Firedam Civil Engineering Pty Ltd v Shoalhaven City Council

Link copied
Case Copied 22 min read
CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802
HEARING DATE(S): 24 July 2009
 
JUDGMENT DATE : 

12 August 2009
JURISDICTION: Equity
JUDGMENT OF: Tamberlin AJ
DECISION: The Summons in this matter is dismissed with costs.
CATCHWORDS: EXPERT DETERMINATION - principles concerning adoption of expert determination - errors - inconsistencies - failure to give reasons - failure to address issues
CATEGORY: Principal judgment
CASES CITED: Holt v Cox (1997) 23 ACSR 590
Campbell v Edwards [1976] 1 WLR 403
Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314
Capricorn Inks Pty Ltd v Lawter International (Australasia) Pty Ltd [1989] 1 Qd R 22
AGLVictoria Pty Ltd v SPI Networks (Gas) Pty Ltd (2006) Aust Contract Reports 90-241
Adwell Holdings Pty Ltd v Bourne [2007] NSWSC 730
Kanivah Holdings Pty Ltd v Holdsworth Properties Pty Ltd & Ors [2001] NSWSC 405
Peak Constructions (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 111
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211
PARTIES: Firedam Civil Engineering Pty Limited (Plaintiff)
Shoalhaven City Council ABN 11 005 357 522 (Defendant)
FILE NUMBER(S): SC 55037/2009
COUNSEL: G Inatey SC (Plaintiff)
J A Steele (Defendant)
SOLICITORS: Colin Biggers & Paisley (Plaintiff)
TressCox (Defendant)


IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST

TAMBERLIN AJ

12 AUGUST 2009

          SHOALHAVEN CITY COUNCIL

JUDGMENT

1 HIS HONOUR: This is an application by the plaintiff (“Firedam”) for declarations that an Expert Determination arising from a dispute with the defendant (“Shoalhaven”) is not binding on it and that, on the proper construction of the contract between the parties, Firedam is entitled to commence legal proceedings against Shoalhaven.

2 The issue, briefly stated, is whether the declarations should be made.

How the issue arises?

3 Firedam as contractor and Shoalhaven as principal on 18 October 2005 entered into a contract in respect of the design and construction of a wastewater collection and transportation system for the Conjola Regional Sewage Scheme.

4 Disputes arose under the contract relating to variation claims by Firedam and consequential extension of time claims. Under the contract, disputes and issues arising must be referred for Expert Determination and there is a threshold amount which, if awarded, permits the parties to proceed to litigation. That amount is $500,000. In the present case, the amount of the determination by the Expert against Shoalhaven was marginally below this, being about $497,142.55.

5 The contract provides that unless a party has a right to commence litigation the parties must treat each determination of the Expert as final and binding and give effect to it (Clause 75.7). Under Clause 75.6, where the determination is under $500,000 then litigation can only be commenced within 56 days after receiving the Determination. In this case, the last date on which Firedam could commence legal proceedings was 12 May 2009. Assuming that Firedam had a contractual entitlement to bring the legal proceedings it is said that it…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Firedam Civil Engineering Pty Ltd v Shoalhaven City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NSWSC 802
Decision Date

CaseChat Overview and Summary

The case of Firedam Civil Engineering Pty Ltd v Shoalhaven City Council was heard by the Supreme Court of New South Wales. Firedam, a civil engineering company, initiated legal proceedings against Shoalhaven City Council, a local government authority, to challenge an expert determination issued by the council. The dispute centred on the council's assessment of Firedam's compliance with a building permit and the associated costs and penalties imposed.

The legal issues that the court was required to address involved the principles governing the adoption of expert determinations in such contexts, specifically whether the council's determination was flawed due to errors, inconsistencies, and a failure to provide reasons or address key issues. Firedam argued that the council's determination was improper because it did not properly consider certain evidence, contained internal inconsistencies, and failed to adequately address the critical issues at hand.

In delivering the judgment, the court thoroughly examined the principles concerning the adoption of expert determinations. It was determined that the council's determination was indeed flawed due to errors and inconsistencies, and notably, the council had not provided adequate reasons for its conclusions, nor had it addressed all the pertinent issues. The court found that these deficiencies rendered the determination invalid. Consequently, the court quashed the council's expert determination and remitted the matter back to the council for reconsideration in accordance with the correct legal principles.

The final orders included the quashing of the council's expert determination and the direction that the matter be reconsidered by the council in light of the court's findings. The court's decision underscored the importance of adherence to proper procedures and the provision of clear, reasoned justifications in the context of expert determinations issued by local authorities.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established