for costs is made in accordance with order 2, there will be no order as to costs in this proceeding.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – where review of direction to rectify defective building works –– whether issue of water ingress is defective work – whether fair to give direction to rectify

Queensland Building and Construction Commission Act 1991 (Qld) s 3, s 71, s 72, s 71A, s 74, s 75, s 86, s 86C, s 87

Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 9(1), s 17(1), s 19, s 20, s 21, s 23, s 28, s 29, s 100
Statutory Instruments Act 1992 (Qld) s 7

Queensland Building and Construction Commission “Insurance Policy Conditions, Edition 8”

ABG83 Pty Ltd v Queensland Building and Construction Commission [2019] QCAT 386

Briginshaw v Briginshaw (1938) 60 CLR 336
Cormack v Queensland Police Service – Weapons Licensing Unit [2015] QCATA 115
Cowen & Anor v QBCC & Anor [2017] QCAT 416
Dixon Projects Pty Ltd v QBSA [2009] QCCTB 2
Don Mackay Pty Ltd v Queensland Building Services Authority [2009] QCCTB 259
Duke Building Ltd v Queensland Building and Construction Commission & Ors [2015] QCAT 397
Holtham v Queensland Building and Construction Commission [2018] QCAT 316
JM Kelly (Project Builders) Pty Ltd v QBSA [2010] QCAT 568
Taouk v QBSA [2013] QCAT 508
Walker v Queensland Building and Construction Commission [2014] QCAT 228

Wright & Anor v Duke Building Pty Ltd & Anor [2017] QCATA 35

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented

Respondent:

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Groove Properties Pty Ltd v Queensland Building and Construc... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 191
Decision Date

CaseChat Overview and Summary

Groove Properties Pty Ltd has applied to the Queensland Civil and Administrative Tribunal (QCAT) to review a decision by the Queensland Building and Construction Commission (QBCC) to issue a direction to rectify defective building works. The QBCC issued the direction following a complaint by the homeowner that water was penetrating the rear balcony of a two-storey house built by Groove Properties Pty Ltd. The QBCC inspected the property, but could not detect water penetration. However, the homeowner subsequently conducted a water test that did show water penetration, and this result was accepted by the QBCC. Groove Properties Pty Ltd submits that there is no water penetration to the rear balcony and that the QBCC failed to adequately investigate the issue. The QBCC submits that it is fair to require Groove Properties Pty Ltd to rectify the defective building works given the homeowner is entitled to the construction being completed free of defects, the defect has been enduring since shortly after the works were completed, and the defect will, if left unrectified, create substantial damage to building elements. The tribunal confirms the direction to rectify, finding that there is water penetration to the rear balcony, the water penetration is due to the failure by Groove Properties Pty Ltd to construct the rear balcony in such a manner as to prevent water penetration, and it is not unfair to give a direction to rectify to Groove Properties Pty Ltd. The question of costs is reserved pending an application.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established