Energy Australia v Downer Construction (Australia) Pty Limited and 2 Ors

Link copied
Case Copied 29 min read
CITATION:

Energy Australia v Downer Construction (Australia) Pty Limited & 2 Ors [2005] NSWSC 1042
This decision has been amended. Please see the end of the judgment for a list of the amendments.

HEARING DATE(S): 12/10/05
 
JUDGMENT DATE : 


14 October 2005

JURISDICTION:

Equity Division
Technology and Construction List

JUDGMENT OF:

Barrett J

DECISION:

Application for interlocutory injunction dismissed with costs

CATCHWORDS:

BUILDING AND CONSTRUCTION - progress payments - Building and Construction Industry Security of Payment Act - claim for interlocutory injunction pending hearing of claim for declarations that purported adjudication void and of no effect - serious question to be tried - plaintiff's ability to seek setting aside of any judgment obtained under the Act not prejudiced - balance of convenience favours defendant - interlocutory injunction refused

LEGISLATION CITED:

Building and Construction Industry Security of Payment Act 1999

CASES CITED:

Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Coordinated Construction Company Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140

PARTIES:

Energy Australia - Plaintiff
Downer Construction (Australia) Pty Limited - First Defendant
The Institute of Arbitrators and Mediators Australia - Second Defendant
William Timothy Sullivan - Third Defendant

FILE NUMBER(S):

SC 5508/05

COUNSEL:

Mr C.R.C. Newlinds SC/Mr S.A. Kerr - Plaintiff
Mr G. Inatey SC/Mr W.V. McManus - First Defendant

SOLICITORS:

Mallesons Stephen Jaques - Plaintiff
Corrs Chambers Westgarth - First Defendant
Colin Biggers & Paisley - Second and Third Defendants

LOWER COURT JURISDICTION:

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND
CONSTRUCTION LIST

BARRETT J

FRIDAY 14 OCTOBER 2005

5508/05 ENERGY AUSTRALIA v DOWNER CONSTRUCTION (AUSTRALIA) PTY LTD & ORS

JUDGMENT

1 The plaintiff, which is a statutory authority responsible for the supply of electricity, seeks in these proceedings declaratory relief to the effect that a purported adjudication application by the defendant under the Building and Construction Industry Security of Payment Act 1999 and a purported adjudicator’s determination under that Act are void and of no effect. As an interim measure, it seeks orders restraining the defendant from putting into operation the machinery the Act makes available in consequence of the making of an adjudicator’s determination – machinery which would culminate in the entry of judgment in favour of the defendant and against the plaintiff for the sum produced by the alleged determination.

2 I heard the application for interlocutory relief over most of Wednesday of this week and indicated that I would give judgment this morning, which I now do.

3 The defendant was retained by the plaintiff under a formal contract to construct a tunnel for electricity cables from a point in the south western part of the City of Sydney near Campbell Street to Surry Hills or thereabouts. The work has been completed and, apart from the subject matter of these proceedings and anything that might arise under defects rectification provisions, the state of the account between the parties has been determined and all payments have been made.

4…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Energy Australia v Downer Construction (Australia) Pty Limit... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2005] NSWSC 1042
Decision Date

CaseChat Overview and Summary

Energy Australia brought a claim against Downer Construction (Australia) Pty Limited and two other respondents for an interlocutory injunction to prevent the enforcement of an adjudicator's decision made under the Building and Construction Industry Security of Payment Act. The dispute arose from a construction project where Energy Australia sought declarations that the adjudicator's decision was void and of no effect, as well as an interlocutory injunction to halt any proceedings to enforce the decision until the main claim was resolved. The court had to determine whether there was a serious question to be tried and whether the balance of convenience favoured granting the injunction.

The court considered whether there was a serious question to be tried regarding the validity of the adjudicator's decision. It was noted that Energy Australia had not demonstrated that the adjudicator had no jurisdiction or had acted in bad faith. Additionally, the court examined whether granting the injunction would prejudice Energy Australia's ability to seek setting aside of any judgment obtained under the Act. The court found that Energy Australia could still pursue this remedy, and therefore, its ability to seek setting aside was not prejudiced. The court also weighed the balance of convenience, finding that it favoured the defendants, as there was no demonstrated harm to Energy Australia if the injunction was not granted.

Given the above, the court held that there was no serious question to be tried on the validity of the adjudicator's decision. Furthermore, Energy Australia's ability to seek setting aside of any judgment obtained under the Act was not prejudiced, and the balance of convenience favoured the defendants. Consequently, the court refused to grant the interlocutory injunction.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established