Goldtaper Pty Ltd v Berela Pty Ltd

Case

[2001] QSC 104

10/04/2001


SUPREME COURT OF QUEENSLAND

CITATION:              Goldtaper Pty Ltd  & Ors v Berela Pty Ltd [2001] QSC 104

PARTIES:                 GOLDTAPER PTY LTD (ACN 010 588 815)

(first plaintiff)

HARACLIFF PTY LTD (ACN 010 820 809)

(second plaintiff)

KEMBROOK PTY LTD (ACN 010 839 933)

(third plaintiff)

v

BERELA LIMITED (ACN 010 671 315)

(Defendant) FILE NO/S:  10989/98

DIVISION:               Brisbane Supreme Court Trial Division

PROCEEDING:       Trial

ORIGINATING COURT:

Supreme Court Brisbane

DELIVERED ON:    10 April 2001

DELIVERED AT:     Supreme Court Brisbane

HEARING DATE:     12, 13, 14 March 2001

JUDGES:                  Atkinson J

ORDER:  Plaintiffs awarded damages in sum of $441,747.07.

CATCHWORDS:       CONTRACT  –  CONSTRUCTION  –  Whether  on  proper construction  of  contract  circumstances  have  arisen  since signing  of  contract  entitling  Plaintiffs  to  payment  under contract.

CONTRACT – RECTIFICATION – PRINCIPLES TO BE APPLIED  –  COMMON  INTENTION  –  Whether  mistake made by parties in expression of common intention so that contract does not embody that intention.

CONTRACT – IMPLIED TERMS – Whether implied term of contract that Defendant would do all things necessary to enable Plaintiffs to have benefit of the contract.

Arlenby Marketing Pty Ltd v Chief Executive of the

Queensland Department of Transport P & E Appeal No 39 of

1996, 4 November 1996, considered

2

Australian Course Grains Pool Pty Ltd v Barley Marketing

Board [1989] 1 QR 499, considered

Australian Gypsum Ltd and Australian Plaster Co Ltd v

Hume Steel Ltd (1930) 45 CLR 54, followed

Barque Quilpué Ltd v Brown [1904] 2 KB 264, considered

Butt v McDonald (1896) 7 QLJ 68, followed

Codelfa Construction Pty Ltd v State Rail Authority of NSW

(1982) 149 CLR 337, considered

Fitzgerald v FJ Leonhardt Pty Ltd (1997) 189 CLR 215, considered

Fowler v Fowler (1859) 4 De G & J 250, followed Liverpool City Council v Irwin [1977] AC 239, followed Mackay v Dick (1861) 6 App Cas 251, considered Maralinga Pty Ltd v Major Enterprises Pty Ltd (1973) 128

CLR 336, followed

Marshall v The Colonial Bank of Australia (1904) 1 CLR

633, followed

New South Wales v The Commonwealth (1990) 169 CLR 482, considered

Nullagine Investments Pty Ltd v Western Australian Club Inc, considered

Pacific Exchange Corporation Pty Ltd v Gold Coast City

Council and Anor, P& E Appeal No 32 of 1996, 29 October

1996, considered

Pukallus v Cameron (1982) 180 CLR 447, followed Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596, considered

Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR

359, followed

Slee v Warke (1949) 86 CLR 271, followed

COUNSEL:                J.Bell QC for the Plaintiffs

P.McMurdo QC for the Defendant

SOLICITORS:          Hopgood Ganim Lawyers for the Plaintiffs

Corrs Chambers Westgarth for the Defendant

[1]     In 1993, the plaintiffs, Goldtaper Pty Ltd, Haracliff Pty Ltd and Kembrook Pty Ltd, owned property at Coomera (“the land”).  The northern border of the land was the southern bank of the Coomera River.  The southern border of the land was the Oxenford - Southport Road, also known as the Hope Island Road.  It was zoned

“special  facilities”.    The  area  of  the  land  owned  by  the  plaintiffs  was  some

104 hectares.  Fourteen hectares of that area was situated on higher ground which was flood free (“Stage 1”).  The remainder was a flood plain which had been approved for canal development with extensive open spaces (“Stage 2”).  The whole of the area was called the Riverlink Project (“Riverlink”).

3

[2]     On 3 December 1993, the plaintiffs applied to the Albert Shire Council (which has since merged with the Gold Coast City Council) (“the Council”) to subdivide the land in Stage 1.  In the application for subdivision, one of the matters of concern in the development of the Riverlink Project was the cost of road works and access to the Oxenford - Southport Road which looped back to the north after it left the Pacific Highway and before it travelled east.  The Main Roads Department had plans to bypass that road to create a more direct access to Hope Island.  Two types of road works were proposed with regard to the Stage 1 development.  In the first instance there would be internal road works which would cost $860,776.00.  This would provide a temporary entrance to Stage 1 from the Oxenford - Southport Road.

[3]     In addition, external road works for the land to serve both Stage 1 and Stage 2 by providing a permanent access from the Oxenford – Southport Road would cost

$2,295,653.00.  It was proposed that the cost of the external road works would be covered by a pro rata contribution from the development of the land.  The average cost  per  dwelling  of  the  external  road  works  was  $2,014.00,  discounted  to

$2,000.00, per dwelling for the Stage 1 area with the balance to be paid in Stage 2. A report prepared by the engineers Burchill Bate Parker and Partners Pty Ltd
(“Burchill  Bate  Parker”)  for  the  plaintiffs  on  3  December  1993  which  was submitted with the subdivision application said:

“As there will be no need for actual construction of the upgraded works to Hope Island Road for this first stage subdivision, other than at the intersection of the subdivision road, it is proposed that this amount of $2,000 per dwelling be paid by the builder applicants into a  fund  managed  by  Council,  at  the  time  of  registration  of  the building plans for drawing upon at the stage 2 construction time.”

[4]     On  23  December  1993  in  Minute  No  P93.12B.105,  the  Council  approved  the proposed subdivision with a number of conditions including two conditions relating to road works.  These conditions were the construction of a temporary entry road to stage  1  of  the  development  and  Condition  19,  which  provided  that  future development of these lots would require a contribution towards future upgrading of the Oxenford - Southport Road estimated at approximately $2,000.00 per dwelling.

[5]     A plan submitted to the Council in January 1994 prepared by Burchill Bate Parker proposed the further subdivision of Stage 1 into 7 large lots ranging from 0.71 to

1.99 hectares in area with road works servicing each lot from the temporary access from the Oxenford – Southport Road.  At that stage, the plaintiffs intended to sell each of the 7 lots to builders for further subdivision into smaller allotments after construction of the temporary access road and other services.  A concept plan for the whole development of Riverlink was also presented to Council (the “Riverlink concept plan”).  As a result of the submission of these plans, the Council approval was varied on 18 February 1994 in Minute No P94.02A.056.

[6]     Geoff Burchill, who acted on behalf of the plaintiffs, was hopeful that the proposal to develop a new main road to Hope Island, south of Riverlink, would subsequently come to fruition and the temporary access road could become permanent because it would not be an access onto a major through road, but it was, he said,  “still a nervous situation”.  He was too concerned that Stage 1 be allowed to go ahead to

4

attempt to change the situation with regard to road contribution at that time.  He believed,  however,  that  there  was  a  possibility  that  the  requirement  for  the

$2,000.00  contribution  per  dwelling  would  be  relaxed  in  the  future.    That expectation  was  not  realised  until  1997.    On  19  December  1997,  the  Council approved the relaxation of that condition for reasons that Mr Burchill had expected. However, in early 1994, Mr Burchill’s primary concern was to sell Stage 1.  He was under pressure from his financiers, the Westpac Bank.

[7]     On 23 March 1994, Mr Burchill on behalf of the plaintiffs approached Ron Borland who was the joint Managing Director of the defendant seeking the defendant’s participation in the development of Stage 1 of Riverlink.  He attached the plan of Stage 1 which had been presented to Council.  In this plan lots 1 and 2 were called Stage 1A and lots 3 – 7 were referred to as Stage 1B.  A meeting took place on 24

March  1994  between  Mr  Burchill,  Mr  Borland  and  Timothy  Wright  from Agrifiscal.  What was discussed was set out in a letter dated 25 March 1994 from Mr Wright to Mr Borland.  Mr Wright was given authority by Mr Burchill to conduct negotiations on behalf of the plaintiffs.

[8]     Mr  Burchill  is  an  engineer  with  extensive  experience  in  the  development  and tourism  industries.    For  21  years  until  December  1994,  he  was  Chairman  and Managing Director of Burchill Bate Parker, which offered consultancy services in civil engineering and town planning.  He was also personally involved in land development for the Burchill Project Group, a group of companies owned and controlled  by  Mr  Burchill  personally.    One  of  those  companies  was  the  first plaintiff, Goldtaper Pty Ltd.  Another was Golden 12 Pty Ltd.  The second plaintiff, Haracliff Pty Ltd, was controlled by Patrick Gay.  The third plaintiff, Kembrook Pty Ltd, was owned and controlled by the first and second plaintiffs.  Mr Burchill had authority to act on behalf of all of the plaintiffs in the sale of the Stage 1 land.

[9]     Mr Burchill and Mr Borland met again on 28 March 1994.  At that meeting, Mr Borland told Mr Burchill that the maximum that the defendant was prepared to pay for Group Title lots in Stage 1 was $35,000.00 to $40,000.00 per lot.  That was the maximum price that the defendant was prepared to pay for lots which were fully developed and ready to build on. Mr Borland wanted to subdivide Stage 1 in a manner and style that was suitable to the defendant.  Accordingly, the defendant proposed to prepare a layout plan.  Once that had been completed, Burchill Bate Parker were to prepare costs estimates for the Stage 1 development to quantify the cost of putting the land into the state where the defendant was prepared to pay

$35.000.00 to $40,000.00 per lot for it.  These negotiations between the parties were recorded in a memorandum of understanding prepared by Mr Wright and signed by Mr Burchill on 13 April 1994 and Mr Borland on 14 April 1994.

[10]     On 20 April 1994, after concept plans were developed by the defendant’s architects, Burchill Bate Parker produced detailed cost estimates for Stage 1.  The estimates included all the costs of the road works for Stage 1 which included the cost of the temporary access from the Oxenford – Southport Road.  Attached to the estimates were a number of notes and exclusions.  Note 12 of the cost estimates dated

21 April 1994 provided:

5

“Estimate provides for a contribution of $2,000/lot toward upgrading of the future main intersection.  Subject to Council approval this may be deleted due to the intersection for Stage 1 being permanent.”

The cost estimates showed that the notional cost per lot of developing the land to the level where the defendant was willing to pay $35,000.00 to $40,000.00 per lot was $22,617.75, including the $2,000.00 per lot contribution to the permanent road works.

[11]     Mr Burchill again met with Mr Borland on 22 April 1994 to discuss Stage 1 of Riverlink.  They negotiated a price that the defendant was prepared to pay for Stage 1 based on the layout plans and the estimate of $22,617.75 development costs per lot.  If the defendant paid $14,000.00 per undeveloped lot, the cost of each lot would be $36,617.75, which was within the $35,000.00 to $40,000.00 price range which the defendant was prepared to pay for developed lots.  The parties calculated a price on the basis of 250 lots in Stage 1.  The total price of $3,500,000.00 was arrived at by multiplying $14,000.00 by 250 lots.  On 23 April 1994, Mr Burchill faxed to Mr Wright a handwritten copy of the key points that he and Mr Borland had agreed.  He noted that the price had been agreed at $3,500,000.00.  He also referred to a number of other agreed terms.  One of those terms was:

“In the event that it is possible to obtain approval of Albert Shire for deletion  of  the  requirement  for  2000  per  dwelling  for  external roadworks contribution then the cost saving benefit of the whole of this will go the Vendor.”

Mr Burchill said that this subject was specifically discussed and that it was left entirely at the plaintiffs’ risk.  Mr Borland agreed that if the money was able to be saved, it should go to the plaintiffs.  At that time it was agreed that the price which was  negotiated  reflected  the  fact  that  the  defendant  would  be  liable  to  pay

$2,000.00 per lot either to the Council, or if the condition was relaxed, to the plaintiffs.  Mr Burchill’s note reflected this agreement.

[12]     Mr Wright then drafted terms of agreement which were signed by Mr Borland on behalf of the defendant on 27 April 1994 and by Mr Burchill on behalf of the plaintiffs’ interests on 30 April 1994.  It gives the details referred to earlier of how the price for the land was calculated.  Recital “O” provides:

“An external roadworks contribution to the Albert Shire Council is included in. . . this agreement however such contribution may not be necessary.  This roadwork contribution has no effect on the Stage 1 development however was a contingent item required by council to allow Stage 1 to proceed.”

[13]     Clause  2  of  the  agreement  was  that  the  purchase  price  of  the  land  would  be

$3,500,000.00 (equivalent to $14,000.00 per lot for 250 lots).  Terms of settlement for progressive payment of the purchase price were set out in clause 3 of the terms of agreement.  It was also provided, in clause 6 of the terms of agreement, that any savings in the cost of development would be shared equally between the parties. An exception was that, in the event that it was possible for the plaintiffs to obtain approval from the Council for deletion of the requirement for the $2,000.00 per

6

dwelling for external road works contribution, the cost savings of the whole of this would be passed back to Mr Burchill’s company.

[14]     On 27 April 1994, Mr Burchill on behalf of the plaintiffs wrote to the QIDC forwarding the terms of agreement.  A copy of this letter was sent to the plaintiffs’ solicitors.  It shows the significance of the cost saving benefit of a relaxation to the parties to the contract, particularly to the plaintiffs as vendor.  Mr Burchill said with regard to the purchase price:

“In addition to the sale price of $3.5million, we point out that there is potential under Clause O, Page 2, for the Vendor to obtain further benefit out of the sale to the extent of $500,000.  This will require obtaining  approval  of  Albert  Shire  Council  to  the  deletion  of  a subdivision   approval   clause   pertaining   to   a   contribution   of

$2,000/dwelling towards External Road Constructions.

The  origin  of  this  condition  lies  in  the  former  proposal  for  a temporary access intersection only to Stage 1, with ultimate access being by the principal entry point further along Hope Island Road to the east.  As this stage access is permanent, there is no justification for Stage 1 to become involved in approved requirements for the balance of the project.”

On 28 April 1994, Mr Burchill instructed solicitors to draw up contracts for the sale of the Stage 1 land.

[15]     On 4 May 1994, Mr Rapp of Bell, Rapp & Partners, solicitors for the vendors, sent draft  contracts  to  Mr  Burchill  and  to  Perrin  Pointon,  solicitors  acting  for  the defendant  in  the  purchase  of  the  land.    The  contracts  acknowledged  that  the developer  would  use  Burchill  Bate  Parker  as  consulting  engineers,  Bennett  & Bennett  as  consulting  surveyors  and  Neumann  Contractors  Pty  Ltd  as  general contractor in the development (the “Team”).  The plaintiffs, as Vendors, warranted the  cost  of  development.    Clause  2.13  of  the  Special  Conditions  of  contract provided.

“2.13      The  Purchaser  agrees  to  use  all  endeavours  reasonably available to it, with the assistance of the Team (to such extent as the Purchaser shall reasonably require), to obtain agreement  from  the  Council  to  its  abandonment  of  its proposed requirement as a condition of its approval of the Development, for contribution for external road works at the rate of TWO THOUSAND DOLLARS ($2,000.00) per dwelling.  In the event that the Purchaser is successful in having the Council agree to abandon this requirement, or, to  reduce  the  amount  payable  per  dwelling,  then  the amount of such saving compared with the requirement of a contribution at the rate of TWO THOUSAND DOLLARS

($2,000.00)    per    dwelling,    for    the    whole    of    the Development, shall be an amount claimable by the Vendor from the Purchaser as a liquidated debt.

7

2.13.01If  such  saving  is  established  prior  to  the Date   for   Completion   hereof   then   the resultant  amount  of  such  saving  shall  be paid  by  the  Purchaser  to  the  Vendor  at completion     hereof     with     the     monies otherwise payable at completion hereof.

2.13.01 [sic]If such saving is not established in time for completion  hereof  but  is  established  later then  forthwith  upon  the  amount  of  such saving being established, the Purchaser shall pay the resultant amount to the Vendor.”

The   contracts   were   dependent   upon   the   plaintiffs’  obtaining   approval   for subdivision.

[16]     Negotiations between the parties as to the terms of the contract continued.  On

3 May 1994, Bennett & Bennett wrote a report on a proposed amendment to the subdivision approval (the “Bennett & Bennett report”).  This report was attached to the final contract signed between the parties.  It proposed submitting to Council that the approval be varied to “a subdivision yielding two management lots, one balance area and an area of new road to the requirements of the Department of Transport ie road widening as previously advised and allowed for in the project planning”. Stage 1 was to be divided into Lots 1 and 2.  By this means, the applicant hoped to have a number of conditions of the existing approval deleted, being conditions 5, 6,

7, 8, 10 and 18.  These conditions did not include condition 19 which, as previously set out,1 provided that future development of these lots would require a contribution towards   a   future   upgrading   of   the   Oxenford-Southport   Road   estimated   at approximately $2,000.00 per dwelling.  There was, it seems, no proposal to seek relaxation of this condition at that time.  Bennett & Bennett commented in their report that:

“The Albert Shire Council, following its normal procedures would accept, consider and could conditionally approve an application by Berela Limited for the detail Group Title Subdivision of proposed Lots 1 & 2 in parallel with its consideration of the above proposed application.

Submission of such an application by Berela Limited, at the same time  as  the  application  for  amendment  to  the  existing  approval, could weigh favourably with Council, but the absence of such an application is not considered to be a probable adverse influence on Council’s decision.”

On 5 May 1994, the revised subdivision plan was submitted to Council by Burchill

Bate Parker (the “May 1994 subdivision plan”).

  1. See paragraph [4]

8

[17]     On 6 May 1994, Mr Burchill wrote to his solicitors saying, with regard to clause

2.13 of the draft contract:

“If I can get Council to waive condition of $2,000 per dwelling, when can I claim the amount?  Berela will have to provide for this, perhaps at the same timing as would have applied to its payment to Council, ie just prior to sealing of Group Title subdivision plans.”

Mr Rapp did not get any immediate response from the defendant’s solicitors on the issues raised by Mr Burchill.  Accordingly Mr Burchill wrote to Horace Thorpe, another director of the defendant on 11 May 1994.  Mr Burchill told Mr Thorpe that the defendant had lodged a subdivision application without details of the Group Title subdivision that the defendant wanted.  He continued:

“It will be necessary when you are in a position to do so, to lodge the group title subdivision application and at that time we request you give us the opportunity to put a case to Council in regard to the

$2,000 / lot contribution for external roadworks to be deleted.”

Mr Burchill wrote this because he was concerned that the defendant may not be “as energetic about seeking to follow up this matter as it should be”.  This concern was confirmed, when at a meeting with Mr Wright and Mr Rapp, Mr Thorpe’s attitude was  that  the  defendant  would  not  be  making  any  effort  to  seek  a  relaxation. Mr Burchill gave instructions to his solicitor with regard to the mechanism for making submissions to Council.

[18]     Negotiations culminated in many terms of the contract being redrawn.  The price was reduced to $3,250,000.00.  In return the total payment was made at an earlier settlement date.  A number of other changes were made.  The plaintiffs no longer guaranteed development costs.  Instead of the contract being dependent on the plaintiffs’gaining sub-divisional approval, it was subject to the defendant’s gaining such approval on satisfactory terms to a group title development called Riverlink Grove  (Lot  1)  and  a  residential  subdivision  subsequently  known  as  Riverlink Gardens (Lot 2).

[19]     No change was made to the question of who would have the benefit of a relaxation of the $2,000.00 per lot contribution to road works which would become payable on the  sale  of  each  lot.    However  a  change  was  made  to  the  way  in  which  the application was to be made so that it was the plaintiffs, as vendor, who would be given the right to negotiate with Council about the relaxation and not the defendant as purchaser.  Mr Borland said this was at the request of the vendors or their solicitors, he was not sure which, and, as it did not affect the defendant financially, they did not have a problem with it and agreed to it.  Mr Borland also said he thought  that  the  plaintiffs  would  make  the  application  for  relaxation  before settlement and had not given any thought to what would happen if they made the application after that date.  However, I do not accept that evidence.  He was unconvincing in his manner of giving evidence on this point and it is much more likely that the defendant knew that the plaintiffs were entitled to the benefit of any relaxation they successfully applied for, whenever it was that they applied for it.  As Mr Borland later said in cross-examination, of the negotiations leading up to the

9

signing of the contract, “At that stage we were going to pay it, whichever way it went.”  The contract was signed on that basis.

[20]     Mr Thorpe said to Mr Wright that the defendant was not interested in being directly involved in obtaining the relaxation.  It was to be Mr Burchill’s responsibility. Mr Thorpe said that they were not interested in the matter because there was to be no financial benefit for them.  The defendant did not think that any relaxation would be given by the Council.  Mr Thorpe said he thought the prospects of getting a relaxation were  “minimal”.  Mr Borland, in his evidence, said he thought there was only a little chance that the plaintiffs would achieve relaxation of the condition.

[21]     On 27 May 1994, the plaintiffs’ solicitors  sent  a  revised  draft  contract  to  the defendant’s solicitors.  This followed discussions with Mr Wright.  Mr Rapp said his interpretation of those discussions was that he  “was  still  to  include  in  the contract reference to the possibility of relaxation of this requirement of $2,000.00 dollars per lot on the basis that we the vendor would still have to do the work to get the relaxation, but it was still to be included in the contract on that basis.”  There were never any instructions to the effect that the defendant would get the benefit of any relaxation.  Amendments to the revised draft contract were suggested by the defendant’s solicitors and accepted by the plaintiffs.

[22]     The final contract dated 6 June 1994 (the “contract”) was signed by the defendant on 31 May 1994 and by the plaintiffs on 4 June 1994.  In that contract, Stage 1 and Stage 2, referred to in clause 4.08, both referred to parts of the land being purchased by the defendant which had previously been referred to by the parties as Stage 1. The contract was subject, inter alia, to the defendant’s gaining satisfactory sub- divisional approval.  Appended to the contract were the Riverlink concept plan, the Bennett & Bennett report and the May 1994 subdivision plan.

[23]     Clause 4 of the contract dealt with the contribution to external roadworks.  It provided:

“4           ADJUSTMENT IN RESPECT OF CONTRIBUTION TO EXTERNAL ROAD WORKS

4.01The Purchaser acknowledges that the Purchaser is aware that the Council may, as part of the Approval Conditions,

(for the Purchaser’s subdivision as referred to in special condition  2)  impose  a  requirement  of  a  contribution  to external road works on a per lot basis, hereinafter called

“Road Contribution”.

4.02Notwithstanding  the  provisions  of  special  condition  2 hereof, the Purchaser agrees that the Purchaser will take no objection to such a requirement.

4.03It is further agreed that should such requirement on the part of  the  Council  exceed  the  sum  of  $2,000.00  per  lot

(relating to the number of lots in the Purchaser’s form of proposed Development) then the amount of such excess over Two Thousand Dollars ($2,000.00) per lot shall at

10

completion   be   deducted   from   the   monies   otherwise payable by the Purchaser at completion.

4.04The   Purchaser   agrees   that   notwithstanding   that   the application  made  to  the  Council  pursuant  to  special condition 2 hereof shall be the Purchaser’s application, the Vendor may and shall be afforded by the Purchaser the opportunity to make submissions to the Council supporting the relaxation in whole or in part of the Road Contribution. If  required  the  Purchaser  shall  provide  to  the  Council written consent and authorisation for such submission or submissions   by   the   Vendor   relating   to   the   Road Contribution.

4.05In the event that the Vendor is successful in negotiating with  the  Council  concerning  a  relaxation  of  the  Road Contribution as evidenced by the terms and conditions of the Council’s subdivisional approval for the Land, either in whole or in part, then the amount of the aggregate value of such relaxation shall be a sum payable by the Purchaser to the Vendor.  Such amount payable by the Purchaser to the Vendor    shall    not    exceed    Two    Thousand    Dollars

($2,000.00)  per  lot  and  where  such  relaxation  is  only partial shall be on a per lot basis, the sum obtained by subtracting  from  the  sum  of  Two  Thousand  Dollars

($2,000.00), the amount of contribution required to be paid per lot.

4.06The total sum to be paid by the Purchaser to the Vendor as a consequence of such relaxation (if applicable) shall be the amount of saving per lot multiplied by the number of lots in the Purchaser’s proposed Development.

4.07In the event and whilst the Purchaser shall retain the Land and proceed with the Development, the said sum payable pursuant to this special condition by the Purchaser to the Vendor,  shall  be  paid  progressively  and  the  amount  of saving on a per lot basis shall be paid at the time of the completion by the Purchaser of any sale of any lot in the Development, whether as vacant land or as a house and land package.  In the event that at any time the Purchaser shall sell all or part of the Development not as retailer of lots or all of the lots, as the case may be, then the sum payable to the Vendor pursuant to this special condition shall be paid at the time of completion of such sale and the amount  payable  shall  be  the  saving  on  a  per  lot  basis multiplied by the number of lots sold at the time.

11

4.08The Vendor and the Purchaser acknowledge, as is set out in special condition 2 hereof, that subdivisional approval for the Development will be applied for in two (2) stages, namely Stage 1 and Stage 2.  It is acknowledged that it is anticipated that the issue of Road Contribution shall be dealt  with  the  Approval  Conditions  for  Stage  1.    It  is agreed  however  that  for  the  purposes  of  this  special condition 4 the Approval Conditions for Stages 1 and 2 shall be read together and any conditions relating to the issue  of  Road  Contribution  shall  be  aggregated  for  the purposes of giving effect to the earlier sub-condition of this special condition 4.”

[24]     The only significant amendment that had been made to this clause of the contract drafted by Mr Rapp on 27 May 1994 was to clause 4.05 which had provided:

“4.05      In  the  event  that  the  vendor  is  successful  and  such anticipated requirement is relaxed, either in whole or in part,  then  the  amount  of  the  aggregate  value  of  such relaxation shall be a sum payable by the Purchaser to the Vendor.  Such amount payable by the Purchaser to the Vendor    shall    not    exceed    Two    Thousand    Dollars

($2,000.00)  per  lot  and  where  such  relaxation  is  only partial shall be on a per lot basis, the sum obtained by subtracting  from  the  sum  of  Two  Thousand  Dollars

($2,000.00), the amount of contribution required to be paid per lot.”

[25]     The purchaser’s solicitors, Perrin Pointon, had written to the plaintiffs’ solicitors in accordance with the defendant’s instructions on 31 May 1994 suggesting, inter alia, that  clause  4.05  be  amended  so  that  the   “words   ‘an  [sic]  such  anticipated requirement is relaxed’should be deleted and the words ‘in negotiating with Council concerning a relaxation of the road contribution as evidenced by the terms and conditions of the Council’s subdivisional approval for the land being acquired by the Purchaser’  inserted  in  their  place”.    The  words  were  changed  accordingly. Mr Burchill said of this clause in cross-examination that he did not think it contained a mistake.  He said, “I would have assumed that as stated in the contract we were to take that initiative and the money was to come to us.”  He believed there was no limit on when they might make submissions and that it “was just there for us to have if we were prepared to take the trouble.”  His evidence continued, “As far as I was concerned it was a very straightforward issue, that if $2,000 a lot was to be saved, that we were entitled to it.  If we failed to make an application to Council, . . . we got it eventually by it coming into the construction.”  Mr Borland had the same view of the agreement.

[26]     On 27 June 1994, Mr Burchill prepared a letter to Council for signing by Mr Parker, the  town  planning  partner  of  Burchill  Bate  Parker,  seeking  relaxation  of  the

$2,000.00 contribution per dwelling to the external road works.  The basis for the relaxation sought was that Council and Department of Transport had agreed that the intersection constructed for access to Stage 1 could be a permanent rather than a temporary access.  The draft letter was not sent on the advice of Mr Parker, who

12

took the view that the matter was too complicated for the Council, given the other matters then under consideration by Council with respect to Riverlink, such as rezoning and the establishment of a deed of agreement.  Mr Burchill’s intention was to make the submissions once those matters were resolved.  It is understandable that he would not want to take any steps which might jeopardise subdivisional approval and so threaten settlement of the contract.

[27]     On 7 October 1994, the Council approved the proposed subdivision of the group title area of Riverlink Stage 1 by Minute Number P94.10A.070.  Included in the conditions was a requirement to make a number of payments to Council at the date of  building  approval  less  any  previously  paid  contributions.    One  of  the contributions required to be paid was:

“An amount towards external road works (currently $2,000 per lot).”

On 27 October 1994, the Council gave approval in similar terms to the residential area of Riverlink Stage 1 in Minute Number P94.10B.106.  These conditions were evidence of the Road Contribution required.

[28]     Mr Burchill did not do anything about obtaining the relaxation during 1995 as, contrary  to  Mr  Burchill’s  expectations,  the  defendant  did  nothing  to  develop Stage 1.  Mr Burchill did not feel obliged to hurry as the money was not yet payable pursuant  to  clause  4.07  of  the  contract  and  in  any  event  the  benefit  would eventually go to the plaintiffs whether the condition was relaxed or the money was held for future road works.

[29]     In  1996,  Mr  Burchill  became  aware  that  the  Department  of  Main  Roads  was imposing a requirement in exactly the same terms as that imposed by Council.  On

15 July 1996, the Department of Main Roads wrote to Burchill Bate Parker setting out its requirements for Stage 1A of Riverlink (Lot 1 on RP 880395).  They included, in addition to road construction:

“(a)     Payment of a monetary contribution calculated by individual assessment based on a transport impact analysis or on a per lot basis.

(b)The contribution on a per lot basis is $184,000 for 92 lots, assessed on the amount of $2,000 per lot as stated in the Council’s conditions of approval.”

[30]     The first payment of the $2,000.00 contribution was made on 24 July 1996 when a

$24,000.00 payment was made by the defendant to the Council.  A letter was immediately sent by the solicitors for the defendant to the Main Roads Department on 25 July 1996 seeking relaxation of the $2,000.00 contribution.  No notice was given to the plaintiffs by the defendant that they were intending to make or had made such an application.  On 27 August 1996, the Department of Main Roads wrote  to  Burchill  Partners  Pty  Ltd  (as  Burchill  Bate  Parker  became  after  Mr Burchill’s interest in it ceased) with regard to part of Lot 2 on RP 880395 in the following terms:

13

“Queensland  Department  of  Main  Roads  acknowledges  that  an unconditional Bank Guarantee for $79,422 has been issued to the Gold   Coast   City   Council,   on   behalf   of   the   Department   for completion of external access roadworks by the Developer before final sealing of all subdivisional plans of the Riverlink Estate.

In addition to the unconditional Bank Guarantee of $79,422, the Department   understands   that   Council   has   received   Transport Infrastructure Contributions of $24,000 to seal subdivision plans for

12 lots only for Stage 1 of the Riverlink Estate.

Queensland Department of Main Roads agrees to the sealing of the subdivision plans for 12 lots only – Stage 1 of the Riverlink Estate, subject   to   Council   transferring   the   Transport   Infrastructure Contributions of $24,000 to Queensland Department of Main Roads

– South Coast Hinterland District.

For future sealing of the subdivision plans on the Riverlink Estate, the  applicant  is  to  make  payment  of  the  required  Transport Infrastructure Contributions on a per lot basis to the Department of Main Roads.

Submission of the survey plan indicating the area of land dedicated to road reserve for the access requirements will be required prior to final sealing of all subdivisional plans of the Riverlink Estate.”

[31]     On 26 August 1996, Council granted approval of a 92 lot Special Residential subdivision of Lot 1 on RP 880395, under Delegated Authority Number 352 on

26 August 1996 subject to conditions of subdivision dated 7 October 1997 (Minute

Number C96.0903.005).  The defendant also gained subdivisional approval for 46

Special Residential lots on Lot 2 on RP 880395 subject to Council’s subdivision conditions on 28 June 1996 (Minute Number N96.0618.021), and approval for two Group Title Lots on 17 April 1997 under Delegated Authority Number 351.  The road works contribution requirement remained in place.

[32]     Towards  the  end  of  1996,  Mr  Burchill  took  the  view  that  “the  Main  Road Department  levy  was  illegal.”    Apparently  this  was  the  view  taken  by  the development industry as a result of two decisions in the Planning and Environment Court, Pacific Exchange Corporation Pty Ltd and Treasure & Associates Pty Ltd v Gold Coast City Council and the State of Queensland2 decided on 29 October 1996 and  Arlenby Marketing Pty Ltd v Chief Executive of the Queensland Department Transport3   delivered on 4 November 1996.  It matters not for present purposes whether or not the view taken of those cases was correct.  What is significant is that the Court ruled against the imposition of a per lot contribution to road works by the Council imposed at the behest of the Department of Transport as a condition of subdivision in these instances and the development industry, of whom Mr Burchill

  1. P & E Appeal No 32 of 1996, Skoien SJDC, 29 October 1996

  1. P & E Appeal No 39 of 1996, Skoien SJDC, 4 November 1996

14

was part, took the view from newspaper reports of the decisions that imposing such a levy was generally illegal.

[33]     On 19 November 1996, Bennett & Bennett, consulting surveyors for the defendant in the Riverlink Project, wrote to the Department of Main Roads with regard to the

“apparent overlap with both Council and Department of Main Roads requesting a contribution of $2,000 per lot for external road works.”  A further $86,000.00 was paid for the contribution to road works on that date.

[34]     On 8 July 1997, an internal Council memorandum from the Subdivision Engineer

(North) to the Special Administration Supervisor provided:

“I  refer  to  a  $2,000  per  lot/unit  contribution  required  from  the Riverlink   development   which   we   discussed   recently.      This contribution was required for civil works along the frontage and within the estate and included:

1.Major intersection works on Oxenford – Southport Road for the major entry into the eastern part of the development

(not the currently constructed Anaheim Drive).

2.Roadworks     along     the     remaining     frontage     along Oxenford – Southport Road to the east and along the future oval area.

3.Cross-road   drainage   associated   with   both   the   above roadworks.

4.Construction of the  main entry road mentioned in point 1. above and an internal roundabout.

5.            Construction of internal pedestrian footpaths.

The  contribution  was  never  questioned  at  the  time  as  it  was  an agreed sum to act as security for works being actually constructed and also to ‘spread out the load’of such contributions over the entire development rather than one particular pocket of the development. In hindsight, the actual contribution should have been scrutinised in more detail, however the developers accepted the contribution as part of subdivision and rezoning conditions.

The breakup between future works required by the Department of Main   Roads   and   those   required   by   Council   (internal   road, roundabout and footpaths) is 90% and 10% respectively ie. $1,800 per unit for DMR related work and $200 per unit for Council related works.

Please note that this contribution is not a contribution required under the Transport Infrastructure Act by the Department of Main Roads and should not be paid into their account. (DMR however should be notified that such a contribution is currently being obtained for the

15

purposes mentioned.)  It could be the case in the future that the contribution is paid directly to those who actually do the works as specified.  Thus Council should continue requesting the contribution as originally requested and retain all monies until works are about to commence or have been completed, depending on what is agreed to at that time.”

[35]     On 25 July 1997, the Department of Main Roads replied to the letter of 25 July

1996 from the defendant’s solicitors saying:

“It is advised that the condition of approval requiring the subject contribution  payment  was  a  Council  condition.    Main  Roads Department has not been involved with this condition.  As such, the monies have been collected by, and remain with, Gold Coast City Council.  An application for review of a decision to collect such monies cannot be processed by this Department with respect to the payment of monies by your client in this instance.”

[36]     On 14 October 1997, the defendant’s solicitors wrote to the Council asking for a review of the Council’s approval conditions seeking removal of  “the requirement for the payment of any further payments or contributions whatsoever for external road works.”  They also requested a refund of the $164,000.00 which had already been paid for this contribution.  This was done without any notice to the plaintiffs on their representatives.  The Council then wrote to the Department of Transport on

27 October 1997 seeking confirmation that the Department did not require the imposition of $2,000.00 per lot.  That was confirmed in writing by the Department of Main Roads on 1 December 1997.

[37]     The   defendant’s   solicitors   repeated   its   written   request   to   the   Council   on

4 November 1997 and threatened to commence proceedings if its demands were not met.  It appears that the Council sought the advice of Burchill Partners Pty Ltd. Upon receipt of a letter from Burchill Partners Pty Ltd on 13 November 1997 and another request from the defendant’s solicitors on 28 November 1997 for a refund of $1,800.00 per lot and a future liability of $200.00 per lot, and the confirmation from Main Roads on 1 December 1997, the Council acceded to the defendant’s request.

[38]     Before a submission was made to Council for relaxation of the external road works contribution by Mr Burchill, he discovered that relaxation had been obtained on

19  December  1997  as  a  result  of  submissions  by  the  defendant  and  that  the defendant intended to keep the benefit, which was $1,800.00 per dwelling.  Before then, $164,000.00 had been paid and retained by the Council in trust.  The Council paid $147,600.00 to the defendant as a result of its decision on 19 December 1997. The decision of the Council was in the following terms:

“That the subdivision conditions that refer to the contribution of

$2,000.00 per lot for external roadworks previously imposed upon the  Riverlink  Gardens  and  Riverlink  Grove  Estates  (Minute  Nos C96.0903.005,   N96.0618.021   &   N97.0902.011   &   Delegated Authority No. 352, 26 August 1996 and No. 351, 17 April 1997) be deleted  and  a  new  condition  be  added  to  each  of  the  above mentioned subdivision approvals to read:

16

AThe payment to Council of $200.00 per lot for roadworks to oval frontage prior to the sealing of survey plans.

B            The applicant is to receive a reimbursement of $1,800.00

per lot for any contributions paid to date in relation to the

$2,000.00 per lot for external works contribution, and no credits  shall  be  given  to  this  estate  as  a  result  of  this amendment.”

[39]     The Council noted in its reasoning that the defendant had constructed its own road works at a cost of $386,000.00 and that the defendant’s land would not have access to the main intersection which had not yet been built.  However, as previously set out in these reasons, the cost estimates had always included the cost of these road works in addition to the $2,000.00 contribution for the future main intersection. Mr Burchill had always been of the view that one of the reasons that this condition might be relaxed was because the defendant did not gain any benefit.  Mr Burchill’s view that he would have been successful in obtaining a relaxation had he applied was not challenged and is a view that I accept.  His expertise in town planning matters, also unchallenged, supports his view.  The Council was unaware of the terms of the contract between the plaintiffs and the defendant.

[40]     Since that time further dwellings have been constructed.  The parties are agreed that the value of the relaxation has been $340,200.00.  In addition, the parties have agreed that the amount of interest claimable4 is $98,716.12 to 14 March 2001 with

$104.85 per day (calculated at 11.25%5 on $340,200.00) thereafter.

[41]     The plaintiffs’ claim is put in three alternative ways:  firstly, the plaintiffs contend that on a proper construction of the contract for sale of land, the money is due in the events that have happened since the signing of the contract;  secondly, the plaintiff seek rectification of clause 4.05 of the contract and payment in accordance with the rectified contract; and thirdly, the plaintiffs claim damages for breach of contract.

Money Claim

[42]     The plaintiffs have properly conceded that on a proper construction of clause 4.05 of the contract, the circumstances entitling them to payment under the contract have not arisen.  Clause 4.05 provided for payment from the defendant to the purchasers,

“[i]n  the  event  that  the  Vendor  is  successful  in  negotiating  with  the  Council concerning  a  relaxation  of  the  Road  Contribution  …         then  the  amount  of  the aggregate value of such relaxation shall be a sum payable by the purchasers to the Vendor.”

  1. Interest has been calculated from the date of the Council refund on 19 December 1997 or the date of settlement of the lots which ever is the later in each case.

  1. Pursuant to Item O of the contract referred to in paragraph 9 of the Further Amended Statement of

    Claim.

17

[43]     However,  as  the  relaxation  by  the  Council  was  not  made  upon  the  plaintiffs’ application,  the  vendor  was  not  successful  in  negotiating  with  the  Council concerning  such  relaxation.    The  occasion  does  not  arise  therefore  under  the contract  for  the  payment  of  the  aggregate  value  of  the  relaxation  by  the defendant/purchaser to the plaintiffs as vendor.

Rectification

[44]     The plaintiffs also claimed rectification of clause 4.05 of the contract so that it would read as follows:

“In the event that  the Council, in its initial approval or by way of

amendment thereof, imposes no requirement for contribution to road

works, or a contribution less than $2000, or otherwise in the event

that the vendor is successful in negotiating with Council concerning

a relaxation of the road contribution as evidenced by the terms and conditions  of  the  Council’s  subdivisional  approval  for  the  land, either in whole or in part, then the amount of the aggregate value of such  relaxation  shall  be  a  sum  payable  by  the  purchaser  to  the vendor…  ”

The underlined words would be added if the plaintiffs were successful in their rectification case.

[45]     At  one  time,  the  parties  had  to  show  that  there  was  an  antecedent  concluded contract before rectification would be ordered.  That is no longer necessary.6  Now the plaintiff must show that the parties made a mistake in the expression of their common intention at the time of entering into the contract so that the contract does not embody that intention.  As Brennan J held in Pukallus v Cameron:7

“…    it is necessary to show a concurrent intention of the parties, existing at the time when the written contract is executed, as to a term which would have been embodied in the contract if the parties had not made a mistake in expressing their intention.”

Proof of such an intention is necessary to  “displace the hypothesis arising from execution of the written instrument, namely, that it is the true agreement of the parties.”8  The plaintiff is required to show  “exactly and precisely”9 the terms in which the contract ought to be to give effect to the expressed common intention of the parties.

  1. Slee v Warke (1949) 86 CLR 271 at 280; Maralinga Pty Ltd v Major Enterprises Pty Ltd (1973) 128

    CLR 336

  1. (1982) 180 CLR 447 at 456

  1. Maralinga Pty Ltd v Major Enterprises Pty Ltd (supra) at 351

  1. Fowler v Fowler (1859) 4 De G & J 250 at 265 [45 ER 97 at 103]; Australian Gypsum Ltd and Australian Plaster Co Ltd v Hume Steel Ltd (1930) 45 CLR 54 at 64; Maralinga (supra) at 349; Pukallus v Cameron (supra) at 452, 457

18

[46]     In this case, as the plaintiffs submitted, by the time the contract was signed, the parties made a distinction between who would get the benefit of the relaxation and how the relaxation would be achieved.  On neither matter, however, was there a mistake in the contract.  The parties both agreed that the plaintiffs would get the benefit  of  any  relaxation  whenever  that  was  achieved  and  secondly,  that  the plaintiffs as vendors would make the application for relaxation.  The precise terms of words used had been suggested by the defendant’s solicitor and the words did, in fact, as I have found, represent the parties’ intention at the time of signing the contract.  As Mr Burchill said in evidence, “…   as stated in the contract we were to take that initiative and the money was to come to us.”  The linkage between the two was not unintended.  There is therefore no ground on which rectification of the contract could be ordered.

Damages

[47]     The third basis of the plaintiffs’ claim is damages for breach of contract.  In this they should be successful.  The intention of the parties at the time of making the contract,  as  expressed  in  the  contract,  was  that  the  plaintiffs  would  have  the opportunity to apply for the relaxation and that they would have the benefit of the relaxation made on their application whenever it occurred.  Clauses 4.04 and 4.05 provide that it was the plaintiffs as vendor who would make the application for relaxation and there was no express time limit on when they might make that application.  This is not surprising in view of the fact that the moneys for Road Contribution would not become payable until the sale of each lot pursuant to clause

4.07 of the contract.

[48]     The Road Contribution was to be  “evidenced by the terms and conditions of the Council’s subdivisional approval for the land” as provided by clause 4.05 of the contract.  It can be seen by clause 4.01 that it was not yet certain whether the Council  would  impose  a  condition  in  the  Approval  Conditions  requiring  a contribution to external road works on a per lot basis.  If such a condition were made in the Approval Conditions it would be called the “Road Contribution”.  The Approval Conditions would provide evidence of the “Road Contribution”.

[49]     The defendant submitted that there was a limit on the time when such a submission could be made.  The submission had to be made and relaxation achieved by the time the approval conditions were given.  The contract was conditional on the defendants gaining sub-divisional approval from the Council on terms that were satisfactory to it.  However, the defendant expressly agreed, in clause 4.02, that it would take no objection to any requirement in the Approval Conditions for a Road Contribution. Clause 4.03 provided that if the Road Contribution required payment of more than

$2,000.00 per lot then the excess would be deducted from the monies otherwise payable by the purchaser at completion.

[50]     In clauses 4.05 and 4.06, the defendant agreed to pay to the plaintiffs the aggregate value per lot of any relaxation multiplied by the number of lots in the defendant’s proposed development.  Clause 4.07 set out that the payment would be made progressively whether at the completion of the sale of the individual lots or of the lots as a group.  It is significant that payment was to be made progressively because it suggests that the Road Contribution which would be evidenced by the Approval Conditions might be relaxed at any time before completion of sale of all of the lots

19

by  the  defendant.    It  differed  from  the  time  when  any  excess  in  the  road contribution over $2,000.00 might be paid.

[51]     The defendant submitted that in clause 4.05, the phrase “as evidenced by the terms and conditions of the Council’s subdivisional approval for the Land” qualifies the word “relaxation”, rather than the words “Road Contribution” which immediately precede it.  The phrase is, however, a participial phrase used adjectively10 to qualify the  noun  “Contribution”  which  it  immediately  follows  rather  than  the  word

“relaxation”.  On a plain reading of the clause, it is the Road Contribution which is to be evidenced in the terms and conditions of the sub-divisional approval.  This meaning is semantically as well as grammatically correct.  The Road Contribution would be evidenced by those terms and conditions because it would be a term or condition whereas a relaxation would not, ex hypothesi, be a term or condition.

[52]     If, contrary to this view, the clause of the contract is ambiguous, then the rest of the contract supports this interpretation, as do the extrinsic facts in the sense used by Mason J in Codelfa Construction Pty Ltd v State Rail Authority,11 ie “the objective framework of facts within which the contract came into existence, and . . . the parties’presumed intention in this setting.”  This evidence shows that the plaintiffs, as vendor, would get the benefit of the relaxation whenever it occurred and that the payment  of  that  benefit  would  be  made  progressively  after  settlement  of  the contract between the plaintiffs and the defendant.  There is no extrinsic evidence which suggests that the objective intention of the parties was that the plaintiffs were restricted  to  making  application  for  relaxation  before  settlement  and  that  the

“relaxation” must be evidenced in the approval conditions given prior to settlement. There was no express or implied agreement that the plaintiffs would be restricted to seeking and obtaining relaxation of the Road Contribution requirement prior to the Approval Conditions being imposed.

[53]     In clause 4.04, the defendant expressly agreed that the plaintiffs might, and should be afforded by the defendant, the opportunity to make submissions to the Council supporting the relaxation, in whole or in part, of the Road Contribution.  The express promise made in the contract, as Dixon J held in  Shepherd v Felt and Textiles of Australia Ltd,12 “necessarily includes an obligation not to hinder or prevent the fulfilment of its purpose.”  This is an implied term which is a legal incident of this type of contractual arrangement.13  The plaintiffs would not be able to have the benefit of this term of the contract if the defendant made application for relaxation and so obtained the financial benefit of relaxation which the parties clearly intended by clause 4.05 should go to the plaintiffs.

10        See New South Wales v The Commonwealth (1990) 169 CLR 482 at 498

11 (1982) 149 CLR 337 at 352

12 (1931) 45 CLR 359 at 378

13        Liverpool City Council v Irwin [1977] AC 239; Codelfa Construction Pty Ltd v State Rail Authority of NSW (supra) at 345.

20

[54]     In these circumstances, there was an implied term that the defendant would do all things necessary to enable the plaintiffs to have the benefit of the contract.  As Griffith CJ held in Butt v McDonald:14

“It is a general rule applicable to every contract that each party agrees, by implication, to do all such things as are necessary on his

[or her] part to enable the other party to have the benefit of the contract.”

Implication  of  this  term  necessarily  implies  that  the  defendant  would  not  do anything that would impede the plaintiffs’ obtaining the benefit of the contract.15

As Griffith CJ explained in Marshall v The Colonial Bank of Australia:16

“Now, all contractual relations impose upon the parties a mutual obligation  that  neither  shall  do  anything  which  is  calculated  to hamper the other in the performance of the contract on his [or her] part.  This rule was recently expressed by Vaughan – Williams, LJ, as follows:-

‘In this contract, as in every other, there is an implied contract by each party that he will not do anything to prevent the other party from performing the contract. . .   I agree that generally such a term is by law imported into every contract’[17].”

[55]     It  was  not  a  matter  of  concern  to  the  defendant  when  the  plaintiffs  made  an application because under the contract the road contribution of $2,000.00 per lot would have to be paid by the defendant either to the Council, or, if it was relaxed in whole or in part, to the plaintiffs.  It was not a payment which it had to make at the time of settlement of its contract with the plaintiffs.  The timing of its relaxation was of no moment to the defendant and so it is unsuprising that no time limit is made  in  the  contract  for  the  plaintiffs  to  apply  for  relaxation  of  the  Road Contribution  condition.    Even  the  plaintiffs  would  not  have  the  benefit  of  a relaxation of road contribution condition until the settlement of lots sold by the defendant.  A relaxation of the condition would not affect the purchase price at settlement,  but  rather  the  identity  of  who  would  receive  the  $2,000.00  road contribution once it became payable.  The only term which might be implied is that the plaintiffs make their application within a reasonable time.  Yet the application for relaxation was made by the defendant at a time when it was still reasonable to expect that the plaintiffs would make an application for relaxation.

14 (1896) 7 QLJ 68 at 70-71; see also Mackay v Dick (1861) 6 App Cas 251 at 263; Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596 at 607; Nullagine Investments Pty Ltd v Western Australian Club Inc (1993) 177 CLR 635 at 659; Fitzgerald v FJ Leonhardt Pty Ltd (1997) 189 CLR 215 at 219.

15        Australian Course Grains Pool Pty Ltd v Barley Marketing Board [1989] 1 QR 499 at 507

16 (1904) 1 CLR 632 at 647

17        Barque Quilpué Ltd v Brown [1904] 2 KB 264 at 271

21

[56]     As the plaintiffs submitted, the defendant breached the terms of the agreement by making application to the Council for the relaxation.  The plaintiffs thereby suffered damages,  in  that  they  were  prevented  from  successfully  negotiating  with  the Council for the relaxation themselves and thereby bringing the relaxation within the scope of clause 4.05 entitling them to payment.  The relaxation would have been achieved whether made by plaintiffs or the defendant.  The only reason which prevented the plaintiffs’ successful application for relaxation was the successful application by the defendant.

Conclusion

[57]     The plaintiffs should be awarded damages for breach of contract in the sum of

$441,747.07, being $340,200.00 plus interest of $98,716.12 until 14 March 2001

and $2,830.95 until the date of judgment.

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

5

Statutory Material Cited

0

Slee v Warke [1949] HCA 57