CITATION: | Cowen & Anor v Queensland Building and Construction Commission & Anor [2017] QCAT 416 |
PARTIES: | Peter Cowen |
| v | |
| Queensland Building and Construction Commission Hinterland Constructions Pty Ltd (Second Respondent) | |
APPLICATION NUMBER: | GAR044-15; GAR113-16 |
MATTER TYPE: | General administrative review matters |
HEARING DATES: | GAR044-15: 8, 9 February 2016; 4, 5 May 2016; 14 September 2016 GAR044-15 and GAR113-16: 13, 14, 15, 16, 17, 21, 22, 23 February 2017 |
HEARD AT: | Brisbane |
DECISION OF: | A/Senior Member Browne |
DELIVERED ON: | 27 November 2017 |
DELIVERED AT: | Brisbane |
ORDERS MADE: | In GAR044-15: 1. The decision made by the Queensland Building and Construction Commission of 22 December 2014 to decline a claim for non-completion under clause 1.2 of the Insurance Policy Conditions is set aside. 2. The Tribunal substitutes its own decision that Peter Cowen and Jan Cowen did validly terminate the contract dated 18 February 2013 and the claim for non-completion under clause 1.2 of the Insurance Policy Conditions is accepted. In GAR113-16: 1. The decision made by the Queensland Building and Construction Commission of 14 February 2017 not to issue a direction to rectify to Hinterland Constructions Pty Ltd for items 1(b), 1(c), 1(d), 3, 4(a), 4(d), 4(e), 5, 7, 8, 10, 14, 17, 18(a), 18(b), 18(c), 18(e), 21, 23(a), 25, 26, 27, 28 and 31 referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) is confirmed. 2. The decision made by the Queensland Building and Construction Commission of 14 February 2017 not to issue a direction to rectify to Hinterland Constructions Pty Ltd for items 1(a), 1(e), 1(f), 1(g), 2, 4(b), 4(c), 12, 13, 15, 16, 18(d), 23(b) and 23(c) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) is set aside. 3. The Tribunal substitutes its own decision that: a) For items 1(a), 1(e), 1(f), 1(g), 2, 12, 13, 23(b) and 23(c) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) the matter be returned to the QBCC for reconsideration pursuant to s24(1)(c) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld); b) For items 4(b) and 4(c), 15, 16 and 18(d) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) a direction to rectify should not be issued to Hinterland Constructions Pty Ltd. |
CATCHWORDS: | PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE – RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – HOME WARRANTY INSURANCE – where decision made to decline a claim for non-completion under clause 1.2 of the QBCC Home Warranty Insurance Scheme Policy Conditions – where homeowner filed an application to review the decision – whether contract properly terminated by the homeowner PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE – RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where decision made not to issue a direction to rectify to the builder – where homeowner filed an application to review the decision – whether items of work are defective work – whether fair… |
Keep reading for free
Create a free CaseChat account to read Cowen & Anor v Queensland Building and Construction Commissi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCAT 416
- Decision Date
CaseChat Overview and Summary
The legal issues before the QCAT included whether the Cowens had validly terminated their contract with the builder and whether the QBCC had correctly assessed the defectiveness of the work and the fairness of issuing a direction to rectify. The QCAT considered the relevant statutory provisions, the terms of the contract, and the evidence presented by both parties. The Court also examined the QBCC's decision-making process and whether it had properly applied the relevant policies and guidelines.
The QCAT found that the QBCC had erred in its decision to decline the Cowens' claim for non-completion. The Tribunal concluded that the Cowens had validly terminated the contract and that the QBCC's assessment of the defectiveness of the work and the fairness of issuing a direction to rectify was flawed. The Tribunal set aside the QBCC's decision in relation to the Cowens' claim and substituted its own decision that the claim should be accepted. In relation to the second application, the Tribunal confirmed the QBCC's decision not to issue a direction to rectify for certain items but set aside the decision for other items and ordered the QBCC to reconsider those items.
The final orders of the Tribunal were that the decision to decline the Cowens' claim for non-completion was set aside and the claim was accepted. For the second application, the Tribunal confirmed the QBCC's decision not to issue a direction to rectify for certain items but set aside the decision for other items and ordered the QBCC to reconsider those items. The Tribunal also ordered that the matter be returned to the QBCC for reconsideration for certain items where the QBCC had not issued a direction to rectify.
Orders
Orders of the court
In GAR044-15:
1. The decision made by the Queensland Building and Construction Commission of 22 December 2014 to decline a claim for non-completion under clause 1.2 of the Insurance Policy Conditions is set aside.
2. The Tribunal substitutes its own decision that Peter Cowen and Jan Cowen did validly terminate the contract dated 18 February 2013 and the claim for non-completion under clause 1.2 of the Insurance Policy Conditions is accepted.
In GAR113-16:
1. The decision made by the Queensland Building and Construction Commission of 14 February 2017 not to issue a direction to rectify to Hinterland Constructions Pty Ltd for items 1(b), 1(c), 1(d), 3, 4(a), 4(d), 4(e), 5, 7, 8, 10, 14, 17, 18(a), 18(b), 18(c), 18(e), 21, 23(a), 25, 26, 27, 28 and 31 referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) is confirmed.
2. The decision made by the Queensland Building and Construction Commission of 14 February 2017 not to issue a direction to rectify to Hinterland Constructions Pty Ltd for items 1(a), 1(e), 1(f), 1(g), 2, 4(b), 4(c), 12, 13, 15, 16, 18(d), 23(b) and 23(c) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) is set aside.
3. The Tribunal substitutes its own decision that:
a) For items 1(a), 1(e), 1(f), 1(g), 2, 12, 13, 23(b) and 23(c) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) the matter be returned to the QBCC for reconsideration pursuant to s24(1)(c) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld);
b) For items 4(b) and 4(c), 15, 16 and 18(d) referred to in the Scott Schedule (identified as ‘Exhibit 24’ in these proceedings) a direction to rectify should not be issued to Hinterland Constructions Pty Ltd.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi