GRD Group (NT) Pty Ltd v K & J Burns Electrical Pty Ltd [2010] NTSC 34

PARTIES:  GRD GROUP (NT) PTY LTD
v
K & J BURNS ELECTRICAL PTY LTD

and

BRIAN GALLAUGHER

TITLE OF COURT:  SUPREME COURT OF THE
NORTHERN TERRITORY
JURISDICTION:  SUPREME COURT OF THE
NORTHERN TERRITORY
EXERCISING TERRITORY
JURISDICTION
FILE NO:  No 44 of 2010 (21014265)
DELIVERED:  28 June 2010
HEARING DATES:  12 May 2010
JUDGMENT OF:  MILDREN J
CATCHWORDS: 

CONTRACTS – subcontract – construction of contracts – payment claims and security – criteria for valid payment claim – retention monies in subcontract for security – late completion of subcontract – reconciliation statements – time for payment of payment claims – whether tax invoices amount to payment claims – strict compliance for valid payment claim – whether repeat claims can be authorised by contract – motion for a declaration that the determination is void – stay of the judgment

ADMINISTRATIVE LAW – JURISDICTION – ADMINISTRATIVE
TRIBUNAL – adjudicator’s jurisdiction – jurisdictional error – adjudication
of construction of contracts – claim for declaration that determination by
adjudicator void – time to have payment dispute adjudicated in contracts –
whether adjudicator wrongly construed the Act – whether the adjudicator
fell into jurisdictional error on construing the Act
Construction Contracts (Security of Payment) Act, s 8(a), s 12, s 19 , s 28,
s 28(1), s 33(1)(a)(ii), s 33(1)(a)(iv)(A), s 45, s 48(1), s 48(3)
Supreme Court Act (NT)
Supreme Court Act 1970 (NSW), s 69(3), s 69(4)

Supreme Court Rules, O.56, O.56.01

Ford, (In) Security of Payments (2010) 1 NTLJ 165

Australian Constructions Pty Ltd v Nilsen (SA) Pty Ltd (2008) 23 NTLR

123; Craig v South Australia (1995) 184 CLR 163; applied

A J Lucas Operations Pty Ltd v Mac-Attack Equipment Hire Pty Ltd (2009)

25 NTLR 14; followed

Kirk v Industrial Relations Commission of New South Wales (2010) 239

CLR 531; referred to

REPRESENTATION:

Counsel:

 Plaintiff:  W Roper
Defendant:  A Wyvill SC

Solicitors:

Plaintiff:  Hunt & Hunt
 Defendant:  Ward Keller

Judgment category classification: B

Number of pages:  14
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

GRD Group (NT) Pty Ltd v K & J Burns Electrical Pty Ltd [2010] NTSC 34

No 44 of 2010 (21014265)

BETWEEN:

GRD GROUP (NT) PTY LTD

Plaintiff

AND:

K & J BURNS ELECTRICAL PTY LTD

and BRIAN GALLAUGHER

Defendants

CORAM:  MILDREN J

REASONS FOR JUDGMENT

(Delivered 28 June 2010)

Introduction

  1. On 25 February 2009, K & J Burns Electrical Pty Ltd (Burns) entered into a subcontract with GRD Group (NT) Pty Ltd (GRD) to undertaken electrical works on land situated at Lot 7100 Brewery Lane, Woolner, Northern Territory for a lump sum price of $354,860 (the Subcontract).

  2. Throughout the course of the Subcontract, Burns submitted 13 invoices to GRD for progress payments totalling $393,274.51, which sum included claims for extras or variations totalling $38,414.50.

  3. GRD made progress payments in relation to the first seven invoices totalling $309,959.47, leaving a balance allegedly payable under…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read GRD Group (NT) Pty Ltd v K and J Burns Electrical Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2010] NTSC 34
Decision Date

CaseChat Overview and Summary

GRD Group (NT) Pty Ltd (GRD) sought a declaration that an adjudication determination was void and a stay of the judgment obtained by the subcontractor, K & J Burns Electrical Pty Ltd (Burns), following the registration of the determination. The dispute arose from a subcontract entered into between GRD and Burns for electrical works on land at Lot 7100 Brewery Lane, Woolner, Northern Territory. The subcontract provided for retention monies as security and for progress payments to be claimed by Burns in accordance with specified requirements. GRD made progress payments for the first seven invoices but withheld a portion of the retention monies. Disputes arose, leading to claims for back charges and liquidated damages for late completion. Burns submitted a summary invoice (SI) claiming the balance allegedly payable under the subcontract. GRD argued that the SI was not a valid payment claim and that the adjudicator lacked jurisdiction to entertain the application. GRD's primary argument was that the adjudicator had no jurisdiction to entertain the application as he wrongly interpreted the Act. The court considered whether the invoices submitted by Burns were valid payment claims under the subcontract and the Act. The court found that the adjudicator erred in finding that strict compliance with the subcontract was necessary for a valid payment claim and that the invoices did not constitute valid payment claims. The court also found that the SI was a valid payment claim for the difference of $7,911.17, and the adjudication was within jurisdiction to that extent. The court concluded that the adjudicator did not have jurisdiction to entertain the SI, except for the amount related to the balance of the retention fund. GRD was entitled to a declaration that the adjudication relating to an amount in excess of $7,911.17 and interest thereon was void and for an order staying the judgment obtained in this Court which exceeds that sum.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established