Galileo Miranda Nominee Pty Ltd v Duffy Kennedy Pty Ltd

Link copied
Case Copied 45 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Galileo Miranda Nominee Pty Ltd v Duffy Kennedy Pty Ltd [2019] NSWSC 1157
Hearing dates: 1, 2, 3 July 2019; 9 August 2019
Date of orders: 06 September 2019
Decision date: 06 September 2019
Jurisdiction:Equity - Technology and Construction List
Before: Parker J
Decision:

6 September 2019

Catchwords:

CONTRACT – Breach of Contract – where Principal sought order that Contractor complete penetration schedule and provide copies of subcontracts – whether Principal’s take-out notice valid – whether Contractor entitled to suspend works by non-payment of interest on progress claim under Building and Construction Industry Security of Payment Act 1999 (NSW) – whether Contractor failed to proceed with due diligence in a competent manner and failed to comply with principal certifier’s occupation certificate requirements – whether Contractor otherwise validly suspended works with “reasonable cause”.

 

BUILDING AND CONSTRUCTION – construction contracts – Building and Construction Industry Security of Payment Act 1999 (NSW) – whether Contractor entitled to suspend works by Principal’s non-payment of interest on progress payment – whether interest accrued under s 11 forms part of “scheduled amount” under s 27(1) – “scheduled amount” comprises amount respondent “proposes to make” identified in payment schedule but excludes interest under s 11 - need to quantify interest in final way - accrual of interest to be interpreted consistently with statutory entitlement under Civil Procedure Act 2005 (NSW), s 100.

 

CONTRACT – Breach of Contract – whether Contractor entitled to suspend contract with “reasonable cause” by acting reasonably and in good faith – whether “reasonable cause” determined subjectively or objectively – suspension without “reasonable cause”.

 

CONTRACT – Breach of Contract – whether Contractor failed to proceed with due diligence in a competent manner and failed to comply with principle certifier’s occupation certificate requirements – whether error by PCA deprives its determination of contractual effect – Legal & General v A Hudson – erroneous view taken by PCA no answer to Contractor’s failure to satisfy preconditions to issue of occupation certificate – foreshadowed claim for extension no answer to Contractor’s failure to proceed with works in diligent manner.

CONTRACT – Breach of Contract – whether default notice valid – whether notice “issued” by Principal’s Representative – whether Principal’s Representative gave adequate or proper consideration to whether notice should be issued – notice “issued” where Principal’s Representative authorised release of notice without taking active role in preparation – notice acts as precursor to rights to terminate and not invalidated by technical deficiencies where commercial purpose achieved.

 

CONTRACT – Breach of Contract – whether Principal’s show-cause and take-out notices valid – whether power to take work out of Contractor’s hands subject to implied obligations of good faith and reasonableness – determination by Principal’s Representative closely connected with Principal’s exercise of power to terminate – Principal’s Representative validly formed determination.

 

EVIDENCE — Privileges — Without prejudice privilege – whether under contractual procedure Principal’s Representative entitled to consider discussions during “without prejudice” meeting when determining whether Contractor failed to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Galileo Miranda Nominee Pty Ltd v Duffy Kennedy Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWSC 1157
Decision Date

CaseChat Overview and Summary

Galileo Miranda Nominee Pty Ltd (the Principal) sued Duffy Kennedy Pty Ltd (the Contractor) over alleged breaches of contract. The Principal sought an order for the Contractor to complete the penetration schedule and provide copies of subcontracts. The dispute also included whether the Principal’s take-out notice was valid and whether the Contractor was entitled to suspend works due to non-payment of interest on a progress claim under the Building and Construction Industry Security of Payment Act 1999 (NSW). Additionally, the Principal argued that the Contractor failed to proceed with due diligence in a competent manner and did not comply with the principal certifier’s occupation certificate requirements. The Contractor claimed it had reasonable cause to suspend works.

The court addressed whether the Contractor was entitled to suspend works due to the Principal’s non-payment of interest on a progress payment. It considered whether interest accrued under section 11 of the Act forms part of the "scheduled amount" under section 27(1). The court determined that interest must be quantified in a final way and its accrual should be interpreted consistently with statutory entitlement under the Civil Procedure Act 2005 (NSW), section 100. The court also assessed whether the Contractor was entitled to suspend works with reasonable cause and whether it failed to proceed with due diligence and comply with the certifier’s requirements. The court concluded that the Contractor’s erroneous view did not negate its failure to satisfy the preconditions for the issue of an occupation certificate.

The court found that the Principal’s default notice was valid as it was authorised by the Principal’s Representative, even though the Representative did not take an active role in its preparation. The notice served as a precursor to the rights to terminate and was not invalidated by technical deficiencies where its commercial purpose was achieved. The court also found that the Principal’s show-cause and take-out notices were valid, as the Representative’s determination was closely connected with the Principal’s exercise of power to terminate. The court concluded that the Principal’s Representative validly formed the determination.

The final orders of the court were that the Principal’s default notice and show-cause and take-out notices were valid, and the Contractor was not entitled to suspend works on the grounds presented. The court also ruled that the Principal was entitled to the return of the contractual security, which extended to the Principal’s claim for unliquidated damages.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established