CPT Manager Ltd v Central Highlands Regional Council

Link copied
Case Copied 28 min read

SUPREME COURT OF QUEENSLAND

CITATION:

CPT Manager Ltd v Central Highlands Regional Council & Ors [2010] QCA 183

PARTIES:

CPT MANAGER LIMITED
ACN 054 494 307
(appellant/applicant)
v
CENTRAL HIGHLANDS REGIONAL COUNCIL
(respondent/not a party to the application)
LASCORP DEVELOPMENT GROUP AUSTRALIA PTY LTD
(co-respondent/respondent)
CHIEF EXECUTIVE, DEPARTMENT OF MAIN ROADS
(co-respondent by election/not a party to the application)

FILE NO/S:

Appeal No 13584 of 2009
P & E Appeal No 2840 of 2008

DIVISION:

Court of Appeal

PROCEEDING:

Application for Leave Integrated Planning Act

ORIGINATING COURT:

Planning & Environment Court at Brisbane

DELIVERED ON:

23 July 2010

DELIVERED AT:

Brisbane

HEARING DATE:

30 April 2010

JUDGES:

Holmes, Fraser and Chesterman JJA
Separate reasons for judgment of each member of the Court, each concurring as to the order made

ORDER:

Application for leave to appeal refused with costs

CATCHWORDS:

APPEAL AND NEW TRIAL – APPEAL - GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – ERROR OF LAW – WHAT IS – DISTINCTION BETWEEN QUESTION OF LAW AND QUESTION OF FACT – where Council approved respondent’s application for a development permit – where applicant was a business competitor of respondent and unsuccessfully appealed to the Planning & Environment Court – where the Emerald Shire Planning Scheme 2007 applied to the development application – where trial judge held the conflict between the development and the Scheme was minor and there was a strong need for the development – whether the trial judge’s assessment of the degree of conflict between the Scheme and the proposed development was a question of law subject to appeal – whether the trial judge erred in failing to appreciate the existence or extent of the conflict – whether the trial judge erred in failing to properly assess the sufficiency of grounds to overcome the conflict

Integrated Planning Act 1997 (Qld), s 4.1.56
Sustainable Planning Act 2009 (Qld), s 822

ALDI Stores (A Limited Partnership) v Redland City Council[2009] QCA 346, cited
Gracemere Surveying and Planning Consultants P/L v Peak Downs Shire Council & Anor
[2009] QCA 237, followed
Harrow Trust v Adelaide Hebrew Congregation Inc & City of Burnside [2002] SASC 308, cited
Regional Land Development Corp No 1 P/L v Banana SC & Ors [2009] QCA 140, followed
SLS Property Group P/L v Townsville CC & Anor[2009] QCA 380, applied
Weightman v Gold Coast City Council & Anor [2003] 2 Qd R 441; (2002) 121 LGERA 161; [2002] QCA 234, followed

COUNSEL:

S Doyle SC, with M Johnston, for the applicant
D R Gore QC, with J D Houston, for the respondent

SOLICITORS:

Minter Ellison for the applicant
Flower & Hart for the respondent

[1]      HOLMES JA:  I agree with the reasons of Chesterman JA and with the order he proposes.

[2]      FRASER JA:  I respectfully agree with Chesterman JA’s reasons for concluding that no error of law has been identified in this application for leave to appeal.  I would refuse the application for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPT Manager Ltd v Central Highlands Regional Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] QCA 183
Decision Date

CaseChat Overview and Summary

CPT Manager Ltd sought leave to appeal against the Central Highlands Regional Council's decision to approve a development permit for the respondent, a business competitor. The appeal originated from the Planning & Environment Court, which upheld the Council's decision. The Emerald Shire Planning Scheme 2007 was relevant to the development application, and the trial judge concluded that the conflict between the development and the Scheme was minor, with a strong need for the development. The appeal focused on whether the trial judge's assessment of the conflict and the sufficiency of grounds to overcome it was a question of law.

The primary legal issue was whether the trial judge's assessment of the degree of conflict between the Scheme and the proposed development was a question of law, subject to appeal. Additionally, the appeal examined whether the trial judge erred in failing to appreciate the existence or extent of the conflict and whether they erred in failing to properly assess the sufficiency of grounds to overcome the conflict. The Court had to determine whether these issues constituted questions of law or fact.

The Court held that the trial judge's assessment of the degree of conflict between the development and the Scheme was a question of fact, not a question of law. The Court found that the trial judge did not err in assessing the conflict, nor in evaluating the sufficiency of grounds to overcome it. The assessment involved weighing evidence and making judgments about the relative importance of various factors, which are inherently factual determinations. Consequently, the Court refused the application for leave to appeal and ordered CPT Manager Ltd to pay costs.

Orders

Orders of the court

Application for leave to appeal refused with costs

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.