SUPREME COURT OF QUEENSLAND
CITATION: Goldtaper P/L & Ors v Berela Ltd [2001] QCA 564 PARTIES: GOLDTAPER PTY LTD (ACN 010 588 815)
(subject to a Deed of Company Arrangement)
(first plaintiff/first respondent)
HARACLIFF PTY LTD (ACN 010 820 809)
(second plaintiff/second respondent)
KEMBROOK PTY LTD (ACN 010 839 933)
(third plaintiff/third respondent)
v
BERELA LIMITED (ACN 010 671 315)
(defendant/appellant)FILE NO/S: Appeal No 3540 of 2001
SC No 10989 of 1998DIVISION: Court of Appeal PROCEEDING: General Civil Appeal ORIGINATING COURT: Supreme Court at Brisbane
DELIVERED ON: 14 December 2001 DELIVERED AT: Brisbane HEARING DATE: 11 October 2001 JUDGES: Davies and Thomas JJA and Cullinane J
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDER: Appeal dismissed with costs CATCHWORDS: CONTRACT - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - IMPLIED TERMS - TERMS ESSENTIAL TO ENABLE PERFORMANCE - where contract for sale of land to builder developer - external road works required for proposed development - negotiations for sale of land conducted in context that contribution to external road works may be imposed by council on a per lot basis - where special conditions in contract acknowledging that relaxation of previously proposed amount for road contribution may be sought and providing for that event - where clause premised only upon vendors' success in negotiation relaxation - where purchaser in fact negotiated the relaxation - where competing constructions placed upon clause intended to avoid occurrence of windfall profit to purchaser - where factual context accordingly relevant to proper construction of the clause - where application by purchaser for relaxation prevented vendors from performing part of the contract - whether implied term that relaxation be obtained within a fixed time - whether breach of fundamental implied term that neither party will do anything to prevent the other from performing the contract
CONTRACT - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - OTHER MATTERS - where factual context relevant to proper construction of contract
CONTRACT - GENERAL CONTRACTUAL PRINCIPLES - DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH - OTHER MATTERS - breach of fundamental implied term
Codelfa Constructions Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337, referred to
Marshall v Colonial Bank of Australia (1904) 1 CLR 632, referred to
Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 569, appliedCOUNSEL: P D McMurdo QC for appellant
J Bell QC, with J D McKenna for respondentsSOLICITORS: Corrs Chambers Westgarth for appellant
Hopgood Ganim Lawyers for respondents
DAVIES JA:
1.The questions in issue
This is an appeal from a judgment in the Trial Division of this Court for damages for breach of a contract for sale of land. The appellant, the unsuccessful defendant, was the purchaser of the land and the respondents, the successful plaintiffs, were the vendors. The damages were for breach of the fundamental term implied in all contracts that…
Keep reading for free
Create a free CaseChat account to read Goldtaper P/L v Berela Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2001] QCA 564
- Decision Date
CaseChat Overview and Summary
The court was required to decide on the proper construction of the clause that acknowledged the potential relaxation of the road contribution amount. The clause was premised only upon the success of the vendors in negotiating the relaxation. However, it was the purchaser who actually negotiated the relaxation. The court had to consider competing constructions of the clause, which aimed to avoid a windfall profit for the purchaser, and determine the relevance of the factual context to the proper construction of the clause. Additionally, the court had to assess whether the purchaser's application for relaxation prevented the vendors from performing part of the contract, and if such an action constituted a breach of the fundamental implied term.
The court found that the factual context was indeed relevant to the proper construction of the clause. It held that the clause was intended to avoid the occurrence of a windfall profit for the purchaser. The court also determined that the purchaser's actions in applying for the relaxation did prevent the vendors from performing part of the contract, which constituted a breach of the fundamental implied term. The appeal by Goldtaper P/L was dismissed, with costs awarded against them. The court's reasoning was based on the interpretation of the contract and the application of the principles of contract law, particularly the fundamental implied term that neither party will do anything to prevent the other from performing the contract.
Orders
Orders of the court
Appeal dismissed with costs
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.