Frances Park (Darwin) Pty Ltd v Chin
[2009] NTSC 45
•16/09/2009
Frances Park (Darwin) Pty Ltd v Chin & Anor [2009] NTSC 45
PARTIES: FRANCES PARK (DARWIN) PTY LTD (ACN 090 382 219) v ANDREW CHIN And: CHUN LOI CHIN TITLE OF COURT: SUPREME COURT OF THE
NORTHERN TERRITORYJURISDICTION: SUPREME COURT OF THE
NORTHERN TERRITORY
EXERCISING TERRITORY
JURISDICTIONFILE NO: AP 3 of 2009 (20911320) DELIVERED: 16 September 2009 HEARING DATE: 31 July 2009 JUDGMENT OF: RILEY and SOUTHWOOD JJ and
OLSSON AJAPPEAL FROM: MARTIN (BR) CJ CATCHWORDS: APPEAL – CONTRACTS –VENDOR AND PURCHASER – construction of clause – failure to discharge obligation – valid rescission of contract – appeal dismissed
Toll (FGCT) Pty Ltd v Alpharpharm Pty Ltd (2004) 219 CLR 165, followed
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451, referred toREPRESENTATION:
Counsel:
Appellant: I C Robertson SC Respondent: A Wyvill Solicitors:
Appellant: CridlandsMB Respondent: T S Lee & Associates Judgment category classification: B
Judgment ID Number: Ril0913 Number of pages: 14 IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN
| [1] | declarations that they had validly terminated three contracts for the sale of |
Frances Park (Darwin) Pty Ltd v Chin & Anor [2009] NTSC 45
No AP 3 of 2009 (20911320)
BETWEEN:
FRANCES PARK (DARWIN) PTY LTD
(ACN 090 382 219)Appellant
AND:
ANDREW CHIN
First Respondent
AND:
CHUN LOI CHIN
Second Respondent
CORAM: RILEY and SOUTHWOOD JJ and OLSSON AJ REASONS FOR JUDGMENT (Delivered 16 September 2009)
RILEY J:
On 20 May 2009, in the Supreme Court, the respondents were granted thereon. The appellant has appealed against the judgment on the ground that the learned trial Judge erred in his construction of the relevant clause of the contract and also challenging his exclusion of certain evidence.
| [4] | of the Parent Parcel may have caused contamination. Possible |
| [2] | dispute. The land in question had been used as an oil storage facility |
As the learned trial Judge noted the essential facts of the matter were not in Parcel (“the Land”). Settlement on the contracts was due on 5 January 2009.
On 30 January 2009 the respondents purported to exercise a power of rescission with respect to each of the contracts.
At the time the contracts were executed the parties were aware that past use the Environmental Auditor’s Report in respect of the Parent Parcel along with access to the full Environmental Auditor’s Report. The contract recorded that the appellant was not responsible for the contents of the report and "the purchaser should obtain its own advice in relation to, and satisfy itself as to, the environmental status of the Parent Parcel" and of the Land. In addition, each contract included a clause (cl 11) in which the respondents acknowledged that the decision on their part to purchase the Land was the result of their own investigations and enquiries and that they did not rely upon any warranty, representation or assurance given by the appellant.
In the proceedings before the learned trial Judge the issue was whether the appellant had failed to comply with the requirements of cl 31.3 of each contract thereby giving rise to the right to rescind. Clause 31 of each contract was in the following terms:
31. REMEDIAL WORKS
The Purchaser acknowledges:
(a) that certain parts of the Parent Parcel (which may include the Land) may contain residual levels of petroleum hydrocarbons, and may be subject to remediation works in respect of those levels; (b) preliminary information regarding the environmental
status and remediation of the Parent Parcel, provided to
the Purchaser a copy of a summary of the
Environmental Auditor’s Report in respect of the Parentthat Frances Park has, with the intent of providing Annexure C and has notified the Purchaser that a copy of the full Environmental Auditor’s Report may be obtained from the Northern Territory Department of Infrastructure Planning and Environment; and
(c)
Frances Park is not responsible for the contents of the Environmental Auditor’s Report and the Purchaser should obtain its own advice in relation to, and satisfy itself as to, the environmental status of the Parent Parcel and the Land.
31.2 The Purchaser:
(a)
| [6] | cl 31.3 had been complied with by virtue of a document dated 28 June 2007 |
acknowledges that there are ground wells located installed for the purpose of monitoring levels of petroleum hydrocarbons in the groundwater in the vicinity of the Land;
(b)
acknowledges that BP Australia Pty Ltd, as the previous proprietor of the Parent Parcel, requires access to the ground wells for the purpose of carrying out a monitoring program;
(c)
must not interfere or allow others to interfere with the ground wells or allow anything to be built over the top of those ground wells or
obstruct access to those ground wells in any
way.
31.3 This Agreement is subject to and conditional on Frances
Park providing to the Purchaser written confirmation
from an accredited environmental auditor that the Land
is suitable for residential use and occupation, subject to
there being no use of the phreatic groundwater from the
Parent Parcel other than for the purpose of
environmental monitoring.31.4 If clause 31.3 is not satisfied at least 2 days before the
date for completion, the Purchaser may at any time prior
to completion whilst clause 31.3 remains unsatisfied,
rescind this Agreement by notice in writing to Frances
Park.
It was the submission of the appellant before the learned trial Judge that was in similar terms to the Environmental Auditor’s Report attached to the contract as annexure C, was in the following terms:
STATEMENT OF ENVIRONMENTAL AUDIT
Environment Protection Act 1970 (‘the Act’) as an environmental auditor for the purposes of the Act, as recognised in the Northern Territory, having
I, Adrian Hall of URS Australia Pty Ltd, a person appointed by the the
1. been requested by BP Australia Pty Ltd to issue a statement of (17) Dinah Beach Road, Town of Darwin (formally Remediation Zone 2 of the BP Darwin Terminal) Northern Territory (‘the site’) owned/occupied by Frances Park (Darwin) Pty Ltd
2. had regard to, amongst other things,
(i) endorsed by the Northern Territory Department of
relevant guidelines issued by the Victorian EPA and including guidelines issued by the National Environment Protection Council
(ii) the beneficial uses that may be made of the site, and
(iii) relevant environment protection policies, related waste management policies, and planning instruments
in making a total assessment of the nature and extent of any
harm or detriment which may be caused to, or the risk of any
possible harm or detriment which may be caused to, any
beneficial use made of the site by any industrial processes or
activity, waste or substance (including any chemicalsubstance), and
completed an environmental audit in general accordance with
Section 53X of the above Act insofar as it applies to the
Northern Territory, a copy of which report and statement of
environmental audit has been sent to the Department of Natural
Resources, Environment and the Arts;
| [7] |
HEREBY STATE that I am of the opinion that
The site is suitable for the beneficial uses associated with:
• single dwelling residential living
•
all uses permitted under the Northern Territory Planning Scheme, as amended 13 June 2007, for SD20 Zone,
subject to the following conditions attached thereto:
(i) There should be no use of groundwater from the site, other than for the purposes of environmental monitoring.
(ii) Within six (6) months of the date of this Environmental Audit Report, an appropriate Groundwater Monitoring and Management Plan (GMMP) for the former Terminal site will be prepared by BP Australia Pty Ltd, and submitted for approval by a Victorian EPA accredited Environmental Auditor and by NRETA, prior to implementation.
I have not issued the equivalent of an unconditional Certificate of Environmental Audit for the site in its current condition, the reasons for which are presented in the environmental audit
report and are summarised as follows:
(i) Groundwater is polluted in wells on the site, with elevated levels of some heavy metals.
This statement of environmental audit forms part of the following environmental audit report.
A preliminary issue
In its written submissions the appellant raised, as a preliminary issue, for summary judgement or as a final hearing. Reference to the transcript of the proceedings before his Honour makes it clear that the parties proceeded on the basis of a "final hearing in this matter", being of the Originating Motion. The appellant did not contend otherwise before this Court.
Ground 1: Construction of clause 31
In construing cl 31 the learned trial Judge applied the principle stated in the judgment of the High Court in Toll (FGCT) Pty Ltd v Alpharpharm Pty Ltd[1]:
Pacific Carriers Ltd v BNP Paribas Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at 461 - 462 [22]].
This Court, in [(2004) 218 CLR be understood as referring to what a reasonable person would understand by the language in which the parties have expressed their agreement. The meaning of the terms of a contractual document is to be determined by what a reasonable person would have understood them to mean. That, normally, requires consideration not only of the text, but also of the surrounding circumstances known to the parties, and the purpose and object of the transaction [
451], has recently reaffirmed the principle of objectivity by which
the rights and liabilities of the parties to a contract are determined.
It is not the subjective beliefs or understandings of the parties about
their rights and liabilities that govern their contractual relations.
What matters is what each party by words and conduct would have
led a reasonable person in the position of the other party to believe.His Honour identified the relevant "surrounding circumstances" as including the fact that the Parent Parcel had previously been used for purposes which had or were likely to have resulted in contamination of the Land rendering the Land unfit for residential purposes. He referred to cl 11 and then concluded that:
"(T)he primary purpose of clause 31.3 is readily ascertained as
providing the purchasers with an assurance that, subject to phreatic
groundwater not being used for any purpose other than environmental
monitoring, the land being purchased by the purchasers was fit for
the intended use, namely, “residential use and occupation".The learned trial Judge found that the Statement of Environmental Audit did not discharge the obligation of the appellant under cl 31.3 of the contracts and concluded that the respondents were entitled to rescind the contracts.
| [11] |
The appellant accepted that the learned trial Judge applied the correct test as in the passage quoted from Alpharpharm. However, the appellant submitted that in the context of this case the "surrounding circumstances" supported the construction of cl 31.3 as requiring two elements namely:
(a) written confirmation from an accredited environmental auditor; (b) that the land "is suitable for residential use and occupation”.
The appellant submitted that, for the purpose of the prescribed use and occupation, the phreatic groundwater from the Parent Parcel can be used for environmental monitoring. The assessment of the Land may be by reference to attributes beyond the Land. The appellant contended that the so-called "conditions" referred to by the Auditor were not conditions relating to the suitability of the land for residential purposes but, rather, related solely to the use of groundwater for monitoring and management purposes. The appellant submitted that, at the time of delivery of the Statement, the Land was suitable for residential purposes and the Statement constituted "written confirmation from an accredited environmental auditor" that this was so.
It was submitted that the effect of his Honour's construction was to treat the use of the phreatic groundwater from the Parent Parcel as a condition and the proposed environmental monitoring as a second condition. It was submitted that the learned trial Judge misconstrued cl 31.3 and misread the Statement of Environmental Audit confirmation by impliedly finding that the "second proviso" or condition meant that the land was not "suitable for residential use and occupation".
| [15] |
|
To interpret the contract it is necessary to apply the "principle of objectivity" referred to in Alpharpharm. The meaning of clause 31.3 is to be determined by what a reasonable person would have understood the clause to mean by reference to the text of the clause, the surrounding circumstances known to the parties and the purpose and object of the transaction.
| [17] | respondents reveals that, whilst the author expressed the opinion that the |
In the light of that background the learned trial Judge determined, in my view correctly, that:
(T)he primary purpose of clause 31.3 is readily ascertained as
providing the purchasers with an assurance that, subject to phreatic
groundwater not being used for any purpose other than environmental
monitoring, the land being purchased by the purchasers was fit forthe intended use namely, "residential use and occupation".
Reference to the Statement of Environmental Audit provided to the under the Northern Territory Planning Scheme, he deliberately did not issue an unconditional certificate for the Land "in its current condition" because "groundwater is polluted in wells on the site, with elevated levels of some heavy metals".
| [18] |
|
In the Statement of Environmental Audit an additional qualification was added by the author. That qualification required a Groundwater Monitoring and Management Plan to be prepared by BP Australia Pty Ltd, which company was not a party to the contract, and submitted to other third parties prior to implementation. The qualification went beyond reserving the right to use the phreatic groundwater for "environmental monitoring" and referred to "management" and to the implementation of a management plan.
[20] As the learned trial Judge observed:
It is not surprising that the existence of such a plan would be a
precondition to the land being suitable for residential use. Without
such a plan, particularly with respect to management of contaminated
groundwater, the land might not be suitable for residential use
because of the presence of that contaminated groundwater.
In my opinion the Statement of Environmental Audit did not convey to a reasonable purchaser, a person without the expertise of an environmental auditor, confirmation that the Land was suitable for residential use and
occupation. On its face the Statement qualified the opinion of the
environmental auditor by requiring an appropriate plan for groundwater
monitoring and management to have been submitted for approval by relevant
authorities and, presumably, then implemented.
Further, it is to be noted that the Statement of Environmental Audit provided to the respondents included a provision that the Statement was to be read as part of the environmental audit report. A reading of that report reveals the following disclaimer (at Section 14):
Opinions and judgments expressed herein are based on the Auditor’s understanding of current regulatory standards and should not be construed as legal opinions. This document and the information contained herein have been prepared for the use of the client (BP Australia Pty Ltd), the Northern Territory Government and the relevant Planning Authority. Any reliance on this report by third parties shall be at such parties’ risk.
The purchasers were "third parties" for the purposes of the disclaimer and were expressly excluded from relying upon the report other than at their own risk. That is contrary to the purpose of the written confirmation to be provided pursuant to cl 31.3 of the contract.
I see no error on the part of the learned trial Judge in concluding that the Statement of Environmental audit did not discharge the obligation of the appellant under cl 31.3 of the contracts.
| [25] |
| ||
| [26] |
|
Ground 2: The exclusion of evidence
At the hearing before the learned trial Judge the appellant sought to rely upon an affidavit sworn by the author of the Statement of Environmental Audit seeking to explain and clarify the Statement. The learned trial Judge
excluded the whole of the affidavit explaining that the content of the
Statement determined the rights and liabilities of the parties pursuant to
cl 31.3 of the contract. Those rights and liabilities were not to be
determined by any subjective intention of the author of the document which,
at the time of presentation of the document and the purported rescission, was
not communicated to the respondents and was unknown by them. This was
not a matter where the common knowledge of the parties suggested there
was any ambiguity in the document which required explanation.
[28] There was no error in excluding the evidence.
[29] The appeal should be dismissed.
SOUTHWOOD J:
I agree with Riley J and have nothing further to add.
OLSSON AJ:
[31] I also agree and have nothing further to add.
[1] (2004) 219 CLR 165
0
1
0