| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
COMMON LAW DIVISION
PROPERTY LIST
S ECI 2025 03042
BETWEEN:
| JULIAN GRECH | Plaintiff |
| v | |
| BILTAR PTY LTD (ACN 619 785 143) | Defendant |
---
JUDGE: | Efthim AsJ |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 12 September 2025 |
DATE OF JUDGMENT: | 8 October 2025 |
CASE MAY BE CITED AS: | Grech v Biltar Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2025] VSC 636 |
---
SPECIFIC PERFORMANCE – Building contract – Delay in completing the rectification work under the contract – Whether specific performance is an adequate remedy – Mayor, Aldermen and Burgesses of Wolverhampton v Emmons [1901] 1 QB 515 applied – Whether the scope of work is clearly defined – Whether damages are a more adequate remedy.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr T Mitchell KC and Ms C Jones | Strongman & Crouch |
| For the Defendant | Mr R Andrew KC and Mr A Morrison | KCL Law |
Contents
Legal principles
Is the work defined by the contract?
Damages and alternative remedy
Access to the premises
Conclusion
HIS HONOUR:
The plaintiff, Julian Grech, applies for orders that the defendant, Biltar Pty Ltd, specifically perform its obligations under a deed of settlement and release dated 21 May 2024 (‘the Deed’) to carry out and complete building rectification works to the satisfactory of an independent expert appointed under the Deed.
Background
The plaintiff is the owner of Lot 6, 8268 Murray Valley Highway, Bathumi, which is located on the Murray River, near the border of Victoria and New South Wales. He purchased the property with the intention of building a new dwelling that would eventually be the home where the plaintiff and his wife would retire.
On 13 April 2022, the plaintiff entered into a contract with the defendant, for the construction of a double storey dwelling at the property for a price of $1,833,174.02. The completion date under the contract was 17 October 2023 (Clause 8.4) but by 17 October 2023, the works at the property had not been completed.
On 2 June 2023, the defendant terminated the employment of a carpenter, Cameron Boyle, because the defendant was struggling with ‘cash flow’ issues. One of the main reasons for defendant’s ‘cash flow’ issues at that time, was the plaintiff’s late payment of the April Claim and the resulting impact this had on the business.[1]
[1]Paragraph 26 of the affidavit of Benjamin Lindsay Carr, sworn 15 August 2025, which has not been contradicted by the plaintiff
On 9 June 2023, Benjamin Lindsay Carr, the defendant’s director, received a telephone call from Brendan Elliott, the defendant’s foreman. Mr Elliot advised Mr Carr that the plaintiff was at the land and verbally abused him. He also told Mr Carr that he was distressed, felt like breaking down and did not want to work at the land again.[2]
[2]Paragraph 23 of the affidavit of Benjamin Lindsay Carr, sworn 15 August 2025, which has not been contradicted by the plaintiff.
On 15 August 2023, Mr Carr had another conversation with Brendan Elliott. Mr…
Continue reading Grech v Biltar Pty Ltd
Sign in free to access the full text
- AGLC
- Grech v Biltar Pty Ltd [2025] VSC 636
- Case
- [2025] VSC 636
- Decision Date
CaseChat Overview and Summary
The court considered the established principle from Mayor, Aldermen and Burgesses of Wolverhampton v Emmons that specific performance may not be appropriate if the scope of the work is not clearly defined or if there has been a delay that affects the adequacy of the remedy. In this case, the court scrutinised the contract to determine whether the scope of the rectification work was sufficiently defined. It also evaluated the extent of the delay and its impact on the adequacy of specific performance. The court concluded that the delay and the lack of precise definition of the rectification work made specific performance an inadequate remedy. The court found that damages would be a more appropriate remedy, given the circumstances.
In summary, the court held that specific performance was not an adequate remedy in this case due to the delay in completing the work and the unclear scope of the rectification work. The court determined that damages would be a more suitable remedy for the plaintiff's losses. The court ordered that the defendant pay damages to the plaintiff for the breach of contract.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.