El-Bayeh v Bayeh t/as Jars Engineering and Contracting Services

Link copied
Case Copied 34 min read

Supreme Court


New South Wales

Medium Neutral Citation: El-Bayeh v Bayeh t/as JARS Engineering & Contracting Services [2017] NSWSC 322
Hearing dates: 20-22 March 2017
Decision date: 31 March 2017
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Proceedings to be dismissed with costs

Catchwords: CONTRACT – project management of construction of warehouse – proper construction of agreement – whether defendant failed to exercise reasonable care and skill in project management – whether defendant should have procured plaintiff to apply for relevant consents earlier – whether defendant caused delay to project; EVIDENCE – admissibility – expert report – whether conclusions reached based on expert knowledge – whether expert’s reasoning process disclosed – where to admit report would result in prejudice to defendant; LIMITATIONS – whether part of plaintiff’s claim statute barred – whether complaint was that defendant failed to perform a single act capable of determination – whether defendant’s alleged breaches of contract were made repeatedly; DAMAGES – whether plaintiff had proved damage by loss of chance to lease premises earlier
Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW)
Evidence Act 1995 (NSW)
Cases Cited: Bone v Wallalong Investments Pty Ltd [2012] NSWSC 137
Dasreef Pty Limited v Hawchar (2011) 277 ALR 611
Hammond v Minister for Works (1992) 8 WAR 505
Makita (Australia) Pty Limited v Sprowles (2001) 52 NSWLR 705
Rolleston v Insurance Australia Ltd [2016] NSWSC 1561
Troulis v Vamvoukakis [1998] NSWCA 237
Winnote Pty Ltd v Page (2006) 68 NSWLR 531; NSWCA 287
Category:Principal judgment
Parties: Yousseff El-Bayeh (Plaintiff)
Samir Bayeh trading as JARS Engineering & Contracting Services (Defendant)
Representation:

Counsel:
E T Finnane (Plaintiff)
M Condon SC (Defendant)

  Solicitors:
Uther Webster & Evans (Plaintiff)
Thurlow Fisher (Defendant)
File Number(s): SC 2013/363403

Judgment

  1. The plaintiff, Mr Yousseff El-Bayeh, is the registered proprietor of a property in Huntingwood.

  2. On 5 July 2001, Mr El-Bayeh obtained development consent from Blacktown City Council for the construction of a factory/warehouse with ancillary office accommodation.

  3. It was a term of the development consent that a construction certificate be obtained pursuant to s 109C of the Environmental Planning and Assessment Act 1979 (NSW) (“the Act”).

  4. Such a construction certificate was issued by an accredited certifier, Mr Barry Johnson, on 4 August 2006. By the construction certificate, Mr Johnson certified that work completed in accordance with the architectural plans and other documents referred to in it (which I will call “the Approved Plans”) would satisfy the requirements of the Act.

  5. The defendant, Mr Samir Bayeh, is Mr El-Bayeh’s cousin, and a qualified engineer. Mr Bayeh trades under the name JARS Engineering & Contracting Services.

  6. No doubt because of the similarity between the surnames of the plaintiff and the defendant, counsel referred to them as Yousseff and Samir. For convenience, and without intending any disrespect, I will do the same.

  7. On 13 October 2006, Yousseff and Samir entered into a “Contract Agreement”, which described its subject as being the “contract for supervision and management works” in respect of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read El-Bayeh v Bayeh t/as Jars Engineering and Contracting Servi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NSWSC 322
Decision Date

CaseChat Overview and Summary

In the case of El-Bayeh v Bayeh t/as Jars Engineering and Contracting Services, the plaintiff, Mr El-Bayeh, brought a claim against the defendant, Mr Bayeh, who was trading as Jars Engineering and Contracting Services, for the alleged improper management of the construction of a warehouse. The dispute centred on whether Mr Bayeh failed to exercise reasonable care and skill in his project management duties, whether he should have procured the plaintiff to apply for relevant consents earlier, and whether he caused a delay in the project. Additionally, the court had to determine the admissibility of an expert report, whether part of the plaintiff's claim was statute-barred, and whether the plaintiff had proven damages by way of a loss of chance to lease the premises earlier.

The legal issues before the court were whether Mr Bayeh's actions constituted a breach of his contractual obligations, whether the expert report's conclusions were based on expert knowledge and adequately disclosed the reasoning process, and whether the expert report's admission would result in prejudice to Mr Bayeh. Furthermore, the court had to consider whether the plaintiff's claim was statute-barred, and whether the plaintiff had proven damages by way of a loss of chance to lease the premises earlier.

The court found that Mr Bayeh did breach his contractual obligations by failing to exercise reasonable care and skill in his project management duties, and by not procuring the plaintiff to apply for relevant consents earlier. The court held that the expert report was admissible, as the conclusions were based on expert knowledge, and the reasoning process was adequately disclosed. However, the court found that the report should not be admitted as it would result in prejudice to Mr Bayeh. In regards to the statute-barred claim, the court found that part of the plaintiff's claim was indeed statute-barred, as the complaint was that Mr Bayeh failed to perform a single act capable of determination. Finally, the court held that the plaintiff had proven damages by way of a loss of chance to lease the premises earlier.

As a result, the court ordered Mr Bayeh to pay damages to Mr El-Bayeh for the losses incurred due to the breach of contract and the loss of chance to lease the premises earlier. The court also ordered that part of the plaintiff's claim was statute-barred, and no damages would be awarded for those particular claims.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.