| CITATION: | Godbold v Queensland Building and Construction Commission [2014] QCAT 537 |
| PARTIES: | Grant Allan Keith Godbold Julianne Jennifer Godbold (Applicants) |
| v | |
| Queensland Building and Construction Commission (Respondent) |
| APPLICATION NUMBER: | GAR080-13 |
| MATTER TYPE: | General administrative review matters |
| HEARING DATE: | 17 March 2014 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Howe |
| DELIVERED ON: | 12 August 2014 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The decision of the Commission made 25 January 2013 assessing the applicants’ entitlement under the statutory home warranty scheme as nil is set aside. 2. The Applicants are entitled to be paid the sum of $44,157.23 for their claim under the statutory home warranty scheme. |
| CATCHWORDS: | Statutory Home Warranty scheme – completion of work under the construction contract – dispute as to variations – variations not in writing – prepayment by the owner before payment due under the contract – indemnity insurance – payment for loss – delay in Commission recognition of termination – completion of the work by the owners – actual costs of completion – expert evidence – reduced value of expert evidence – assumptions of fact by expert – owners resiling from some of the contract work after termination – Commission to act reasonably in estimating owners remaining liability under the contract |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Gregory Richards, Solicitor, represented Mr and Mrs Godbold |
| RESPONDENT: | Ms Cheriden Farthing, Solicitor, represented the Queensland Building and Construction Commission |
REASONS FOR DECISION
Mr and Mrs Godbold own a home at Shailer Park. They wanted to renovate and expand. They signed a fixed-price building contract with Mr Camilleri, a builder, on 27 July 2009. The agreed cost was $363,446.
There were eight staged progress payments under the contract not including the deposit. The final two were for fixing and practical completion, each for $36,344.60. There were a number of variations to the contract which increased the price. They were not in writing.
Mr Camilleri found himself in financial difficulties. He asked for more money to keep him going with the rest of the job. The Godbolds acknowledged they owed him for variations. On 25 February 2010 they wrote him out two cheques, each for $36,344.60, the progress payment amounts for the remaining two stages of work[1].
[1]Exhibit 2 at [70].
Mr Camilleri did not finish the job. He met Mr Godbold on 20 March 2010 and said to do that it would take another $163,523.03. The Godbolds refused to pay that additional sum and on 27 March 2010 terminated the contract. They made complaint to the Queensland Building and Construction Commission (the Commission) and thereby claimed under the statutory home warranty scheme. The Commission initially disallowed the claim on the basis the contract had not been properly terminated. The Godbolds applied to the Tribunal for review of that decision and they were successful[2]. The issue of the amount of their claim was remitted to the Commission. The Commission determined their entitlement was nil. The Godbolds have brought this present application seeking review of that assessment.
Keep reading for free
Create a free CaseChat account to read Godbold v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] QCAT 537
- Decision Date
CaseChat Overview and Summary
The primary legal issues for the court to determine were whether the Commission was correct in its assessment of the applicants' entitlement under the statutory home warranty scheme as nil, and if the applicants were entitled to compensation for the variations and the costs associated with completing the work after the contract was terminated. The court also had to consider the validity of the expert evidence presented by the applicants and whether the assumptions made by the expert were reasonable.
The court found that the Commission's decision to assess the applicants' entitlement as nil was incorrect. The court held that the Commission had failed to act reasonably in estimating the applicants' remaining liability under the contract. The court also found that the expert evidence, despite some reduced value due to certain assumptions, was sufficient to establish the applicants' entitlement to compensation. The court concluded that the applicants were entitled to be paid the sum of $44,157.23 for their claim under the statutory home warranty scheme.
The court ordered that the decision of the Commission made on 25 January 2013, which assessed the applicants' entitlement under the statutory home warranty scheme as nil, be set aside. The applicants were awarded the sum of $44,157.23 for their claim under the statutory home warranty scheme.
Orders
Orders of the court
1. The decision of the Commission made 25 January 2013 assessing the applicants’ entitlement under the statutory home warranty scheme as nil is set aside.
2. The Applicants are entitled to be paid the sum of $44,157.23 for their claim under the statutory home warranty scheme.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.