SUPREME COURT OF QUEENSLAND
CITATION:
Gracemere Surveying and Planning Consultants P/L v Peak Downs Shire Council and Anor [2009] QCA 237
PARTIES:
GRACEMERE SURVEYING AND PLANNING CONSULTANTS PTY LTD (ACN 124 780 445) as agent for D & B CARNE INVESTMENTS PTY LTD (ACN 068 618 600) t/a CAPELLA HOTEL/MOTEL
(appellant/applicant)
v
PEAK DOWNS SHIRE COUNCIL
(respondent/first respondent)
CUPOSA PTY LTD
(ACN 001 285 025)
(respondent/second respondent)FILE NO/S:
Appeal No 72 of 2009
P & E Appeal No 3460 of 2007DIVISION:
Court of Appeal
PROCEEDING:
Application for Leave Integrated Planning Act
ORIGINATING COURT:
Planning and Environment Court at Brisbane
DELIVERED ON:
21 August 2009
DELIVERED AT:
Brisbane
HEARING DATE:
21 July 2009
JUDGES:
Chief Justice, Chesterman JA and Wilson J
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDERS:
1. Application for leave to appeal is refused
2. Applicant to pay the first and second respondent’s costs of the application, to be assessed on the standard basis
CATCHWORDS:
APPEAL AND NEW TRIAL – APPEAL - GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – ERROR OF LAW – WHAT IS – DISTINCTION BETWEEN QUESTION OF LAW AND QUESTION OF FACT – where second respondent was given council approval to develop land into a hotel/motel with a liquor licence in competition with the applicant – where land was designated for certain purposes and approval allowed a material change to those purposes – where the applicant submits that approval is in contravention of the Council planning scheme – whether any conflict constitutes a question of law as required by s 4.1.56(2) of the Integrated Planning Act 1997 (Qld) to appeal
Integrated Planning Act 1997 (Qld), s 4.1.56(2)
Harrow Trust v Adelaide Hebrew Congregation Inc & City of Burnside (2002) 221 LSJS 449; [2002] SASC 308, applied
COUNSEL:
L Kelly SC, with A Skoien, for the applicant
J H Davies for the first respondent
C Hughes SC, with M Williamson, for the second respondentSOLICITORS:
Minter Ellison Lawyers for the applicant
King and Company Solicitors for the first respondent
Connor O’Meara Solicitors for the second respondent
CHIEF JUSTICE: I have had the advantage of reading the reasons for judgment of Chesterman JA. I agree with the orders proposed by His Honour, and with his reasons.
CHESTERMAN JA: Capella is a small country town about 50 kilometres north of Emerald in the central highlands of Queensland, which serves surrounding rural activities and, more recently, mining activities conducted at nearby coalmines. It has a population of about 900. The applicant owns and operates the Capella Hotel/Motel which is the only facility in Capella with a general liquor licence and facilities associated with such a licence. The applicant has benefited from the increase in coalmining activity in recent years with the consequent increase in miners resorting to the town for accommodation and recreation.
The second respondent (“respondent”) proposes to develop land at the southern end of the town into an…
Keep reading for free
Create a free CaseChat account to read Gracemere Surveying and Planning Consultants Pty Ltd v Peak... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2009] QCA 237
- Decision Date
CaseChat Overview and Summary
The court considered the distinction between questions of law and questions of fact in the context of appeals. It noted that questions of law are those that are determinative of the merits of the case, while questions of fact are those that depend on the evidence and findings of fact. The court held that the conflict between the approval and the planning scheme was a question of fact, as it depended on the evidence and findings of fact. The court found that the appellant had not demonstrated that there was an error of law in the decision of the second respondent. The court also noted that the appellant had not demonstrated that there was any other ground for appeal under s 4.1.56(2) of the Act.
The court refused the application for leave to appeal and ordered the appellant to pay the costs of the first and second respondents of the application, to be assessed on the standard basis. The court held that the appellant had not satisfied the requirements for leave to appeal under the Act. The court noted that the appellant had not demonstrated that there was an error of law in the decision of the second respondent, or any other ground for appeal. The court also held that the appellant had not demonstrated that there was any substantial injustice that would be caused by the refusal of leave to appeal.
In summary, the court held that the conflict between the approval and the planning scheme was a question of fact, and that the appellant had not demonstrated that there was an error of law in the decision of the second respondent. The court refused the application for leave to appeal and ordered the appellant to pay the costs of the first and second respondents of the application, to be assessed on the standard basis.
Orders
Orders of the court
1. Application for leave to appeal is refused
2. Applicant to pay the first and second respondent’s costs of the application, to be assessed on the standard basis
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi