NEW SOUTH WALES COURT OF APPEAL
CITATION: Fekala Pty. Ltd. v. Castle Constructions Pty. Ltd. [2002] NSWCA 297
FILE NUMBER(S):
40222/02
HEARING DATE(S): 7 August 2002
JUDGMENT DATE: 07/08/2002
PARTIES:
Fekala Pty. Limited - appellant
Castle Constructions Pty. Limited - respondent
JUDGMENT OF: Beazley JA Hodgson JA Santow JA
LOWER COURT JURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S): ED 3812/01
LOWER COURT JUDICIAL OFFICER: Windeyer J
COUNSEL:
Mr. B. Skinner for appellant
Mr. D. Officer QC with Mr. D.L. Warren for respondent
SOLICITORS:
Nugent Wallman & Carter, Edgecliff for appellant
Day Dockrill, Neutral Bay for respondent
CATCHWORDS:
CONTRACTS
CONVEYANCING - Vendor and purchaser - Notice to complete - Whether party giving a notice to complete can deny its validity - Whether party giving a notice to complete can unilaterally extend the time limited by the notice - Need for notice making time of the essence to be explicit - Whether vendor's notice to complete waived submission of transfer.
LEGISLATION CITED:
DECISION:
Appeal dismissed with costs.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 40222/02
ED 3812/01BEAZLEY JA
HODGSON JA
SANTOW JAFriday 6 September 2002
FEKALA PTY. LIMITED V.
CASTLE CONSTRUCTIONS PTY. LIMITED
Judgment
BEAZLEY JA: I agree with the reasons of Hodgson JA as set out below.
HODGSON JA: Proceedings were commenced in the Equity Division on 1st August 2001 by the respondent Castle Constructions Pty. Limited (the Purchaser) against the appellant Fekala Pty. Limited and others (the Vendors) in relation to a contract for sale by the Vendors to the Purchaser of property at Eastwood. The proceedings initially sought declarations as to what was included in the sale; but on 29 August 2001, the Purchaser gave notice that it terminated the contract, and by an Amended Summons (later further amended) the Purchaser claimed a declaration that the contract had been terminated, return of the deposit, and damages. By a cross-claim in the proceedings, the Vendors sought specific performance and damages, and alternatively a declaration that they were entitled to the deposit.
Windeyer J gave judgment in the proceedings on 26 February 2002, and on 1 March 2002 made orders granting the relief sought by the Purchaser (including an enquiry as to damages) and dismissed the Vendors’ cross-claim. The Vendors appeal to this Court from those orders.
FACTS
The contract was entered into on 28 June 2001, in the form of the 2000 edition of the Standard Contract for the Sale of Land. The Vendors were named as “Fekala Pty. Limited and others as mortgagees exercising power of sale pursuant to registered mortgage No.6152594”. The contract was signed on behalf of the Vendors by their solicitor: no issue is now raised by reason of that circumstance. The completion date was specified as the 42nd day after the contract date, which was in fact 9 August 2001. The price was $3 million, with a deposit of $300,000.00.
The names of the Vendors were set out in Annexure A to the contract.…
Continue reading Fekala Pty Ltd v Castle Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Fekala Pty Ltd v Castle Constructions Pty Ltd [2002] NSWCA 297
- Case
- [2002] NSWCA 297
- Decision Date
CaseChat Overview and Summary
The legal issues before the Court of Appeal concerned the validity and effect of a notice to complete served by the Vendors. Specifically, the court had to determine whether a party giving a notice to complete could unilaterally extend the time stipulated in that notice, whether the Purchaser was precluded from terminating the contract due to its own alleged failure to submit a transfer form, and whether the Vendors' failure to disclose the death of a mortgagee and the grant of probate to her executors impacted the validity of the notice to complete. The court also considered whether the Vendors had waived their right to rely on the Purchaser's alleged breach of the transfer submission clause by serving a notice to complete.
The Court of Appeal upheld the primary judge's reasoning. It was held that a notice to complete, once served, binds both parties and cannot be unilaterally extended by the party issuing it. The Vendors' failure to disclose the death of mortgagee Colburt and the grant of probate to her executors, which was information necessary for the form of transfer, constituted a breach of clause 4.2 of the standard contract. This breach meant the Vendors were not entitled to issue a valid notice to complete, as they had not complied with their own obligations under the contract. Furthermore, the court found that by issuing the notice to complete without having complied with clause 4.2, the Vendors had waived any breach by the Purchaser of clause 4.1 concerning the submission of the transfer form.
Consequently, the Purchaser's termination of the contract was deemed effectual. The appeal by the Vendors was dismissed with costs.
Orders
Orders of the court
Appeal dismissed with costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.