| CITATION: | Feldis Holdings Pty Ltd t/as PGS Constructions v Tweddell & Anor [2013] QCAT 164 |
| PARTIES: | Feldis Holdings Pty Ltd t/as PGS Constructions (Applicant) |
| v | |
| Rebecca Jane Tweddell Mr James Tweddell (Respondents) |
| APPLICATION NUMBER: | BDL228-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 23 and 24 August, 2012 and 9 November, 2012 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Ann Fitzpatrick |
| DELIVERED ON: | 12 April 2013 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The respondents pay to the applicant the sum of $38,457.29 within 21 days of the date of this Order. 2. The parties file and serve written submissions in relation to costs by 19 April, 2013 and that they file and serve any submissions in reply by 26 April, 2013. |
| CATCHWORDS: | DOMESTIC BUILDING CONTRACT – implication of terms - variations not in writing – provisional sums – deemed practical completion stage Ansett Transport Industries v Commonwealth (1977) 139 CLR 54 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Feldis Holdings Pty Ltd trading as PGS Constructions represented by Mr Paul Stringer, Director |
| RESPONDENT: | Rebecca Jane Tweddell and Mr James Tweddell represented by Mr J Hitchcock, Rudkin Hitchcock Grant, Lawyers |
REASONS FOR DECISION
The applicant is a building contractor. Its director Mr Stringer is its nominee. Mr Stringer conducted this matter on behalf of the applicant and was its principal witness at the hearing.
The history of this matter is that the respondents, Mr and Mrs Tweddell had engaged another building contractor, Palladio Homes Pty Ltd, to construct a home at Sovereign Island. Mr Stringer was employed as a supervisor on the job by Palladio Homes.
The contract with Palladio Homes was terminated before construction was completed. Feldis Holdings Pty Ltd trading as PGS Constructions agreed through Mr Stringer, to enter into a contract with the Tweddells’ to complete the house.
Mr Stringer asserts that Feldis has not been paid the balance of the contract sum, payment for variations, including GST, payment for provisional sum items, including rectification of work performed by Palladio Homes, payment for repairs to flood damaged areas and interest calculated at 10% per day on outstanding money. During the course of the hearing certain concessions were made which affect the quantum of the applicant’s claim. Feldis has not recalculated the quantum of its claim. I will attempt to do so at the conclusion of this decision.
The Tweddells’ deny any liability to Feldis under the contract and assert by counter-application that they are entitled to payment of the sum of $55,091.22 from Feldis, calculated as follows:
·Total Contract Value $747,311.55
Less
·Bank payments $706,549.11
·Advance payments
Keep reading for free
Create a free CaseChat account to read Feldis Holdings Pty Ltd t/as PGS Constructions v Tweddell and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] QCAT 164
- Decision Date
CaseChat Overview and Summary
The primary legal issue revolved around whether the additional works performed by the applicant could be deemed to be part of the original contract due to the lack of written documentation. The court had to assess if the absence of written confirmation of the variations nullified their enforceability and if the provisional sums were sufficient to cover the costs of these works. Another important aspect was to ascertain whether the works in question were performed during the practical completion stage, which could affect the respondent’s liability for the additional costs.
The court held that the additional works were indeed part of the original contract terms and that the lack of written confirmation did not render them unenforceable. It was determined that the provisional sums allocated in the contract did not cover the full extent of the additional works performed. The court further ruled that the additional works were completed during the practical completion stage, thus the respondent remained liable for these costs. Consequently, the court ordered the respondent to pay the applicant the sum of $38,457.29 within 21 days. Additionally, the court mandated that both parties submit written submissions on costs by specified dates.
Orders
Orders of the court
1. The respondents pay to the applicant the sum of $38,457.29 within 21 days of the date of this Order.
2. The parties file and serve written submissions in relation to costs by 19 April, 2013 and that they file and serve any submissions in reply by 26 April, 2013.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.